Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Diaphragm-wall guide walls: construction and detailing requirements per GB 51004-2015 clause 6.6.2, with key parameters compared across local codes

Per GB 51004-2015 "Code for construction of building foundation works" clause 6.6.2: guide walls shall be cast-in-place reinforced concrete, strength grade not below C20, thickness not less than 200 mm; top surface 100 mm above ground and at least 0.5 m above the groundwater table; bottom keyed at least 200 mm into undisturbed soil; height not less than 1.2 m; inner faces vertical with clear spacing 40 mm wider than the design wall thickness; outer side backfilled with cohesive soil; cast symmetrically, forms stripped only at 70% design strength and struts added (horizontal spacing preferably 1.5-2 m, one row top and bottom); over unfavorable geology such as buried creeks or miscellaneous fill, ground improvement (e.g. triple-axis deep soil-mixing (cement) columns) or deep guide walls is preferred. Local codes differ slightly in clear-spacing allowance (30-60 mm), embedment (1.0-2.0 m) and height above groundwater (0.5-1.5 m); where the design is silent, follow the national code.

Applicable Codes

  • GB 51004-2015 建筑地基基础工程施工规范 第6.6.2条
  • DBJ/T 15-20-2016 建筑基坑工程技术规程 第9.2.1条
  • DBJ/T 15-152-2019 建筑地基基础施工规范 第24.3.2条及Table 24.3.2
  • DB62/T 25-3111-2016 建筑基坑工程技术规程 第11.3.4条
  • DB11/T 1526-2018 地下连续墙施工技术规程 第4.1.2条
  • SJG 05-2020 基坑支护技术标准 第8.3.2条
  • DB/T 29-103-2018 天津市钢筋混凝土地下连续墙施工技术规程 第5.0.1条
  • CJJ 2-2008 城市桥梁工程施工与质量验收规范 第10.5.3条
  • T/ZCEAS 1002-2022 预制-现浇咬合地下连续墙技术规程 第5.5.10条

Topic Positioning

Before trenching for a diaphragm wall, guide walls must be built along both sides of the wall line. This card consolidates guide-wall construction and detailing requirements: primary basis GB 51004-2015 "Code for construction of building foundation works" clause 6.6.2, with key parameters compared against Guangdong DBJ/T 15-20-2016 and DBJ/T 15-152-2019, Gansu DB62/T 25-3111-2016, Beijing DB11/T 1526-2018, Shenzhen SJG 05-2020, Tianjin DB/T 29-103-2018, industry code CJJ 2-2008 and T/ZCEAS 1002-2022 — for design value selection, preparation of construction method statements and clause checking.

Core Conclusions

1. Primary basis: GB 51004-2015 clause 6.6.2 (national code) Diaphragm-wall construction shall install reinforced-concrete guide walls conforming to:

  1. Guide walls shall be cast-in-place concrete, strength grade not below C20, thickness not less than 200 mm;
  2. The top surface shall be 100 mm above ground and at least 0.5 m above the groundwater table; the bottom shall enter undisturbed soil by at least 200 mm; height not less than 1.2 m;
  3. The outer side shall be backfilled solid with cohesive soil; the inner faces shall be vertical, with clear spacing 40 mm wider than the design wall thickness;
  4. Concrete shall be cast symmetrically; strip forms only at 70% design strength and add struts between walls after stripping;
  5. Over unfavorable geology (buried creeks, miscellaneous fill), ground improvement or deep guide walls are preferred. Commentary additions: 100 mm above the working ground prevents surface water entering the trench; at least 0.5 m above groundwater maintains slurry pressure on the trench walls (wall-stabilizing); founding on undisturbed soil keeps trench-wall stability and vertical capacity adequate for construction loads; 40 mm wider than the panel width eases trenching-machine operation; struts (horizontal spacing preferably 1.5-2 m, one row top and bottom) shall be installed immediately after stripping until panel excavation; in buried-creek areas or loose miscellaneous fill, the soil on both sides may be improved beforehand and the guide-wall base deepened into undisturbed soil, preferably by triple-axis deep soil-mixing (cement) columns.

2. Guide-wall forms Common forms are inverted-L, "[", and C shapes, selected per soil conditions (DBJ/T 15-20-2016 clause 9.2.1; DBJ/T 15-152-2019 clause 24.3.2); where the soil below the guide wall is poor, C-shaped guide walls are preferred (DB62/T 25-3111-2016 clause 11.3.4). The Tianjin code adds that the guide-wall toe length should be 200-300 mm.

