The height boundary, quantity bases and base-layer / additional-layer computation of interior scaffolding and birdcage scaffolds (TB/T 10831-2024 and the Shaanxi, Hunan, Jiangsu and other local quota differences)

Interior scaffolding measures on vertical wall projection without deducting door and window openings, applying to masonry up to 3.60 m (internal walls from floor to soffit, or half the gable); birdcage scaffolds measure on clear room area, 3.60-5.20 m taking the base layer, each extra 1.20 m one additional layer, remainders under 0.60 m one layer x 0.50; where storeys over 3.60 m need ceiling finishing and a birdcage scaffold is added, wall finishing scaffolds are not counted again.

Applicable Codes

  • TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程
  • SJG 111.2-2022 城市地下综合管廊工程消耗量标准(Vol. 2 管廊建筑与装饰工程)
  • 陕西省2024消耗量定额(征求意见稿)
  • 湖南省2025版房屋建筑与装饰工程消耗量标准
  • 江苏省2026版建筑与装饰工程消耗量定额

Scope of the question

Interior and birdcage scaffolds are both individual scaffolds (scaffolding splits into comprehensive and individual; items unsuited to comprehensive scaffolding take the relevant individual items). This card gathers their applicability tests, height boundaries, quantity bases and base / additional-layer computation, with the railway and local differences - for budgeting, measurement and compliance checks.

Core conclusions

  1. Interior scaffolding Scope (TB/T 10831-2024 Volume 10 Buildings):
  • Internal-wall masonry from the design floor to soffit (or half the gable height) within 3.60 m takes interior scaffold items.
  • Parapet masonry or casting over 1.20 m takes interior scaffold items.
  • Roof chimneys with masonry over 1.20 m: area = drawn chimney perimeter + 3.60 m x the height above the roof, interior scaffold items.
  • Duct walls and brick foundations over 1.20 m: area = drawn masonry length x height, interior scaffold items.
  • Boundary walls: floor-to-top masonry within 3.60 m by interior scaffolds; beyond, single-row external scaffolds. Measurement: interior scaffolds on vertical wall projection; internal and external wall scaffolds deduct no doors, windows, openings or voids; differing heights in one building compute separately. Local: Shaanxi (2024 draft) likewise vertical wall projection, no deductions. Jiangsu (2026): internal-wall scaffolds on net length x net height (the same projection basis), gables to half the apex, basements from the basement floor to wall top; masonry within 3.60 m interior, beyond external. SJG 111.2-2022 (utility tunnels): single and double-row scaffolds on horizontal wall-edge length x height in m2, columns on drawn perimeter + 3.60 m x height, mobile decoration scaffolds on wall area.
  1. Birdcage scaffolds Scope: where storeys over 3.60 m need ceiling plastering, painting or ceilings, a birdcage scaffold may be added with no wall finishing scaffold (TB/T 10831-2024 notes). Where high or heavy beam-slab formwork needs full steel-pipe falsework, the falsework quota applies without further high-placing charges. Measurement (railway and Shaanxi): clear room area; height 3.60-5.20 m takes the base layer; above 5.20 m, each 1.20 m one additional layer; remainders under 0.60 m one layer x 0.50. Additional layers = (clear height - 5.2 m) / 1.2 m. Shaanxi adds: no deduction for columns, piers or attached chimneys; mobile scaffolds on clear floor area, no deduction for columns, piers or partitions. Local differences (always execute the current local quota):
  • Hunan (2025): actually erected horizontal projection, no deduction for attached columns; base layer 3.6 m up to 5.2 m; beyond 5.2 m one layer per 1.2 m, layers = (storey height - 5.2) / 1.2 rounded to integer; where birdcage scaffolds count, internal wall decoration takes no decoration scaffold, only a re-erection fee on wall projection (rate per local quota). Decoration external scaffolds on centre line x wall height, no deduction for openings, eaves 5-24 m (beyond 24 m per special scheme).
  • Jiangsu (2026): ceiling plastering over 3.60 m on clear room area, no deductions; base layer within 8 m; beyond, one layer per 2 m, decimals under 0.6 dropped, over carried; height floor (or slab) to ceiling or roof-soffit (sloping on mean height); ceiling plastering within 3.60 m on the plastered ceiling area (columns and beams undeducted); where birdcage scaffolds serve, wall, column and beam plastering scaffolds drop.
  • SJG 111.2-2022 (tunnels): ceiling finishing and repair scaffolds on clear area between main walls; birdcage scaffolds on erected clear area.

Applicability limits

  • This card is quota measurement and pricing, not scaffolding safety standards - erection, design and acceptance follow the safety codes.
  • Interior and birdcage scaffolds are individual scaffolds, exclusive of comprehensive scaffolding - no double counting; once a birdcage scaffold counts for ceilings over 3.60 m, wall finishing scaffolds drop for that part (mutually exclusive).
  • Height boundaries: interior scaffolds bounded by masonry / finishing height 3.60 m (floor to soffit or half gable), beyond which external scaffolds; birdcage by ceiling finishing height 3.60 m, under which none.
  • Base / additional banding differs markedly: railway and Shaanxi 3.60-5.20 m base + 1.20 m steps + 0.60 m x 0.50; Jiangsu 8 m base + 2 m steps + 0.6 rounding; Hunan rounds to integers. No cross-system application.
  • Birdcage scaffolds (access) and full steel-pipe falsework (load-bearing) are not priced alike.
  • Eaves height runs from outside ground to the drip (flat roofs: slab soffit; pitched: the intersection of outer wall and roof soffit); roof-level stair rooms, lift rooms, tanks and skylights excluded.

Further reading

  • TB/T 10831-2024 Volume 10 volume notes and Chapter 1 Section 4 scaffolding works (item 2 individual scaffolds - birdcage and full falsework, internal finishing scaffolds, units 100 m2 / 100 m3; item 6 quantity rules, paragraph 3).
  • Shaanxi 2024 draft scaffolding rules; Hunan 2025 scaffolding rules; Jiangsu 2026 scaffolding rules; SJG 111.2-2022 Volume 2, 8.2.3 preliminaries.