concrete over-consumption coefficient (bored piles)
- 01
Cost treatment of re-drilling after borehole collapse in cast-in-place piling: attribution of rework responsibility (employer cause / contractor cause / adverse physical conditions), the on-site confirmation evidence chain, the measurable cost heads, responsibility for concrete over-consumption coefficient excesses, and the 28-day claim procedure
Whether the cost of re-drilling after collapse can be measured depends o…
GB/T 50500-2024 建设工程工程量清单计价标准 第7.1.4条、第7.6.4条、第8.11.3条GB/T 51262-2017 建设工程造价鉴定规范 第5.8.4条GB/T 50319-2013 建设工程监理规范 第5.2.11条及Table A.0.62026-10-29 - 02
Judging reasonable variance between purchased ready-mix concrete volume and theoretical drawing quantity (quota loss-rate yardstick)
Use the quota wastage rate as the yardstick: a purchased volume exceedin…
T/HNCT 001-2022 湖南省建筑工程绿色施工评价标准技术细则DBJ/T 15-83-2017 广东省绿色建筑评价标准DB62/T 3081-2018 绿色建筑施工与验收规范2026-09-25 - 03
Soil nail grouting water-cement ratio and re-grouting control: calibers of JGJ 120-2012 / DB11 489-2016 / DBJ/T 15-70-2021 / JGJ 167-2009
The control indicator of soil nail grouting is the water-cement ratio (w…
JGJ 120-2012 建筑基坑支护技术规程 第5.4.5条DB11 489-2016 建筑基坑支护技术规程 第6.3.14条DBJ/T 15-70-2021 土钉支护技术规程 第6.8.3条2026-09-25 - 04
Concrete over-consumption coefficients and wastage rates for railway bored/cast-in-place piles: TB/T 10823-2024 bridge volume (+1m, no over-break, no over-consumption coefficient) vs TB/T 10831-2024 buildings volume (coefficients 1.15-1.30) and TB/T 10821-2024 cast-in-place concrete wastage rate 2%
Two regimes in the 2024 railway quotas: (1) bridge bored piles (TB/T 108…
TB/T 10823-2024 铁路工程预算定额 Vol. 2 桥涵工程TB/T 10821-2024 铁路工程基本定额TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程2026-09-25