Engineering Knowledge Cards.
Confidence HighUpdated 2026-10-18

Criteria for the additional charge for penetrating rock with bored piles (two routes: by rock hardness or by degree of weathering), whether strongly, moderately or slightly weathered rock counts as rock penetration, and how the rock quantity is measured and the line items banded

Whether rock penetration is charged depends on the local quota's criterion route: under the rock-hardness route (Beijing DB11/T 2382-2024 clause 4.4.1 item 4, pointing to GB/T 50218 - penetrating comparatively soft rock, comparatively hard rock etc.), a strongly weathered zone counts only if tested saturated uniaxial compressive strength falls at comparatively soft rock or above; under the weathering-degree route (Shenzhen SJG 111.1-2022 clause 3.1.4 item 4), 'moderately and slightly weathered rock are distinguished; fully and strongly weathered rock is not counted as rock penetration'. The additional charge is measured by design (actual) penetration depth x the pile cross-sectional area, in volume; line items band by rig type + design pile diameter (and rock class), not by penetration depth; the railway bridge and culvert volume sets no separate rock charge - hole-boring items are banded directly by stratum.

Applicable Codes

  • DB11/T 2382-2024 · Standard for Construction Consumption of Construction Works (Beijing) 第4.4节桩基工程
  • SJG 111.1-2022 · Consumption Standard for Urban Utility Tunnel Works (Shenzhen) 第3.1.4条、第3.2.2条
  • GB/T 50218《工程岩体分级标准》岩石分类表
  • GB 50007-2011《建筑地基基础设计规范》表4.1.3 岩石坚硬程度划分
  • TB 10077-2019《铁路工程岩土分类标准》表3.1.1、表3.1.2
  • TB/T 10823-2024 · Budget Quota of Railway Engineering (Volume 2: Bridge and Culvert Works) 册说明第四节(表2 钻孔地层分类表)
  • TB/T 10831-2024 · Budget Quota of Railway Engineering (Volume 10: Housing Works) Ch. 1第二节 灌注桩成孔子目 FY-143~FY-158
  • 湖南 2025 版《房屋建筑与装饰工程消耗量标准》桩基章说明第(1)~(5)款
  • 陕西新编消耗量定额征求意见稿 灌注桩工程量计算规则
  • https://www.tj.gov.cn/zwgk/szfgb/qk/2010/14_3215/202005/t20200520_2475058.html

Positioning

This card answers three pricing questions on the "additional charge for penetrating rock" with bored piles: by what standard rock entry is judged, whether strongly, moderately or slightly weathered rock counts as rock, how the rock quantity is measured and by what dimension the line items are banded. For BOQ preparation, quota rate build-up and settlement disputes where the pile toe enters rock.

Core conclusions

1. Three criterion routes exist - first identify which one the project executes

Route A (by rock hardness, the mainstream): Beijing DB11/T 2382-2024 Construction Consumption Standard, clause 4.4.1 item 4 - "Where the design drawings of rotary-bored cast-in-place piles require entry into rock strata, the corresponding rock-entry items apply; rock entry follows the cases of penetrating comparatively soft rock, comparatively hard rock etc. in the rock classification table of GB/T 50218, Standard for Engineering Rock Mass Classification." Banded by saturated uniaxial compressive strength frk, the threshold sits at comparatively soft rock and above: hard rock frk over 60MPa; comparatively hard rock 60 down to 30MPa; comparatively soft rock 30 down to 15MPa; soft rock 15 down to 5MPa; very soft rock frk up to 5MPa (GB/T 50218; GB 50007-2011 Table 4.1.3 hardness classes).

Route B (by weathering degree): Shenzhen SJG 111.1-2022 Consumption Standard for Urban Utility Tunnel Works (Volume 1), clause 3.1.4 item 4 - "Where the design requires entry into rock, the rock-penetration additional-charge items apply. The charge distinguishes moderately and slightly weathered rock; fully and strongly weathered rock is not counted as rock penetration."

