Routing grouting items when existing-line strengthening uses grouting under the 2024 railway budget quotas: the bridges and culverts volume's existing-line strengthening and protection items exclude grouting; grouting routes by location and slurry type to the subgrade volume's underground cavity treatment, the buildings volume's grouting reinforcement and the tunnel volume's mining-method support items
The existing-line strengthening and protection items of TB/T 10823-2024 Volume 2 Bridges and Culverts (QY-843 to QY-846, banded by strengthening length up to 5 m / 7 m x timber / concrete sleeper sections, unit per track) have work content limited to hoisted rail beam erection and removal, sleeper replacement, track dressing and ballast topping-up and track protection (concrete-sleeper sections adding reinstatement of reinforced concrete sleepers) - no grouting. Grouting in existing-line strengthening routes separately by location plus slurry type: subgrade / underground cavities under TB/T 10822-2024 Volume 1 Chapter 7 underground cavity treatment (drilling LY-443-446; grouting LY-447 cement mortar, LY-449 sleeve-valve cement grout, LY-448 sleeve-valve cement-silicate double slurry 1:0.8); general soil under TB/T 10831-2024 Volume 10 grouting reinforcement (layered grouting FY-293/294, compaction grouting FY-295/296); tunnel locations under TB/T 10824-2024 Volume 3 mining-method tunnel support (advance-support grouting SY-119/120, advance reinforcement SY-123-129, perimeter reinforcement SY-130-132, surface reinforcement SY-133-137). Drilling and grouting are separate paired items; double-slurry items carry far higher material shares than plain cement grout.
Applicable Codes
- TB/T 10822-2024 铁路工程预算定额 Vol. 1 路基工程(Ch. 7 地下洞穴处理)
- TB/T 10823-2024 铁路工程预算定额 Vol. 2 桥涵工程(Ch. 4 涵洞工程 既有线加固及防护)
- TB/T 10824-2024 铁路工程预算定额 Vol. 3 隧道工程(Ch. 1 矿山法隧道 第三节 支护)
- TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程(注浆加固)
Scope of the question
A frequent application question under the 2024 railway budget quota system: when existing-line strengthening (underpasses, jacking, defect treatment) is designed with grouting, which volume and chapter apply, and each item's work-content boundary. The conclusion: the existing-line strengthening chapter itself excludes grouting; grouting routes across volumes by location plus slurry type.
Core conclusions
1. The bridges and culverts volume's existing-line strengthening and protection chapter excludes grouting. TB/T 10823-2024 Volume 2 Bridges and Culverts, Chapter 4 culverts, Section 3 circular culverts - reinforced concrete circular culvert jacking - (3) existing-line strengthening and protection, items QY-843 to QY-846 banded by strengthening length (m) up to 5 / 7 x timber / concrete sleeper sections, unit per track. Work content, source: timber sections - hoisted rail beam erection and removal, sleeper replacement, track dressing and ballast topping-up, track protection; reinforced concrete sleeper sections - adding conversion of RC sleepers to timber and reinstatement. The chapter covers only track (permanent way) strengthening and protection; grouting is outside its work content and must be applied per location, never double-counted against grouting items.
2. Routing by grouting location and slurry type (item numbers, names, units)
(1) Subgrade / underground cavities - TB/T 10822-2024 Volume 1 Roadbed Works, Chapter 7 underground cavity treatment:
- 1, drilling: LY-443 soil, LY-444 soft rock, LY-445 moderately hard rock, LY-446 hard rock, unit 100 m; work content: rig positioning, drilling, shifting.
- 2, grouting: LY-447 cement mortar (10 m3), LY-449 sleeve-valve grouting with cement grout (10 m3), LY-448 sleeve-valve grouting with cement-silicate double slurry 1:0.8 (10 m3). Work content, source: the cement mortar item - cement mortar, including mortar mixing and grouting; the sleeve-valve items - including making and injecting the sleeve-shell material, installing sleeve-valve pipes and grouting mandrels, slurry making, grouting, hole sealing.
- Slurry materials by reference to HT-931 M30 cement mortar (grade 42.5 cement, medium-coarse sand), unit m3.
- Volume notes (Part 2 chapter notes, Chapter 7) points: 1 this chapter covers drilling and grouting; 2 the grouting quota is compiled on cement mortar - other slurry types may be substituted where designed; 3 the cavity grouting and surface cement-silicate items are used in tandem with the drilling items; 4 drilling depth is compiled within 40 m - different design depths need separate analysis; 5 the surface cement-silicate items take water-binder 1:1 and volume ratio 1:0.8, allowing 5% water and 1% cement loss; other designed mixes may be substituted.
