Railway 2024 quota Volume 10 building works (TB/T 10831-2024): scope, contents, and the volume attribution of external appurtenances (fences/roads/drainage ditches)
TB/T 10831-2024 Volume 10 "applies to works related to railway buildings"; column-free platform canopies count floor area by the horizontal projection of the outer edge, cantilevered platform canopies bounded by the station building's external wall line by projection; otherwise per GB 55031; telecom repeater/base/signal relay stations take labor and plant x 1.25 under this volume. In the TB 10801-2024 Appendix A chapters, building external appurtenances form "IV. building appurtenance works" (earthworks, retaining walls and slope protection, roads and hardened surfaces, fences with gates, heat-network piping, chimneys, greening, others including drainage ditches); by quota items: fences, retaining walls/slope protection, aprons, outdoor block paving, and brick trenches are in this volume; concrete/asphalt/clay-bound gravel pavements and cast-in-place drainage channels are not (they sit in Volume 13 station yard works or Volume 1 subgrade).
Applicable Codes
- TB/T 10831—2024 铁路工程预算定额 Vol. 10 房屋工程
- TB 10801—2024 铁路基本建设工程设计概(预)算编制办法 App. A
- GB 55031 民用建筑通用规范
Topic Positioning
The scope and contents of TB/T 10831-2024 Volume 10 (building works), and the attribution of building external appurtenances (fences, roads, drainage ditches, retaining walls, etc.) across the railway 2024 volumes — "which work uses Volume 10, which goes elsewhere".
Core Conclusions
1. Scope (volume note as written): this volume applies to works related to railway buildings. Companion boundaries: (1) floor area — column-free platform canopies by the horizontal projection of the outer edge without deducting structurally open areas; cantilevered platform canopies bounded by the station building's external wall line, by projection, into the canopy area; otherwise per GB 55031 "General code for civil buildings". (2) Telecom repeater stations, base stations, and signal relay stations: labor and plant x 1.25 under this volume. (3) Concrete members are compiled with ready-mixed concrete. (4) Boiler, oil tank, and sodium-ion softener installation per Volume 12 TB/T 10834 (locomotive/car/machinery works) items.
2. Estimate chapter calibers (TB 10801-2024 Appendix A): external appurtenances form a separate "IV. building appurtenant works" chapter: earthworks; retaining walls and slope protection (dry stone / mortared stone / concrete / RC); roads and hardened surfaces (concrete / asphalt / clay-bound gravel / block paving / hardened surface); fences (with gates; solid / open / metal); heat-network piping (pipes / trenches); chimneys (including outdoor flues bounded by the external wall, excluding wall-attached chimneys; brick / RC / steel); greening (excluding spoil-ground treatment greening); others (drainage ditches, locomotive/car inspection trenches).
3. Quota-item calibers (Volume 10 vs others):
- Fences: in this volume. Masonry rules: "fence height to the top of the capping (or its underside where there is a concrete cap); fence posts merge into the fence volume".
- Retaining walls and slope protection: in this volume (masonry works).
- Roads: partly. This volume covers aprons and outdoor ground paving attached to buildings; concrete, asphalt, and clay-bound gravel pavement items are not here — they belong to Volume 13 station yard works "roads, hardened surfaces and tree (flower) pools".
- Drainage ditches: brick ditches may use this volume's masonry trench items; cast-in-place concrete channels are not here — Volume 13 (cast-in-place drainage channels) or Volume 1 subgrade (ditches).
Applicable Boundaries
- For the railway 2024 system (TB/T 10831-2024 and TB 10801-2024); not old or other-sector quotas.
- Whether an item is in the volume follows the volume/chapter notes; the estimate chapter table (Appendix A) and quota-volume attribution are two calibers — compile as "estimate chapter goes to 'IV. building appurtenant works'; quota items follow the volume correspondence".
- Comprehensive scaffolding does not apply to structures and appurtenances; fences etc. need separate item scaffolding.
- Wall-attached chimneys, ventilation ducts, and refuse chutes use the sundry masonry items, not the chimney chapter; masonry guide walls are computed separately.
Further Reading
- TB/T 10831-2024 Volume 10 notes; three chapters: Chapter 1 civil works (masonry; concrete and RC; repairs), Chapter 2 decoration, Chapter 3 building services; appendix of concrete/mortar mix tables.
- TB 10801-2024 Appendix A "IV. building appurtenant works".
- GB 55031 — floor areas otherwise follow this code.
- Boundaries: Volume 13 TB/T 10834-2024 (roads, hardened surfaces, cast-in-place drainage channels), Volume 1 TB/T 10822-2024 (ditches), Volume 12 (boilers, oil tanks, softeners).
Keywords
- railway works budget quota manual (China Railway)
- 第十册
- building works
- TB/T 10831
- 房屋附属工程
- 围墙
- 排水沟
- 概预算章节表