Concrete over-consumption coefficients and wastage rates for railway bored/cast-in-place piles: TB/T 10823-2024 bridge volume (+1m, no over-break, no over-consumption coefficient) vs TB/T 10831-2024 buildings volume (coefficients 1.15-1.30) and TB/T 10821-2024 cast-in-place concrete wastage rate 2%
Two regimes in the 2024 railway quotas: (1) bridge bored piles (TB/T 10823-2024): priced concrete = (design length + 1m) x design shaft area; "over-break shall not be included in the quantity" - no over-consumption coefficient; pile-head over-grout ring-cut removal priced separately per pile. (2) Building piles (TB/T 10831-2024): material contents already include over-consumption coefficient and wastage - impact-hole rigs 1.30, rotary/percussion 1.25, rotary/auger 1.20, driven-tube 1.15. (3) Site handling/operation wastage of concrete (TB/T 10821-2024 appendix): cast-in-place 2%, precast 1%; material consumption = priced volume x (1 + wastage rate).
Applicable Codes
- TB/T 10823-2024 铁路工程预算定额 Vol. 2 桥涵工程
- TB/T 10821-2024 铁路工程基本定额
- TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程
Topic Positioning
Pricing and wastage rules for bored/cast-in-place pile concrete under the 2024 railway quota system: how the pour quantity is measured (over-grout height, over-consumption coefficient or not) and what material wastage rate applies - for bridge bored piles and building piles, and to avoid misapplying over-consumption coefficients across volumes.
Core Conclusions
I. Bridge bored piles (TB/T 10823-2024 Vol.2 Bridges, Ch.1 substructure, Sec.4 bored and hand-dug piles):
- Priced quantity per volume notes Article 11 method of measurement rule 2, original: "shaft concrete is measured as design length (top to bottom) plus 1m times the design shaft area; over-break shall not be included." That is, priced concrete = (design length + 1m) x shaft area. The +1m is over-grout (compensating laitance and sediment at the head); removal is priced separately by the ring-cut item per pile count (that item excludes hauling off the cut head - reference rock haul).
- No over-consumption coefficient multiplier in this volume: over-break (actual over-consumption) may not enter the priced quantity; the pour item excludes the concrete itself (unpriced material listed separately), its quantity computed with the basic-quota wastage rate.
- Slurry and cuttings haul measured by bore volume: V = 0.25 x pi x D^2 x H (D - design diameter, H - depth).
II. Concrete wastage rate (TB/T 10821-2024 Basic Quota appendix "site handling and operation wastage rates", applied by all railway volumes except buildings): cast-in-place concrete 2%, precast 1%; the same table has rebar and splices (round phi<10 and phi>=10 welded 1.5%, mechanical 1%), cement 2%, sand 2%, crushed stone 2%, etc. So shaft concrete material consumption = priced volume x (1 + 2%).
III. Railway building piles (TB/T 10831-2024 Vol.10 Buildings, "piles and ground foundation works"): material contents already include the over-consumption coefficient and wastage, taken by hole-forming method: impact-hole rigs 1.30; rotary and percussion rigs 1.25; rotary/auger rigs 1.20; driven-tube rigs 1.15. Pour quantity = design shaft area x design length (incl. tip) plus over-grout length (0.50m if design is silent). The volume also sets: empty-bore backfill per "loose fill" items; gravel backfill per "gravel spreading" x 0.70; grout-pipe installation per toe grouting, lateral grouting x 1.20 on labor and machinery.
IV. Practice: bridge bored-pile concrete = (length + 1m) x area x 1.02 (with wastage) - no additional over-consumption coefficient; where the contract settles by measurement (procurement/reconciliation), actual over-consumption belongs to contract/site management, separate from quota pricing - align bases when reconciling (drawing theory vs mixer-truck loads).
Applicable Boundaries
- Only the 2024 railway system (TB/T 10823-2024, TB/T 10821-2024, TB/T 10831-2024); 2017 and earlier volumes have their own rules - verify against those originals.
- "+1m" applies only to bridge bored-pile shaft concrete; hand-dug piles in the same volume measure top-to-bottom length x area excluding lining concrete (lined separately) at full-depth items.
- The building over-consumption coefficient table (1.15-1.30) applies only to that volume's pile items; bridge bored piles have no multiplier - the two volumes must not be mixed.
- The 2% is "site handling and operation" wastage, excluding off-site transport wastage; wastage already inside quota items is not to be double-counted.
- Over-grout concrete cost sits in the +1m quantity; ring-cut removal is per-pile and excludes haul-off.
Further Reading
- TB/T 10823-2024 Vol.2: notes Article 11 (depth, +1m, over-water platforms extended 2.5/3.5/5m, casing by design weight, ring-cut per pile), Article 1 (stratum/depth factors), large-diameter (>=2.5m) swaps (cancel vessels; <=20t mast crane swapped to 50t crawler); hole items QY-88~147, pour items QY-202~209, ring-cut QY-229~231.
- TB/T 10821-2024 appendix wastage table.
- TB/T 10831-2024 Vol.10: over-consumption coefficient table, filler piles 1.30 and sand-gravel compaction 1.334, triaxial mixing cement 18% of 1800 kg/m3, diaphragm and sheet-pile rules.
Keywords
- concrete over-consumption coefficient (bored piles)
- bored piles
- 灌注桩
- 混凝土损耗率
- railway works budget quota manual (China Railway)
- TB/T 10823-2024
- TB/T 10821-2024
- TB/T 10831-2024