3. Key parameters compared across codes

  • Concrete strength: all codes "not below C20" (SJG 05-2020 and CJJ 2-2008 worded "preferably not below C20").
  • Thickness: national code and both Guangdong codes >=200 mm; SJG 05-2020 150-200 mm; Tianjin 200-300 mm.
  • Clear spacing (widened vs wall thickness): national code +40 mm; both Guangdong codes, Gansu and CJJ 2-2008 +40-60 mm; Shenzhen +30-50 mm; T/ZCEAS 1002-2022 30-50 mm.
  • Embedment/depth: national code — bottom into undisturbed soil >=200 mm, height >=1.2 m; both Guangdong codes depth 1.5-2.0 m; Gansu embedment preferably >=1.5 m with base preferably >=200 mm below the wall's design top; Shenzhen embedment preferably >=1.5 m; Tianjin depth 1.5-2.0 m (into undisturbed soil >=300 mm); CJJ 2-2008 bottom embedded preferably >1 m into soil; T/ZCEAS 1002-2022 height >=1.3 m, base preferably into undisturbed or improved soil >=200 mm.
  • Top elevation: national code 100 mm above ground and >=0.5 m above groundwater; both Guangdong codes >=100 mm above ground and, respectively, 1.5 m (DBJ/T 15-20-2016) and 1 m (DBJ/T 15-152-2019) above groundwater; Tianjin slurry level >=1.0 m above groundwater, and in coastal areas >=1.5 m above the highest tide; T/ZCEAS 1002-2022 top >=500 mm above groundwater and preferably above ground.
  • Struts between walls: national code horizontal spacing 1.5-2 m, one row top and bottom; Gansu horizontal 1500-2000 mm, vertical 800-1200 mm; Shenzhen preferably upper and lower rows of timber props about every 1 m; CJJ 2-2008 spacing preferably 1-1.5 m; both Guangdong codes: add struts promptly after stripping.
  • Reinforcement: Gansu two-way rebar 8-16 mm dia @150-200; Shenzhen 12 mm @200 both ways, horizontal bars made continuous; T/ZCEAS 1002-2022 main bars HRB400 or above, diameter >=12 mm, spacing <=200 mm; DBJ/T 15-20-2016 preferably structural reinforcement, single-layer allowed in good soil (on the underside of the flange and inner face of the web).
  • Tolerances: SJG 05-2020 guide-wall longitudinal axis +/-10 mm; other tolerance items in DBJ/T 15-152-2019 Table 24.3.2.

4. Functions and craft points The guide wall is key to diaphragm-wall quality; its functions: survey datum and trenching guide; slurry storage and level stabilization to keep trench walls stable; preventing collapse at the trench mouth; and a working platform bearing the trenching rig, jacking/extraction of joint pipes and boxes, reinforcement cages and the concreting platform — its strength and stability must suit the trenching rig and joint-pipe extraction (DB62/T 25-3111-2016, DB/T 29-103-2018, DB11/T 1526-2018). Guide walls shall sit on dense undisturbed soil; machine-cutting the guide trench must never overcut and disturb the soil; where loose miscellaneous fill within 500 mm below the guide-wall design depth is met, remove it and backfill compacted with lime- or clay-stabilized soil; beyond 500 mm, improve the ground (vibratory compaction, deep cement mixing, high-pressure jet grouting, grouting, triple-axis mixing etc., depth per geology, minimum 7 m) so the guide wall sits on dense firm strata. As a temporary structure, the guide wall is demolished and removed after wall construction (DB/T 29-103-2018); in coastal areas fully allow for tidal action.

Applicable Boundaries

  • This card targets cast-in-place reinforced-concrete guide walls (temporary works) for diaphragm-wall construction; precast concrete and steel guide walls (reusable, currently mainly for rectangular bored-pile works) are outside its scope (DB/T 29-103-2018).
  • Code values differ (clear-spacing allowance 30-60 mm; above groundwater 0.5-1.5 m; embedment 1.0-2.0 m etc.); execution follows the design documents; where design is silent, use the national code GB 51004-2015.
  • The specific tolerance table (width, verticality, top flatness, plan position, top elevation) is DBJ/T 15-152-2019 Table 24.3.2 — check that table; not expanded item by item here.
  • Strut the walls after stripping until panel excavation; keep heavy plant and material stacks off the ground behind the walls; consider steel plates for plant travel per soil conditions to prevent guide-wall displacement and deformation (SJG 05-2020).

Further Reading

  • National: GB 51004-2015 "Code for construction of building foundation works" clause 6.6.2 and commentary (five provisions on guide-wall construction).
  • Local/industry codes: DBJ/T 15-20-2016 "Technical regulation for building excavation engineering" clause 9.2.1 (guide-wall design); DBJ/T 15-152-2019 "Code for construction of building foundations" clause 24.3.2 and Table 24.3.2 (tolerances); DB62/T 25-3111-2016 "Technical regulation for building excavation engineering" clause 11.3.4 and Fig. 11.3.4 (forms and detailing); DB11/T 1526-2018 "Technical specification for diaphragm wall construction" clause 4.1.2 (structural types and functions); SJG 05-2020 "Standard for excavation support" clause 8.3.2; DB/T 29-103-2018 "Tianjin technical specification for reinforced-concrete diaphragm walls" clause 5.0.1 (including ground-improvement methods and tidal effects); CJJ 2-2008 "Code for construction and quality acceptance of city bridge works" clause 10.5.3; T/ZCEAS 1002-2022 "Technical regulation for precast-cast-in-place interlocking diaphragm walls" clause 5.5.10 (guide-wall detailing).
  • Ground improvement under guide walls over unfavorable geology commonly uses triple-axis deep soil-mixing (cement) columns; their construction speed and per-rig 24 h advance limits are in GB 51004-2015 clauses 4.10.2 and 4.10.3.

Keywords