Rules for pricing fencing (wall) and finishing works scaffolding by applying quota line items: the 3.60 m threshold, interior finish / birdcage (full-area) / cradle classification, and regional system differences (railway / Hunan / Jiangsu / Beijing)
Fencing (wall) scaffolding is banded by masonry height: ≤3.60 m by interior scaffolding, above that by the single-row exterior scaffolding item (TB/T 10831-2024; Hunan/Jiangsu likewise use the 3.6 m boundary). Finishing scaffolding by location: interior wall finishing above 3.60 m executes the interior-wall finishing scaffolding item; where the story height exceeds 3.60 m and the ceiling is finished, a birdcage (full-area) scaffold may be added and wall finishing scaffolding is not counted separately (mutually exclusive); exterior cradles by vertical projected exterior wall area without deducting openings; exterior masonry scaffolding beyond 15 m or with finished area over 60% executes double-row. Beijing's quantity-price-fee separation system sets no scaffolding items — priced as non-precisely-measurable preliminary items on a market basis.
Applicable Codes
- TB/T 10831-2024 · Budget Quota of Railway Engineering (Volume 10: Housing Works)
- 湖南2025版《房屋建筑与装饰工程消耗量标准》
- 江苏2026版《建筑与装饰工程消耗量标准》
- 京建法〔2021〕11号(北京市预算消耗量标准计价政策)
Topic Positioning
Rules for pricing fencing (wall) and finishing works scaffolding by applying quota line items (interior wall finishing, ceiling birdcage (full-area) scaffold, exterior cradles, etc.): the 3.60 m masonry-height banding, selection by finishing location, and the basis differences between item-based systems (railway / Hunan / Jiangsu) and Beijing's quantity-price-fee separation system.
Core Conclusions
I. Fencing scaffolding (TB/T 10831-2024 railway Vol. 10 volume notes, original text): "For fencing scaffolding, where the masonry height from ground to wall top is within 3.60 m, calculate by interior scaffolding; where the masonry height exceeds 3.60 m, execute the single-row exterior scaffolding item." Interior scaffolding quantities are calculated by the vertical projected area of the wall face. Jiangsu 2026 edition, same basis: "Where masonry height is within 3.60 m, use interior scaffolding; above 3.60 m, use exterior scaffolding." Systems generally adopt 3.60 m as the interior/exterior boundary.
II. Finishing scaffolding (railway basis):
- Interior wall finishing — "where the interior wall finishing height exceeds 3.60 m, execute the interior-wall finishing scaffolding item"; interior-wall finishing scaffolding is calculated by the vertical projected area of the interior wall face, without deducting door/window openings.
- Ceiling finishing — "where the story height exceeds 3.60 m and the ceiling requires plastering, painting, suspended ceilings or other finishing, a birdcage (full-area) scaffold may be added, and wall finishing scaffolding is not calculated separately" (mutually exclusive for the same location, preventing duplication). The birdcage (full-area) scaffold is calculated by clear indoor area: 3.60–5.20 m counts the basic layer; above 5.20 m, each additional 1.20 m counts one additional layer; height remainders under 0.60 m count as one additional layer × factor 0.50.
- Exterior finishing — where cradles are used, calculated by the vertical projected exterior wall area of the work zone, without deducting door/window openings; cantilever scaffolding suits local finishing of eaves overhangs and similar parts. The choice of exterior masonry scaffolding directly affects the exterior finishing scaffold: eaves masonry height within 15 m uses single-row scaffolding; beyond 15 m, or under 15 m but with exterior door/window and finished area exceeding 60% of the exterior wall surface, the double-row exterior scaffolding item applies; exterior scaffolding already includes ramps, loading platforms, and guard rails — no substitution or extra counting where actuals differ.
- Railway exterior scaffolding items FY-434–439: single-row ≤15 m, double-row ≤15 m / 20 m / 30 m / 50 m, double-row each +10 m, unit 100 m²; fencing beyond 3.60 m executes the single-row exterior scaffolding item (corresponding to FY-434 single-row ≤15 m).
III. Local bases for comparison:
- Hunan 2025 edition: finishing scaffolding includes exterior finishing scaffolding, birdcage (full-area) finishing scaffold, interior-wall finishing scaffolding, and cradles; "wall and ceiling finishing with story height over 3.6 m calculates the corresponding finishing scaffolding"; where interior walls/columns and the ceiling are all finished and the ceiling height exceeds 3.6 m, birdcage (full-area) scaffold costs apply.
- Jiangsu 2026 edition: masonry height within 3.60 m uses interior scaffolding, above that exterior scaffolding; exterior scaffolding is calculated as exterior wall face length (each cantilevered balcony adds one side width) × exterior wall height; interior scaffolding as clear interior wall length × clear interior wall height; exterior wall finishes follow the "exterior wall cladding/hung scaffolding" rules.
IV. Beijing basis (no item system): Beijing's Budget Consumption Standard is a quantity-price-fee separation system — scaffolding (including fencing and finishing scaffolding) has no fee-standard items and belongs to "non-precisely-measurable preliminary items": quantities cannot be precisely calculated from drawing dimensions, costs depend directly on the construction scheme and/or input duration, and pricing is generally per item; the tender price ceiling is estimated by the employer from the measures scheme, or, where Beijing Construction Cost Information publishes fee-index ranges, at no less than the range midpoint; tenderers price independently from their project execution plans.
V. General anti-duplication principle: comprehensive and individual scaffolding are not double-counted; for the same location, birdcage (full-area) scaffold and wall finishing scaffolding are either/or; included ramps, loading platforms, and guard rails are not counted again.
Applicable Boundaries
The railway basis applies to projects adopting TB/T 10831-2024 Vol. 10; the Hunan/Jiangsu bases are same-logic comparisons only — item names, units, and factors follow the current local quota norms (consumption standard) and volume notes of the project location; the Beijing system has no scaffolding items and must not be handled as "applying quota items"; the 3.60 m boundary is a common convention across systems, but local banding and item divisions may differ slightly.
Further Reading
TB/T 10831-2024, Railway Works Budget Quota Manual Vol. 10 Building Works, volume notes (interior wall finishing, addition of birdcage (full-area) scaffold, fencing scaffolding, parapets over 1.20 m using interior scaffolding, etc.) and Chapter 1 civil works, Section 4 "Scaffolding Works" ("V. Individually priced scaffolds", "VI. Method of measurement"; exterior scaffolding items FY-434–439); Hunan 2025 edition Building and Decoration Consumption Standard, scaffolding chapter; Jiangsu 2026 edition Building and Decoration Consumption Standard, scaffolding chapter; Beijing basis see Jing Jian Fa [2021] No. 11 and the "fee index" column of Beijing Construction Cost Information.
Keywords
- 围墙脚手架
- 装饰脚手架
- 内墙面粉饰脚手架
- birdcage (full-area) scaffold
- suspended (cradle) scaffold
- interior scaffolding
- 单排外脚手架
- 3.60m分界