Formwork and scaffolds of retaining walls: formwork by concrete contact area, the consumption of the wall-formwork item, and scaffolds of walls and slopes over 1.2m vertical height by vertical projected area

Formwork computes by the contact area with concrete in m2 (DB11/T 2382-2024 Appendix D Table D.1.31, item D1-7-6 'formwork, retaining wall body', unit m2, work content covering fabrication of formwork and supports, erection, release agent, removal, repair and stacking; per m2 - all-in labour I 0.2080 workdays, steel formwork connectors 0.2380 kg, steel props 0.5580 m, timber 0.0026 m3, release agent 0.0500 kg, nylon caps 4.8208, 4t truck 0.0042 machine-shifts, 8t crane 0.0177 machine-shifts). Cast formwork rules: single holes up to 0.3m2 not deducted and hole side faces not added; over 0.3m2 deducted with the side faces merged in. Scaffolds per SJG 181.2-2024 clause 8.2.4: retaining walls and slopes (over 45 degrees) with vertical height over 1.2m take scaffolds by vertical projected area, one or two faces per the approved execution plan.

Applicable Codes

  • DB11/T 2382-2024 · Standard for Construction Consumption of Construction Works (Beijing) App. D Table D.1.31 子目D1-7-6
  • SJG 181.2-2024 · Consumption Standard for Municipal Works (Volume 2) (Shenzhen) 8.2.4
  • 《湖南2025市政工程消耗量标准》模板工程说明及工程量计算规则

Positioning

How the two preliminaries of municipal retaining walls - formwork and scaffolds - are charged: formwork measurement, the work content and consumption of the wall-formwork item, and the scaffold threshold height and area. For tendering, quantity take-off and audit.

Core conclusions

1. Formwork by contact area with concrete, m2 - not by concrete volume. Rule verbatim: 'Cast concrete formwork computes by the contact area with concrete. Single holes up to 0.3m2 in walls, columns, slabs, caisson and tank walls are not deducted and their side faces not added; single holes over 0.3m2 are deducted with the side-face formwork merged in.' Weep holes and form-tie holes in wall bodies follow the 0.3m2 threshold; the developed area beside tie holes is never added.

2. A dedicated wall item; base and wall formwork apart. DB11/T 2382-2024 Appendix D Table D.1.31:

  • D1-7-6 'formwork, retaining wall body', unit m2, work content 'fabrication of formwork and supports, erection, release agent, removal, repair, stacking etc.'
  • Per m2: all-in labour I (000103010000) 0.2080 workdays; steel connectors 0.2380 kg; steel props 0.5580 m; composite units 1.0140 m; timber 0.0026 m3; nails 0.0190 m / 0.1000 kg; release agent 0.0500 kg; joint sealant 0.3570 kg; nylon caps 4.8208; d100 nylon discs 5.0000; plant - 4t truck 0.0042 machine-shifts, 8t truck crane 0.0177 machine-shifts, other plant 2.0000%.

Base formwork takes the wall-base items, never merged into the body item; the formwork items already cover fabrication, erection, removal, repair, stacking and prop amortisation - no separate support or removal items.

3. Scope and borrowing of the formwork chapter (Hunan 2025 municipal notes): the section serves retaining walls, bridges, tunnels, water-treatment structures and utility tunnels; cast beam and slab formwork includes soffit boards but excludes falsework (charged separately); precast formwork systems include the amortisation of forms, supports and hydraulics; small members are those under 0.05m3 each.

4. Scaffolds: threshold 1.2m, by vertical projected area. SJG 181.2-2024 clause 8.2.4: '4 Retaining walls and slopes (over 45 degrees) with vertical height over 1.2m take scaffolds by vertical projected area; the face(s) scaffolded (one or two) follow the approved execution plan.' The same clause: single / double-row scaffold erection by wall-face horizontal length x masonry height in m2; columnar masonry by structural perimeter + 3.60m x height; scaffold use by area x effective days per 100m2.10days; birdcage scaffolds by actual space volume in m3.

5. Regional bases and conversions: Hunan 2025 municipal: 'slopes using scaffolds take chapter 11 scaffold items', and 'masonry over 1.2m or plastering over 1.5m computes scaffold erection, including ramps and corner platforms' - the 1.2m threshold matches Shenzhen. Wall-formwork consumption does not adjust for the site's forming method (props already averaged); only one-shot water-stop ties per design deduct the sleeve and ironwork contents locally and run the stop-tie and sealing items.

Applicable boundaries

  • Contact-area measurement fits cast members; precast formwork (ground moulds, mats, hollow slabs) has its own rules.
  • The 0.3m2 threshold is per single hole - holes never merge; side faces merge only above the threshold.
  • The 1.2m scaffold threshold and vertical-projection measurement are regional bases; comprehensive and individually priced scaffolds are mutually exclusive (computable gross floor area takes the comprehensive; no double charge per element) - whether walls carry extra scaffolds depends on the local preliminaries setup.
  • The item's consumption data are region-specific - swap local items; never port numbers or contents.
  • Formwork items exclude placing and curing and the extra supports of layered pours over 4m - height effects follow local extra-height items or factors.

Further reading

  • DB11/T 2382-2024 Appendix D Table D.1.31 (D1-7-6 and the adjacent base-formwork items); SJG 181.2-2024 Volume 2 clause 8.2.4 items 1-4; Hunan 2025 municipal formwork notes and rules; DB11/T 2382-2024 clauses 7.1.39~7.1.50 (wall and slope itemisation and concrete measurement).