Choosing the measurement basis for scaffold costs in tender rate build-up for building works (frame-structure office building): comprehensive scaffold by gross floor area versus individually priced scaffolds by vertical projected area / net room area, double-row external scaffold triggers, interior scaffolds and birdcage scaffold for ceilings
Building works whose gross floor area can be computed (including multi-storey frame-structure office buildings) always take the comprehensive scaffold basis first, measured by gross floor area; only projects unsuited to the comprehensive scaffold take the individually priced scaffold basis (external, interior and birdcage scaffolds measured by vertical projected area / net room area) - for the same element the two bases are mutually exclusive and must not be stacked. The external scaffold is measured by the length of the outer face of the external wall (including pilasters and attached shafts) x the external wall height (taken to the top of the parapet where one exists), with no deduction for door and window openings; the double-row item applies where the masonry height exceeds 15m, or is under 15m but door, window and decoration areas exceed 60% of the external wall surface. Interior wall masonry heights (indoor floor to soffit) up to 3.60m take the interior scaffold item (by vertical projected area of the wall face); over 3.60m the single-row external scaffold item applies instead. Where the storey height exceeds 3.60m and the ceiling needs plastering, painting or a suspended finish, a birdcage scaffold may be added (by net room area: the basic layer covers 3.60~5.20m, beyond 5.20m each extra 1.20m is one added layer, a fraction under 0.60m counting as one layer x 0.50), with no further wall-decoration scaffold.
Applicable Codes
- TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程(册说明四、五、六)
- GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准 App. R 措施项目
- 湖南2025版房屋建筑与装饰工程消耗量标准 第十八章 脚手架工程
- 陕西新编消耗量定额(征求意见稿)脚手架工程量计算规则
- 江苏2026版江苏省建筑与装饰工程消耗量 脚手架计算规则
Positioning
The route for taking scaffold costs at the tender rate build-up stage of building works (typically a multi-storey frame-structure office building): first fix the comprehensive-scaffold or individually-priced-scaffold basis by whether the gross floor area can be computed, then pick line items and quantities element by element - external scaffold, interior scaffold, birdcage scaffold. The main rule source is the volume notes of TB/T 10831-2024 (Railway Works Budget Quota, Volume 10: Building Works), checked against the Hunan 2025, Shaanxi new-edition and Jiangsu 2026 consumption standards for building and decoration works.
Core conclusions
1. Fix the route first: computable gross floor area means the comprehensive scaffold
- Hunan 2025, chapter 18 notes: "Wherever the gross floor area can be computed, the comprehensive scaffold line items apply." TB/T 10831-2024 volume note 6(2): "The comprehensive scaffold is computed by gross floor area." A multi-storey frame office building has computable gross floor area, so it is priced on the comprehensive scaffold.
- Individually priced scaffolds apply only where the project is unsuited to the comprehensive scaffold, per TB/T 10831-2024 volume note 5 (same wording in Hunan): "projects unsuited to the comprehensive scaffold may be executed on the corresponding individually priced scaffold items".
- The rate build-up must also match the preliminaries itemisation of the tender BOQ: where the BOQ lists only "comprehensive scaffold", price one item by gross floor area; where the BOQ splits external, interior and birdcage scaffolds into separate items, price each by projected or net area and do not stack the comprehensive scaffold on top. Only one of the two bases may be taken per element - duplicate charging is a high-frequency tender disallowance.
2. Comprehensive scaffold: quantity and included scope
- Quantity = gross floor area. Jiangsu 2026: "The comprehensive scaffold is computed separately for the above-ground and below-ground gross floor area. Within a unit works, areas of different eaves heights and different structural types are computed separately." The eaves height only selects the line-item step; it does not enter the area computation.
- Eaves height definition (TB/T 10831-2024 volume note 6(1)): "The eaves height of a building is taken from the design outdoor ground level to the drip edge of the eaves (for flat roofs the soffit of the roof slab, for sloped roofs the intersection of the outer face of the external wall with the soffit of the sloped roof slab). Stair towers, lift machine rooms, water tank rooms and roof skylights projecting above the main roof do not count towards the eaves height."
- Included (not chargeable separately): 1) scaffolds for external wall masonry and external wall decoration; 2) scaffolds for interior wall masonry, interior wall faces and ceiling decoration within 3.6m; 3) within the vertically enclosed safety netting of the external scaffold - formwork to members, concrete placing, member erection, access ramps, hoist frames for vertical transport, loading platforms and construction safety protection; 4) scaffold costs relating to the building itself within the external scaffold envelope (the skeleton covers members projecting no more than 600mm beyond the external wall).
