Railway 2024 quota rules for measuring grouting strengthening: measured by design grout volume (10 m3) with handling of over-injection (TB/T 10831-2024 Volume 10, FY-293~296)
In the railway 2024 quota system (TB/T 10831-2024 Volume 10 building works, FY-293~296), the "grouting" quota line items of grouting strengthening are measured by grout volume (unit 10 m3), the volume being computed from the design strengthening zone rather than the slurry actually pumped on site: where the drawings show the zone by point layout, the diffusion radius is half the hole spacing and the computation plane is formed by offsetting the layout boundary lines outward by that radius; where grout points lie between bored piles, the volume is that of cylinders with diffusion radius half the hole spacing. "Boring" is measured per design depth in 100 m. Actual grout take exceeding the design quantity is not adjusted directly: normal construction losses are already included in the quota and are not paid extra; where geological conditions differ from design and make the design quantity too small, the design-change procedure applies (TB 10106-2023 clause 21.1.5); over-consumption attributable to the contractor is not measured.
Applicable Codes
- TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程
- TB/T 10822-2024 铁路工程预算定额 Vol. 1 路基工程
- TB 10106-2023 铁路工程地基处理技术规程
- TB 10801-2024 铁路基本建设工程设计概(预)算编制办法
Topic Positioning
Measurement caliber of the grouting-strengthening quota line items in the railway 2024 quota system (TB/T 10831-2024 Volume 10 building works, effective 1 January 2025): grouting is measured by the grout volume of the design strengthening zone rather than the slurry actually pumped on site, together with the principles for handling the case where actual grout take exceeds the design quantity.
Core Conclusions
- Item location and composition: grouting strengthening appears in TB/T 10831-2024 "Railway works budget quota manual, Volume 10: building works", Chapter 1 civil works, Section 2 piles and foundation works, "6. grouting strengthening", with 4 quota line items — FY-293 layered grouting, boring (100 m); FY-294 layered grouting, grouting (10 m3); FY-295 compaction grouting, boring (100 m); FY-296 compaction grouting, grouting (10 m3). Work content: setting out, boring, injecting walling slurry, preparing grout, inserting grouting core pipes, grouting, and checking the grouting effect. Note: Chapter 3 ground treatment of Volume 1 subgrade works (TB/T 10822-2024) contains only strengthening piles and similar items, with no grouting items — within the railway 2024 quota, grouting-strengthening items appear only in the building works volume.
- Measurement method: the grouting quota line items are measured by grout volume (unit 10 m3), the volume computed from the design strengthening zone, not from the slurry actually pumped on site; boring is measured per design depth in 100 m.
- Grout-volume rules (as written in the volume notes): "Where the design drawings show the soil-strengthening zone by point layout, take half the hole spacing as the diffusion radius, add the diffusion radius beyond each layout boundary line to form the computation plane, and compute the grout volume"; "where the design drawings place grout points between bored piles, take half the hole spacing as the diffusion radius of each hole and compute the grout volume as that cylinder volume".
- Three principles for actual grout take exceeding the design quantity: (1) normal construction fluctuation is not paid extra — quota material consumptions include both net use and losses (including site haulage and operational losses); the material costs of FY-294/296 already include normal losses; (2) where geological conditions differ from design and make the design grout quantity too small — this is a design-parameter adjustment handled through the design-change procedure: TB 10106-2023 "Technical regulation for ground treatment of railway works", clause 21.1.5, "grouting shall follow the principles of combining probing with grouting and of process control, adjusting the relevant design and construction parameters and the grouting technique in light of the geological features revealed by probing and construction"; once approved, the quantities are adjusted as a variation, with costs compiled on the compilation principles, quota norms and fee standards of the originally approved estimate; (3) contractor-caused over-consumption (loss of control over grout mix proportions, wastage from excessive grouting pressure, etc.) — not measured, and the cost is borne by the contractor.
- The same principle of "measure by design quantity, with process factors not payable extra" also appears in adjacent chapters: the ground-treatment chapter of TB/T 10822-2024 Volume 1 provides that "the quantities of all ground-strengthening piles are computed by the design length from pile top to pile tip as shown on the drawings; where measured by volume, by that length multiplied by the design pile-diameter cross-sectional area. Hole enlargement, reservations and other process factors during construction are not paid extra"; test piles are measured per the design documents.
Applicable Boundaries
Applies to the preparation of estimates and budgets and to final account review under the railway 2024 quota system (the 13 budget quota manuals accompanying TB 10801-2024, effective 1 January 2025, which simultaneously abolished TZJ 1001-2017 and 20 other old standards); the measurement caliber addressed here covers quota line items FY-293~296. Where the contract or tender documents separately agree a grouting measurement method (for example, actual grout take certified through site records) together with conditions for certifying over-injection, the agreed terms prevail. Other quota systems (municipal, building) adopt similar grouting measurement calibers (for example Shenzhen SJG 111.1-2022: where the design specifies the grout take per hole, measure it by the volume shown on the drawings; where not specified, measure the soil-strengthening grout quantity), but each must be applied under its own quota system, and the systems must not be mixed. At budget stage, the grout volume should be computed from the design strengthening zone and the quota line items applied accordingly; an "expected over-injection allowance" should not be added in advance.
Further Reading
- TB/T 10831-2024 "Railway works budget quota manual, Volume 10: building works": volume notes (original grout-volume computation rules); Chapter 1 Section 2 "6. grouting strengthening" quota line item tables FY-293~296.
- TB/T 10822-2024 "Railway works budget quota manual, Volume 1: subgrade works", Chapter 3 ground treatment, chapter notes (strengthening-pile measurement rules; for the portions drilled but not grouted, labour and plant multiplied by 0.5, etc.).
- TB 10106-2023 "Technical regulation for ground treatment of railway works", clause 21.1.5 (principle of combining probing with grouting and of process control).
- TB 10801-2024 "Measures for compiling design estimates (budgets) of railway capital construction projects" (published by National Railway Administration Announcement No. 28 of 2024, effective 1 January 2025).