Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Pile foundation pricing: general rules on whether empty bore, rock socketing, slurry, reinforcement cages, and pile head trimming are priced separately

Empty bore is not listed separately: boring is measured over the full hole depth (including the empty section), and only the concrete material is deducted as-is for the empty section; rock socketing, reinforcement cages, and pile head trimming/cutting are priced separately — rock socketing by actual socket depth × design pile-diameter cross-sectional area, counting only moderately to slightly weathered rock; slurry preparation and on-site transport are included in the boring item, off-site hauling is separate; for precast square/tubular piles, head trimming is already included as an allowance and not counted again.

Applicable Codes

  • GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准
  • GB/T 50861-2024 城市轨道交通工程工程量计算标准
  • SJG 111.1-2022 城市地下综合管廊工程消耗量标准
  • TB/T 10823-2024 铁路工程预算定额 Vol. 2 桥涵工程
  • TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程

Topic Positioning

This card answers the classic pricing-scope question in pile foundation works: whether the five cost types — empty bore, rock socketing, slurry, reinforcement cage, and pile head trimming/cutting — should be priced separately, at both the BOQ measurement and quota pricing levels, across national, railway, and local standards.

Core Conclusions

  • Empty bore: not listed separately. Boring is measured over the full hole depth (including the empty section) against the boring item, with no pricing distinction between empty and concrete-filled sections; for the empty section only the concrete material is deducted as actually absent, and empty-hole backfilling is included in the bored pile work content.
  • Rock socketing: priced separately. A separate rock-socketing surcharge item applies, calculated as actual socket depth × design pile-diameter cross-sectional area; only moderately and slightly weathered rock counts — fully and highly weathered rock does not.
  • Slurry: preparation and on-site transport are included in the boring item; off-site hauling of slurry (drill spoil) is a separate item — the national standard requires listing it under the relevant ground-treatment item codes in Appendix B, and the railway companion quota computes it by drilled volume V = 0.25πD²H.
  • Reinforcement cage: priced separately. Fabrication and installation are listed separately under rebar works against the reinforcement-cage quota, not included in the boring/concrete items.
  • Pile head trimming/cutting: priced separately. Apply the dedicated concrete pile-head breaking item (graded by pile diameter), with head spoil hauling counted separately; for precast square piles and tubular piles the quota already includes a head-trimming allowance — not counted again.

Applicable Boundaries

  • The above is the general pricing scope; implementation follows the current local quota and BOQ standard of the project location (e.g., Shenzhen SJG 111.1-2022 differs slightly from the national standard in details of empty-bore material adjustment).
  • Precast and bored piles are treated differently for head trimming: precast piles include the allowance — not counted again.
  • The bore-depth starting point varies with construction conditions: from ground level on land, from the riverbed surface on water, from the built-up island surface for islands; where a pipe column serves as casing, the embedded depth of the pipe column must be deducted.

Further Reading

  • National standards: GB/T 50854-2024 Appendix C (Table C.2.1 bored piles, C.3.13 slurry hauling items); GB/T 50861-2024 Appendix B.9.1 pile foundations (empty bore length, reinforcement cage listing).
  • Railway: TB/T 10823-2024 bridges and culverts volume notes (drilling depth and pile concrete calculation rules, ring-cut pile head items QY-229–231); TB/T 10831-2024 buildings (pile head cutting/trimming FY-185–189).
  • Shenzhen: SJG 111.1-2022 Clauses 3.1.2, 3.1.4 (empty-bore drilling, rock-socketing surcharge, slurry transport).

Keywords

  • 桩基工程
  • 空桩
  • 空孔
  • 入岩增加费
  • 泥浆外运
  • 钢筋笼
  • pile head cropping
  • 另行计价
  • 灌注桩

Cited By