- Excluded (chargeable separately): protected walkways over footways, temporary cantilevered platforms, personnel crossings and plant protection frames not relating to the building itself; roof frames; arcade scaffolds not counted in gross floor area. Comprehensive scaffolds or integral lifting platforms above a certain scale are settled under dedicated method statements.
3. Element-by-element taking of individually priced scaffolds
- External scaffold rows and quantity: "For the external wall scaffold of a building, where the masonry height from design outdoor ground to eaves is within 15m, compute on the single-row scaffold; where the masonry height exceeds 15m, or is under 15m but door, window and decoration areas exceed 60% of the external wall surface, apply the double-row scaffold line item." The quantity is "computed by the length of the outer face of the external wall (including pilasters and attached shafts) x the external wall height, as area. Where a parapet exists, the external wall height is taken to the top of the parapet"; "in computing internal and external wall scaffolds, no deduction is made for doors, windows, openings and voids. Where a building has different heights, compute separately by height"; the external scaffold already includes ramps, loading platforms and guard rails - no conversion for different actual assemblies. The basement external wall height runs from design outdoor ground to the underside of the base slab bedding (Shaanxi basis).
- Interior wall masonry scaffold: "where the masonry height of an interior wall from design indoor floor to soffit (or half the gable height) is within 3.60m, the interior scaffold line item applies", "the interior scaffold is computed by the vertical projected area of the wall face"; over 3.60m the single-row external scaffold line item applies. The starting threshold varies: Jiangsu 2026 - "any masonry over 1.5m in height requires a scaffold"; railway - for parapets "where the masonry or casting height exceeds 1.20m, the interior scaffold line item applies".
- Ceiling plastering scaffold: within 3.60m already included in the comprehensive scaffold, not taken again; where the storey height exceeds 3.60m and the ceiling needs plastering, painting or a suspended finish, "a birdcage scaffold may be added, and no wall-decoration scaffold is computed separately"; the birdcage scaffold is computed on net room area - 3.60~5.20m is the basic layer, beyond 5.20m each extra 1.20m is one added layer, and a fraction under 0.60m counts as one added layer x 0.50. Placing scaffolds for cast-in-place beams and isolated columns beyond 3.60m, and full steel-pipe falsework for floor slabs, follow volume note 4 with factors (concrete walls: single-row x 0.3; isolated columns and single/continuous beams: double-row x 0.3; floor slabs: birdcage x 0.30).
Applicable boundaries
- Parameters vary with the quota system: the rounding rule for added birdcage layers (railway/Shaanxi: under 0.60m counts a half layer; Hunan rounds), factors for isolated columns and beams (railway x 0.30; Hunan bands by column height into single/double rows without the 0.3 factor), and the basic-layer height of birdcage scaffolds (Jiangsu: basic layer within 8m, one added layer per 2m beyond) all differ - values must follow the current consumption or budget quota of the works location and must not be applied across regions.
- Applies to masonry, decoration and concrete-placing scaffolds in building and decoration works; structures, municipal works, bridges and tunnels have their own bases.
- What the comprehensive scaffold already includes may not be adjusted or charged again even if the actual assembly differs; tender items must match the tender BOQ itemisation - the tenderer must not add or drop preliminaries items on its own.
Further reading
- TB/T 10831-2024 Railway Works Budget Quota Volume 10 Building Works, volume notes 4 (factors for parts over 3.60m), 5 (element-wise application of individually priced scaffolds), 6 (eaves height definition and quantity rules).
- Hunan 2025 consumption standard, chapter 18 scaffold works notes; Shaanxi new consumption quota, scaffold quantity rules; Jiangsu 2026 building and decoration consumption, scaffold computation rules.
- GB/T 50854-2024 Appendix R preliminaries items (scaffolds): "scaffolds" there cover all scaffolds erected during construction per the relevant codes and the needs of the works.
- Related topics: mutual-exclusion audit rules (comprehensive versus individual; birdcage versus wall-decoration), the inclusion boundary (within 3.6m included; over 3.6m charged separately), and regional differences in added-layer rounding.
Keywords
- 脚手架投标组价
- 综合脚手架
- individually priced scaffolds
- 外墙双排脚手架
- interior scaffolding
- birdcage (full-area) scaffold
- gross floor area (GFA)
- 垂直投影面积
- 檐高