Decomposition of the external-wall scaffolding quantity formula: length of the external wall face x external wall height, the single-row and double-row switching criteria (15m masonry height / 60% openings-and-finishes ratio), the no-deduction rule for door and window openings, the 3.60m inside-outside scaffold boundary, and the item tiers FY-434 to FY-439 of the railway quota manual

The external-wall scaffolding quantity S(ext) = length of the external wall face (including pilasters and shafts attached to the wall, with no deduction for door and window openings) x external wall height (up to the top of the parapet where one exists), in m2. Single versus double row is not a multiplier on the area but a switch of quota line item, tiered by 'whether the masonry height from the design ground level to the eaves exceeds 15m' or by 'whether the area of openings and decorative finishes on the external wall exceeds 60% of the external wall surface' (FY-434 single row up to 15m; FY-435, 436, 437 and 438 double row up to 15, 20, 30 and 50m; FY-439 double row per additional 10m; the unit in every case being 100m2). In the whole volume only isolated columns and cast-in-place concrete beams take the double-row external scaffold item with a coefficient of 0.30; where one building has differing heights, each segment must be tiered on its own and summed segment by segment.

Applicable Codes

  • TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程 册说明五、六(一)(三)
  • TB/T 10831-2024 Vol. 10 Ch. 1 土建工程 第四节 脚手架工程 二、单项脚手架 (一)外脚手架 FY-434~FY-439

Positioning

Decomposition of the external-wall scaffolding quantity (railway works basis, TB/T 10831-2024 Volume 10, building works): the area has only two multipliers, 'length of the external wall face x external wall height'; single versus double row is not an area factor but a switch of quota line item by masonry height and openings-and-finishes ratio; door and window openings are never deducted; the boundary between interior and external scaffolds is 3.60m. This card gives the variable table, the tiering chain and the item tiers FY-434 to FY-439.

Core conclusions

1. Formula skeleton: three factors, only two multipliers

S(ext) = L(ext) x H(ext) (m2) which item applies = f(H(masonry), k)

L(ext) and H(ext) are the only multiplier variables; the number of rows (single or double) is determined by H(masonry) and the openings ratio k, which is a change of quota line item, not a coefficient: single-row FY-434 and double-row FY-435 are different item numbers with different base prices, and there is no 'double row = single row x 1.5' conversion. In the whole volume, only isolated columns and cast-in-place concrete beams take a coefficient of 0.30 on the double-row external scaffold item (volume notes VI(III)3 and 4).

2. Variable table

Variable Meaning and valuation rule Source
L(ext) Length of the external wall face, including pilasters and shafts attached to the wall; the widths of door and window openings are not deducted Volume notes VI(III)1 and 2
H(ext) External wall height: from the design outdoor ground level to the drip line of the eaves (on a flat roof, the soffit of the roof slab; on a pitched roof, the intersection of the external wall face with the soffit of the sloping roof); up to the top of the parapet where one exists; stair towers, lift rooms, water tank rooms and roof skylights projecting above the main roof are not counted into the eaves height Volume notes VI(I) and (III)1
H(masonry) (for tiering) Masonry height from the design outdoor ground level to the eaves, used only for the 15m single-row and double-row tiering Volume notes V.1
k (openings-and-finishes ratio) Area of openings and decorative finishes on the external wall / external wall surface area; where k exceeds 60%, the double row applies even where H(masonry) is under 15m Volume notes V.1
Row tier Single row (up to 15m); double row (up to 15m, 20m, 30m, 50m, and per additional 10m) Items FY-434 to FY-439
H(int) (for the inside-outside boundary) Masonry height of internal walls from the design indoor floor to the soffit (or to mid-height of the gable); up to 3.60m, the interior scaffolding applies Volume notes V.3

Corresponding quota line items (Chapter 1, civil works, Section 4, scaffolding works, 2. individual scaffolds, (1) external scaffolds; the unit in every case is 100m2; the working content includes carrying materials, erecting and dismantling scaffolds and toe boards, re-decking as work rises, and stacking materials after dismantling):

  • FY-434 external scaffold, single row, up to 15m
  • FY-435 external scaffold, double row, up to 15m
  • FY-436 external scaffold, double row, up to 20m
  • FY-437 external scaffold, double row, up to 30m
  • FY-438 external scaffold, double row, up to 50m
  • FY-439 external scaffold, double row, per additional 10m

The two 'heights' are of different provenance: tiering uses the eaves masonry height H(masonry), while the measured area uses the external wall height H(ext) (up to the parapet top where one exists). Where there is a parapet the two differ; this is the standard's own basis, not a contradiction, and the same figure must not be used for both.