Route C (railway: no separate rock charge, banded by stratum): TB/T 10823-2024 Railway Works Budget Quota Volume 2 (bridges and culverts) bands bored-pile items by stratum in volume note 4; in its Table 2 "bored-pile stratum classification", the "soil" class includes "soil-like weathered rock" and the "soft rock" class is "soft rocks of all kinds with saturated uniaxial compressive strength up to 30MPa ... strongly weathered magmatic rock and granite gneiss" - strongly weathered siltstone usually falls in the "soft rock" class, with no separate rock charge. But TB/T 10831-2024 Volume 10 (building works) of the same system does set "rock-entry addition" items (rotary rigs FY-146~148, rotary-bored rigs FY-152~154, impact rigs FY-157~158, unit 10m3) - the two volumes differ and must not be mixed.

2. Weathering degree versus "counts as rock" (key: weathering is only a name, not a hardness class)

  • Fully weathered: not rock. Excluded expressly in Shenzhen; "soil" class on the railway (soil-like weathered rock); TB 10077-2019 Table 3.1.1 puts "fully weathered rocks of all kinds" in very soft rock.
  • Strongly weathered: generally not rock (Shenzhen expressly excludes it); but not absolute - the same TB 10077-2019 Table 3.1.1 states that "strongly weathered very hard rock" ranks as comparatively soft rock, "weakly to strongly weathered hard rock" as soft rock, and "strongly weathered soft rock" as very soft rock. Under the strength route (Route A), a strongly weathered zone with tested frk over 15MPa (comparatively soft rock or above) still counts as rock.
  • Moderately weathered, slightly weathered / unweathered: counts as rock. Express in Shenzhen ("distinguishing moderately and slightly weathered rock"); strength generally reaches comparatively soft rock or above.

Conclusion: whether a toe penetrating 1.5m into strongly weathered siltstone attracts the charge cannot be read off the words "strongly weathered" alone - under the Shenzhen-type weathering route, never; under the Beijing-type strength route, only if the ground investigation shows saturated uniaxial compressive strength over 15MPa; on the railway bridge volume it merges into the "soft rock" stratum class with no separate charge.

3. Quantity: by volume, soil and rock measured separately

  • Rock-penetration charge quantity = design (actual) penetration depth x pile cross-sectional area, in volume (m3). Shenzhen SJG 111.1-2022 clause 3.2.2 item 1: "the rock-penetration charge is computed by the design penetration depth x the design pile cross-sectional area, in cubic metres"; the Shaanxi new consumption quota draft states the same ("rock-entry item quantity = actual penetration depth x design pile cross-sectional area, in volume").
  • Boring and rock entry measured in batches: Beijing DB11/T 2382-2024 clause 4.4.7 - "rotary-bored pile hole-boring quantities are computed by the design pile cross-sectional area x the boring length through soil and through rock respectively, in volume"; concrete is placed by "design pile cross-sectional area x design effective pile length including the toe plus the over-casting length", in volume. In Shenzhen clause 3.2.2 item 1 the boring depth starts at the pre-driving natural ground level to the design pile toe level.
  • Related bases: Beijing clauses 4.4.2 and 4.4.1 item 1 - the over-consumption coefficient of cast-in-place / rotary-bored piles is per the drawings, or taken at 1.15 where the design is silent; clauses 4.4.3~4.4.5 - boring items exclude earth and rock haulage and off-site slurry transport and exclude rebar cages; pile-head cropping items exclude head haulage; each follows its own chapter.