(2) General soil grouting - TB/T 10831-2024 Volume 10 Buildings, Chapter 1 civil works, Section 2 piles and foundations, item 6 grouting reinforcement:
- Layered grouting: FY-293 drilling (100 m), FY-294 grouting (10 m3); work content: layered grouting, including positioning, drilling, bentonite injection, slurry mixing, mandrel insertion, layered fracturing grouting, effect checking.
- Compaction grouting: FY-295 drilling (100 m), FY-296 grouting (10 m3); work content: compaction grouting, including positioning, drilling, bentonite injection, slurry mixing, mandrel insertion, compaction grouting, effect checking.
(3) In-tunnel and out-of-tunnel reinforcement - TB/T 10824-2024 Volume 3 Tunnels, Chapter 1 mining-method tunnels, Section 3 support:
- (2) advance-support grouting: SY-119 cement grout, SY-120 cement-silicate slurry, unit 10 m3; work content: moving plant, arranging air lines, slurry making, grouting, hole-mouth treatment.
- (1) advance reinforcement: SY-123 to SY-126 drilling (depth up to 30 m, bore d89 / d108, grade IV / V surrounding rock, 100 m); SY-127 curtain grouting with cement grout, SY-128 cement-silicate slurry, SY-129 grout stop wall, unit 10 m3. Drilling work content: site clearing, working platform erection and removal, hole setting, air-water-power connections, drilling, hole-pipe fabrication and installation.
- (2) perimeter reinforcement: SY-130 radial drilling (depth up to 4 m, bore d42, 100 m); SY-131 radial grouting with cement grout, SY-132 cement-silicate slurry, unit 10 m3; work content: mobile stage erection and removal, drilling, grout plant positioning, slurry making, grouting, checking, hole sealing.
- (3) surface reinforcement: SY-133 drilling (25 m < h up to 75 m), SY-134 drilling (75 m < h up to 120 m), unit 100 m; SY-135 sleeve-valve pipe fabrication d76 (100 m); SY-136 grouting with dual-control cement grout, SY-137 cement-silicate slurry, unit 10 m3. Work content: drilling - rig positioning, drilling, hole cleaning, depth checking; sleeve-valve fabrication - pipe making, casing working.
3. Decision logic. First locate the volume and chapter by grouting location (subgrade under track / cavities - subgrade Chapter 7; general foundation soil - buildings grouting reinforcement; in-tunnel advance, perimeter or surface - tunnels mining-method support), then pick the item by slurry type (plain cement / cement mortar / cement-silicate double slurry) and by depth, bore, stratum (soil / soft / moderately hard / hard rock) or rock grade. Drilling and grouting are mostly separate items charged in tandem (subgrade note 3 pairs grouting and surface cement-silicate items with drilling); cement-silicate items carry markedly higher material shares than plain cement grout. Base-period prices, cost make-ups and main material contents follow the quota tables.
Applicability limits
- Based on TB/T 10822-2024, TB/T 10823-2024, TB/T 10824-2024 and TB/T 10831-2024 base prices and work contents; amounts and consumptions need the original tables; item numbers and splits differ across versions - no carrying of old numbers.
- Existing-line strengthening means different things in different volumes: QY-843-846 cover only track strengthening and protection, no grouting; never use that chapter to cover grouting, nor double-count grouting against track work content.
- Subgrade cavity drilling is compiled within 40 m - deeper designs need separate analysis; grouting compiled on cement mortar, substitutable by designed mixes.
- The buildings volume's grouting reinforcement suits general foundation soil; in- and out-of-tunnel reinforcement takes the tunnel volume; cross-volume borrowing needs a basis or a supplementary rate analysis.
- This card settles which item and what it contains, not the design of grouting extent, hole spacing or diffusion radius.
Further reading
- TB/T 10823-2024 Volume 2, Chapter 4 Section 3, item 3 RC circular culvert jacking, (3) existing-line strengthening and protection (QY-843 to QY-846).
- TB/T 10822-2024 Volume 1, Chapter 7 underground cavity treatment: 1 drilling (LY-443-446); 2 grouting (LY-447-449, HT-931); volume notes Part 2 Chapter 7 (items 1-5).
- TB/T 10831-2024 Volume 10, Chapter 1 Section 2, item 6 grouting reinforcement (FY-293 to FY-296).
- TB/T 10824-2024 Volume 3, Chapter 1 Section 3 support: item 4 advance support (2) advance-support grouting (SY-119, SY-120); item 5 rock reinforcement - (1) advance (SY-123-129), (2) perimeter (SY-130-132), (3) surface (SY-133-137).
Keywords
- 既有线加固
- 注浆定额
- 地下洞穴处理
- 袖阀管注浆
- 注浆加固
- 帷幕注浆
- TB/T 10823-2024
- TB/T 10822-2024
- TB/T 10824-2024