Drill-hole grouting for water stop of leakage through cracks in cast-in-place concrete underground structures: hole layout parameters (spacing 300~500mm, depth 1/3~1/2 of structural thickness, bore up to 20mm, inclination 45~60 degrees), rapid plugging and surface-port grouting methods, the extent of the rigid waterproof layer, and the basic rules and completion criteria of grouting

JGJ/T 212-2010 clause 4.2.1: leakage through cracks of cast-in-place structures is preferably stopped first, then a rigid waterproof layer applied. With high water pressure or large leakage, drill-hole grouting applies: for cracks needing no strengthening, grout holes cross over both sides of the crack, inclined to cut through it, vertical depth preferably 1/3~1/2 of the structural thickness h, horizontal offset from the crack 100~250mm, spacing 300~500mm, bore preferably not over 20mm, inclination preferably 45~60 degrees, seam-sealing width preferably 50mm; where strengthening is required, first inject polyurethane grout to stop the water (depth not less than 1/3h), then drill a second set of inclined holes for moisture-curing epoxy or cement-based grout (not less than 1/2h); structures under 200mm thick take vertical holes at 1/2 the thickness; the rigid waterproof layer coats cementitious capillary crystalline coating and polymer-cement waterproof mortar over 200mm each side of the crack. GB 50108-2008 clause 7.2.7: grout holes inside the lining preferably reach 1/3~2/3 of the lining thickness at 0.5~0.8MPa.

Applicable Codes

  • JGJ/T 212-2010 地下工程渗漏治理技术规程 第3.4.10条、第4.2.1条、附录A
  • GB 50108-2008 地下工程防水技术规范 第7.2.7条、第7.4.7条

Positioning

Hole layout parameters for drill-hole grouting to stop leakage through cracks of cast-in-place concrete underground structures (base slabs, walls, linings of relatively small thickness) - spacing, depth, bore, inclination and sealing width - plus grout-port layout, rapid-plugging groove sizes, the extent of the rigid waterproof layer, and the basic construction rules and completion criteria of grouting.

Core conclusions

1. General principle: crack leakage is preferably stopped first, then a rigid waterproof layer applied over the substrate (JGJ/T 212-2010 clause 4.2.1).

2. Cracks under high water pressure or large leakage - drill-hole grouting:

  1. Cracks needing no strengthening: grout holes preferably staggered on both sides, inclined to cut through the crack, vertical depth preferably 1/3~1/2 of the concrete thickness h; horizontal distance from the crack preferably 100mm~250mm; spacing preferably 300mm~500mm; bore preferably not over 20mm; inclination preferably 45~60 degrees; where pre-sealing is needed, the sealing width is preferably 50mm.
  2. Cracks needing strengthening: first drill inclined holes and inject polyurethane grout to stop the water, vertical depth preferably not less than 1/3h; then drill a second set of inclined holes for epoxy grout curable in damp conditions or cement-based grout, vertical depth preferably not less than 1/2h.
  3. The grout port enters the hole preferably no deeper than 1/2 the hole length.
  4. For concrete under 200mm thick: vertical holes on the crack, depth preferably 1/2 the thickness. Commentary (clause item 1): inclined holes favour cutting the crack so the grout flows along the crack face, reacts and cures, quickly cutting the leakage path; building underground structures being relatively thin, the vertical depth is capped at 1/2 the thickness both to protect the structure from grouting pressure and to place the grout inside it.

3. Cracks under low pressure and small leakage: grout as above, or plug rapidly with quick-setting inorganic leak-plugging material. Rapid plugging: cut a U-groove along the crack on the surface, preferably 40mm~50mm deep and 40mm wide, fill it with the quick-setting material, leaving a recess of not less than 20mm, then level with polymer-cement waterproof mortar containing cementitious capillary crystalline material.

4. Damp cracks without running water: surface-port grouting with moisture-curing epoxy grout: port bases preferably carry through-holes (the adhesive keys through them on curing, improving bond; non-return ports where conditions allow); ports sit preferably at the wider and crossing parts of the crack, spaced 200mm~300mm, crack sealing width preferably 50mm.

5. Rigid waterproof layer: coat cementitious capillary crystalline coating over 200mm each side of the crack, then trowel a single layer of polymer-cement waterproof mortar; substrates with dense cracking take mortar over a larger area.

6. Basic rules of grouting works (clause 3.4.10): air, water and power supplies reliable, dedicated lines where necessary; crews trained in technique, safety, environment and emergency response; single-component grout mixed 'in small lots, often' with temperature control (chemical grouting cures exothermically - unvented heat can flash-polymerise and damage equipment); two-component grout proportioned exactly; substrate temperature preferably not below 5C and grout not below 15C (cold substrates hinder diffusion and curing; cold grout loses injectability); small hole bores and small-bore lines, the pump close to the port and lines short (avoiding pressure drop and grout loss); sequence: clean the leak - set ports - flush holes (cracks) - seal - mix - grout - close holes - clean up; safety and environment per Appendix A; on grout escape, lower pressure, reduce flow, adjust proportions or stop; grout continuously, resuming promptly after interruption.

7. Lining grouting parameters (GB 50108-2008 clause 7.2.7): 'Grout holes inside the lining are laid out per the leakage; depth preferably 1/3~2/3 of the lining thickness, grouting pressure preferably 0.5~0.8MPa.' (Depth at 1/3~2/3 of the wall keeps behind-wall sand from rushing in and grout from escaping.)

8. Completion criteria (GB 50108-2008 clause 7.4.7): '1 Pre-grouting: every hole section reaches the design requirement and holds 10min, with intake at 1/4 of the initial rate or 80% of the design volume; 2 Backfill grouting behind the lining and rock grouting: reach the design final pressure; 3 Other grouting: meet the design.' Different purposes, different completion standards.

Applicable boundaries

  • The parameters suit non-structural and structural crack leakage treatment of cast-in-place underground structures (thin slabs, walls, linings); soil improvement, rock pre-grouting and anchor grouting use different spacing, pressure and depth - never apply these.
  • Clause 7.4.7's three items serve pre-grouting, backfill / rock grouting and other grouting - classify the grouting type first; crack plugging normally runs on item 3, 'meet the design'.
  • Pressures, bores and depths also follow the design documents and product data; special thickness, reinforcement or loading (strengthening required, thin walls) - parameters and vertical drilling need the designer's confirmation.
  • 'Preferably' clauses are recommendations - design requirements govern; stricter local standards govern where they exist.

Further reading

  • JGJ/T 212-2010 (leakage treatment of underground works) clause 4.2.1 and commentary with Figures 4.2.1-1~-4 (hole layout, water-stop and strengthening holes, rapid plugging, surface-port grouting); clause 3.4.10 and commentary; Appendix A.
  • GB 50108-2008 (code for waterproofing of underground works) clauses 7.2.7 and 7.4.7.
  • The pricing interface (trade split, point / linear-metre / square-metre measurement, gap items) sits in the grouting cost cards.