Soil improvement for undercrossing existing railways: treatment extent, hole-layout parameters, and construction requirements of grouting and jet-grouting columns
Where the soil ahead of the jacking face cannot remain stable, grout for improvement first: when crossing a railway, the top grouted zone should be no thinner than 2-5 tunnel diameters and extend longitudinally over the full subgrade-load range; grout diffusion radius preferably 3-5 m; goaf hole spacing 5-20 m and karst 3-10 m, holes sequenced from large to small spacing; the jet-grouting treatment extent should be no smaller than the foundation base, extending to the embankment fill slope toe for embankments, with column spacing 2-4 diameters and column diameter 500-1500 mm; where groundwater stands above 1 m below the base, dewatering is required and jacking with water is strictly forbidden; grouting near existing buildings/structures must control pressure and intensify deformation monitoring.
Applicable Codes
- TB 10106-2023 铁路工程地基处理技术规程
- TB 10303-2020 铁路桥涵工程施工安全技术规程
- DB14/T 2399-2022 大涌水量隧道工程高聚物注浆技术规程
- TB 10751-2018 高速铁路路基工程施工质量验收标准
Topic Positioning
This card covers pre-construction improvement of the subgrade soil for undercrossing existing railways (pipe jacking/tunneling/bridge jacking) — treatment extents, hole-layout parameters, and construction requirements of grouting and jet-grouting columns, for improvement scheme design and compliance review.
Core Conclusions
Where the soil ahead of the jacking face cannot be ensured stable, it should be grouted first (TB 10303-2020 Clause 17.2.13); soil improvement is required when crossing railways (CJJ/T 74-2020 Clause 7.2.1).
- Grouting extent: when a tunnel crosses a railway, the longitudinal extent should cover the subgrade-load range, the cross-section may be square or horseshoe-shaped, and the top grouted zone should be no thinner than 2-5 times the tunnel (pipe) diameter (DB14/T 2399-2022 Clause 5.4.2, where the experience value for tunnels with large water inflow may be referenced); grout diffusion radius preferably 3-5 m (TB 10106-2023 Clause 21.2.6).
- Hole layout: grout holes sequenced with spacing from large to small; three sequences for large goaf areas; goaf hole spacing preferably 5-20 m and karst 3-10 m, with curtain holes preferably on the periphery (21.2.2, 21.2.3); grouting pressure is set comprehensively by grouting purpose, geological conditions, and impact on the surroundings (21.2.7).
- Jet-grouting columns: the treatment extent should be no smaller than the foundation base, preferably extending to the embankment fill slope toe for embankments and suitably widened for rigid foundations; column spacing preferably 2-4 column diameters, column diameter 500-1500 mm, column length penetrating the soft soil stratum (12.2.1-12.2.4).
- Dewatering: where groundwater stands above 1 m below the frame-bridge foundation base, dewatering is required and jacking with water is strictly forbidden; in soft-soil, sand, and silt areas with abundant groundwater, cutoff structures shall be provided (TB 10303-2020 Clause 17.2.14).
- Process control: grouting follows "probe combined with grouting" and process control; grouting near existing buildings/structures must control grouting pressure and intensify deformation monitoring; effectiveness is evaluated comprehensively by geophysical prospecting, water-pressure tests, and borehole coring (TB 10106-2023 Clauses 21.1.5-21.1.8, Section 21.4).
Applicable Boundaries
This card is the "soil (subgrade-level) improvement" standard; "track (rail-level) reinforcement" is on another card. Most values are design experience ranges; formal works must set parameters through workmanship trials/test columns (Clause 21.1.4). Applies to improvement of operating-line and near-operating-line subgrades; the work must proceed under track closure or slow-speed conditions, with constant monitoring of changes in the subgrade, traffic equipment, and surrounding buildings/structures (TB 10302-2020 Section 13.4).
Further Reading
See TB 10106-2023 "Technical Code for Ground Improvement of Railway Engineering", Section 12.2 (jet-grouting column design) and Sections 21.1-21.4 (grouting); TB 10303-2020 Clauses 17.2.13-17.2.14; DB14/T 2399-2022 Clause 5.4.2; jet-grouting quality acceptance for high-speed railways: TB 10751-2018 Section 5.13.