Soil nail grouting water-cement ratio and re-grouting control: calibers of JGJ 120-2012 / DB11 489-2016 / DBJ/T 15-70-2021 / JGJ 167-2009
The control indicator of soil nail grouting is the water-cement ratio (water to cement by weight): neat cement grout preferably 0.5-0.55 (JGJ 120-2012 cl. 5.4.5; DB11 489-2016 cl. 6.3.14); cement mortar 0.4-0.45 with cement-sand ratio 0.5-1.0 and medium-coarse sand with mud content <=3% (JGJ 120-2012); Guangdong DBJ/T 15-70-2021 relaxes neat grout to 0.5-0.6. Grouting uses the bottom-of-hole method: pipe end not more than 200mm (JGJ 120-2012; DBJ/T 15-70-2021) or 250-500mm (DB11 489-2016; JGJ 167-2009) from the bottom, outlet always submerged, stop when fresh grout overflows at the mouth; re-grout when the level drops; repeatedly in leaky strata (fill, sand-gravel); gravity grouting re-fill 1-2 times before initial set; pressure grouting hold 3-5min after filling, filling coefficient over 1.
Applicable Codes
- JGJ 120-2012 建筑基坑支护技术规程 第5.4.5条
- DB11 489-2016 建筑基坑支护技术规程 第6.3.14条
- DBJ/T 15-70-2021 土钉支护技术规程 第6.8.3条
- JGJ 167-2009 湿陷性黄土地区建筑基坑工程安全技术规程 第6.4.6条
Topic Positioning
Grout mix (water-cement ratio) and re-grouting control of soil nails (rebar nails and driven steel-pipe nails), consolidating four codes — JGJ 120-2012 cl. 5.4.5, DB11 489-2016 cl. 6.3.14, DBJ/T 15-70-2021 cl. 6.8.3, JGJ 167-2009 cl. 6.4.6 — for reuse in schemes, disclosure and site grouting quality control.
Core Conclusions
Terminology: the current control indicator is the "water-cement ratio" (water to cement by weight); with fly ash etc. it is in substance a water-binder ratio — in technical disclosures and schemes, state it as "water-cement ratio" to align with the codes.
I. Water-cement ratio (by weight):
- Neat cement grout preferably 0.5-0.55 (JGJ 120-2012 cl. 5.4.5 item 1; DB11 489-2016 cl. 6.3.14 item 1);
- Cement mortar: water-cement ratio preferably 0.4-0.45, cement-sand ratio 0.5-1.0, medium-coarse sand with mud content by weight not over 3% (JGJ 120-2012 cl. 5.4.5 item 1);
- Guangdong DBJ/T 15-70-2021 cl. 6.8.3 item 1: neat grout, water-cement ratio preferably 0.5-0.6;
- Site control: weigh the water; spot-check with a mud balance; grout or mortar shall be uniformly mixed and used before initial set (JGJ 120-2012 cl. 5.4.5 item 2; JGJ 167-2009 cl. 6.4.6 item 3 same: mix and use promptly, finish before initial set).
II. Grouting method (bottom-of-hole, precondition):
- Before grouting, clear residual loose soil from the hole (JGJ 120-2012 item 3; JGJ 167-2009 item 1 "residual or loosened soil"; DB11 489-2016 item 2 "residual and loosened waste soil");
- Grouting shall insert the pipe to the hole bottom and inject from there, pipe end not more than 200mm from the bottom; during grouting and withdrawal the outlet shall stay submerged; stop after fresh grout overflows at the mouth (JGJ 120-2012 item 4; DBJ/T 15-70-2021 item 4 same: to within 200mm of the bottom, outward grouting, outlet submerged during withdrawal);
- DB11 489-2016 item 3 and JGJ 167-2009 item 2: insert the pipe to 250-500mm from the bottom; a packer and vent pipe at the mouth are recommended; grout while withdrawing as overflow appears.
III. Re-grouting control:
- After grouting, re-grout when the grout level drops (JGJ 120-2012 item 4); promptly when it drops markedly (DB11 489-2016 item 3); top up at the mouth in due time (DBJ/T 15-70-2021 item 5);
- In leak-prone fill and sand-gravel strata, re-grout repeatedly to ensure fullness (DB11 489-2016 item 3);
- Gravity grouting: re-fill 1-2 times after filling, before initial set (JGJ 167-2009 item 2);
- Pressure grouting (packed off): hold pressure 3-5min after filling; grout over-consumption coefficient over 1 (JGJ 167-2009 item 2; DBJ/T 15-70-2021 bottom method same: pressurize top-up after packing, done when pressure holds 3-5min);
- When grouting starts after or stops for over 30min, lubricate pump and lines with water or thin grout (DB11 489-2016 item 5);
- Below the water table, seal the hole mouth (DBJ/T 15-70-2021 item 6).
Applicable Boundaries
- For grouting quality control of rebar nails and driven steel-pipe nails; anchor (strand) grouting and jet grouting are governed elsewhere.
- The ratios are "preferably" intervals; actual mixes by trial; grout strength and fullness verified through grout-volume records (theoretical vs actual) and concealed-work acceptance.
- Local standards (Beijing DB11 489-2016; Guangdong DBJ/T 15-70-2021) govern their regions; JGJ 120-2012 is the nationwide industry caliber; on conflict, the project's governing basis prevails.
- DBJ/T 15-70-2021 deleted mouth grouting and recommends bottom grouting (pipe sent with the nail, outlet about 0.2m from the bottom) — follow current valid procedures, not the deleted old method.
Further Reading
- JGJ 120-2012 cl. 5.4.5: four items on rebar nail grouting (hole formation, fabrication and grouting are key quality links distilled from experience);
- DB11 489-2016 cl. 6.3.14: rebar nail grouting (incl. >30min interruption lubrication; repeated top-up in leaky strata);
- DBJ/T 15-70-2021 cl. 6.8.3: six items + bottom-grouting method (background of deleting mouth grouting);
- JGJ 167-2009 cl. 6.4.6: nail grouting (incl. grout over-consumption coefficient >1; spacers at <=2m; main bar centered).