3. The single-row and double-row tiering chain

The rule, verbatim (volume notes V.1): 'For the external wall scaffold of a building, where the masonry height from the design outdoor ground level to the eaves is within 15m, it is calculated as a single-row scaffold; where the masonry height is beyond 15m, or where the masonry height, though under 15m, comes with openings and decorative finishes on the external wall exceeding 60% of the external wall surface, the double-row scaffold items apply.'

  • H(masonry) over 15m: double row; choose the increment by H(masonry) (up to 20m, 30m, 50m; beyond 50m add FY-439 per additional 10m);
  • H(masonry) no more than 15m and k no more than 60%: single row, FY-434;
  • H(masonry) no more than 15m but k over 60%: double row (at the up-to-15m tier, i.e. FY-435).

4. Deduction rule for door and window openings: no deduction on any basis

The rule, verbatim (volume notes VI(III)2): 'In calculating internal and external wall scaffolds, no deduction is made for the areas occupied by doors, windows, openings, voids and the like. Where a single building has differing heights, each height is calculated separately.'

Same-basis extensions (likewise 'no deduction' or no extra deduction):

  • Suspended (cradle) scaffolds are calculated on the vertical projection area of the external wall over the work zone, without deduction for door and window openings (VI(III)6);
  • Internal-wall finish scaffolds are calculated on the vertical projection area of the internal wall face, without deduction for door and window openings (VI(III)7);
  • Interior scaffolding is calculated on the vertical projection area of the wall (VI(III)8).

'Where a single building has differing heights, calculate each height separately' is a mandatory segmentation requirement; for multiple segments the formula expands to S(ext) = the sum over all segments of (L(ext,i) x H(ext,i)), each segment being tiered on its own H(masonry,i) and k,i; neither an average height nor the highest tier applied once is permissible.

5. The boundary between interior scaffolding and external scaffolds

  • Internal wall masonry: where the masonry height from the design indoor floor to the soffit (or to mid-height of the gable) is no more than 3.60m, the interior scaffolding items apply (V.3); above 3.60m, finishes to internal walls take the internal-wall finish scaffold items (volume notes IV(2)).
  • Parapets: where the masonry or casting height exceeds 1.20m, the interior scaffolding items apply (IV(5)).
  • Fences: where the masonry height from ground to the top of the fence is no more than 3.60m, calculate as interior scaffolding; above 3.60m the single-row external scaffold items apply (V.6).
  • Stone masonry walls: where the masonry height exceeds 1.20m, the external scaffold items apply (V.7); where large equipment foundations stand over 1.20m above ground, the double-row external scaffold items apply (V.8).

Boundaries of application

  • Applies only to external-wall parts unsuited to comprehensive scaffolding and charged as individual scaffolds (volume notes V: items unsuited to comprehensive scaffolding may take the corresponding individual scaffold items); where gross floor area can be computed, comprehensive scaffolding still applies (calculated on gross floor area); comprehensive and individual are mutually exclusive for the same part and must not both be charged.
  • The tiering height and the measured height are two bases: where there is a parapet, the quantity runs to the parapet top while tiering still uses the eaves masonry height; the two are not interchangeable.
  • No uniform conversion coefficient exists between single and double rows; only isolated columns (structural perimeter plus 3.60m, times the height) and cast-in-place concrete beams (height from beam top to ground or floor, times the clear beam length) take the double-row external scaffold items with coefficient 0.30.
  • Local consumption quota manuals differ; the development method and boundary values for external scaffolds follow the current local standard: Shaanxi takes the total length of the external wall face including projections and recesses (including projecting balconies) times the height; in Jiangsu, masonry up to 3.60m high uses interior scaffolding and above 3.60m external scaffolds, and where the external wall has cantilevered balconies each balcony contributes one side width to the external wall length, two adjoining balconies counting as one side only.
  • Item base prices adjust with the quota edition and the regional rules; set them from the current edition before pricing. This card lists no base-price figures.

Further reading

  • TB/T 10831-2024, Railway Works Budget Quota Manual, Volume 10, building works: volume notes V (application of individual scaffolds by part), VI(I) and (III) (eaves-height definition and quantity rules), IV (loading and conversion rules for parts above 3.60m).
  • The same manual, Chapter 1, civil works, Section 4, scaffolding works, 2. individual scaffolds, (1) external scaffolds: FY-434 (single row, up to 15m), FY-435 (double row, up to 15m), FY-436 (up to 20m), FY-437 (up to 30m), FY-438 (up to 50m), FY-439 (per additional 10m), unit 100m2.
  • Local comparisons: the scaffolding measurement rules of the Shaanxi new consumption quota exposure draft; the scaffolding chapter of the Jiangsu 2026 building and decoration consumption quota (the cantilevered-balcony side-width rule).