4. Banding dimensions: rig type + pile diameter, not penetration depth

  • The railway building volume's rock-entry items band by design pile diameter: rotary rig FY-146 (up to 800) / FY-147 (up to 1200) / FY-148 (up to 1500); rotary-bored FY-152 (up to 1000) / FY-153 (up to 1500) / FY-154 (up to 2000); impact rigs FY-157 (up to 1000) / FY-158 (up to 1500), all per 10m3; the boring items (FY-143~FY-174) stack rig type x diameter band x stratum band.
  • The rock items are compiled against a benchmark rock class: a different actual class is corrected by factor, not by adding depth bands. Hunan 2025 pile-foundation chapter notes: "the rotary-bored rock-entry items all assume soft rock; with comparatively soft rock multiply the soft-rock item by 2.00, with comparatively hard rock by 3.00. The impact-rig rock-entry items assume comparatively soft rock; with soft rock multiply by 0.70, with comparatively hard rock by 1.50. Very hard rock or karst interlayers are computed separately." The same standard also deducts slurry materials and the slurry pump / mortar mixer machine-shifts where rotary-bored or impact boring needs no slurry support.
  • Shenzhen SJG 111.1-2022 clause 3.1.4 adds: the full-rotary casing pile items suit diameters up to 2m and single pile lengths up to 35m; for lengths over 35m up to 45m, labour and plant are x 1.20; the steel casing item is amortised, and where the casing cannot be extracted the consumption may be adjusted after site confirmation.

Applicable boundaries

  • Judging and charging follow the contract and the current consumption standard / quota of the project location; the three routes must not be cross-mixed - in particular the railway bridge volume (no rock charge, stratum bands) and the railway building volume (rock-entry items, diameter bands) must not be swapped.
  • Route A presupposes that the drawings expressly "require entry into rock strata"; where the design is silent, the ordinary boring items apply. The rock zone must be supported by the ground investigation / design documents (rock name, weathering, saturated uniaxial compressive strength), not by borehole logs alone.
  • Strongly weathered very hard rock and weakly-to-strongly weathered hard rock may classify as comparatively soft rock and soft rock respectively, so "strongly weathered = no rock charge" holds only in weathering-route regions and must not be applied across regions.
  • Hunan's 2.00/3.00 and 0.70/1.50 factors apply only to the benchmark rock class of the rotary-bored and impact rock-entry items, not to other rig types or other regions.
  • Rock and soil zones are measured in layers: the full pile length must not be priced on rock-entry items, and the empty bore must not be double-counted.

Further reading

  • Beijing DB11/T 2382-2024 clause set 4.4 pile foundations: 4.4.1 (over-consumption 1.15, casing amortised 2m, dry-boring deducts bentonite and slurry pump x 0.90, rock entry per GB/T 50218), 4.4.2~4.4.5 (coefficients, exclusions of haulage and cages), 4.4.7 (soil/rock layered measurement), 4.4.11 (head cropping by over-cast length x design area).
  • Shenzhen SJG 111.1-2022 clauses 3.1.4 (wet boring includes slurry making, excludes slurry transport and steel casing; rock entry distinguishes moderate/slight weathering; casing amortisation; over-consumption) and 3.2.2 (quantity rules).
  • Hunan 2025 pile-foundation chapter notes (1)~(5) (rotary rigs on rotary-bored items, slurry conversion, rock-class factors, impact rigs in sand-gravel / cobble).
  • Shaanxi new consumption quota draft, cast-in-place pile quantity rules (rock-entry item = actual penetration depth x design pile area).
  • Railway: TB/T 10823-2024 Volume 2 note 4 (hole depth definition, Table 2 stratum classes, adjustment over 50m); TB/T 10831-2024 Volume 10 chapter 1 section 2 boring items FY-143~FY-174.
  • Rock classification: GB/T 50218 rock classification table; GB 50007-2011 Table 4.1.3 (five hardness classes by frk); TB 10077-2019 Tables 3.1.1 and 3.1.2.
  • Public government text for verification: https://www.tj.gov.cn/zwgk/szfgb/qk/2010/14_3215/202005/t20200520_2475058.html

Keywords

  • 入岩增加费
  • 入岩判定标准
  • 强风化 中风化 微风化 入岩
  • 岩石坚硬程度 较软岩
  • 饱和单轴抗压强度
  • 灌注桩成孔工程量计算
  • DB11/T 2382-2024
  • SJG 111.1-2022