Technical requirements for filter screens and filter pack (gravel pack) of dewatering wellpoints: material and porosity, casing installation tolerances, gravel quality and quantity calculation
For dewatering wellpoints, filter screens should be sand-free concrete filter pipes, UPVC pipes, rebar-cage pipes, steel pipes, or geosynthetic pipes, with porosity greater than 15% and a sediment trap at the bottom (length preferably not less than 1000mm). Casing installation: concentric and vertical, top of screen below the design dynamic water level (tolerance +/-300mm), casing top at least 300mm above ground, centralizers every 6m for gravel-pack wells (diameter 25mm-50mm smaller than the hole). Filter gravel should be well-rounded siliceous gravel (hard rock), mud content not greater than 3%, screened (off-spec quantity not over 15% of design), uniformity coefficient below 2; quantity by V = pi/4 (Dk^2 - Dg^2) x L x alpha (alpha preferably 1.2-1.5); place gravel promptly after casing installation, thin the mud in the well before packing (except in artesian aquifers), mud density preferably 1.05-1.10 g/cm3.
Applicable Codes
- DB11/T 1832.1-2021 建筑工程施工工艺规程 第1部分:地基基础工程(第31.1.2条、第31.4.7条)
- GB 50296-2014 管井技术规范(第7.5.1条)
- DBJ04/T 405-2020 建筑基坑降水工程技术标准(第6.2.8条)
- JGJ 167-2009 湿陷性黄土地区建筑基坑工程安全技术规程(第9.2.9条)
Topic Positioning
This card compiles the material selection, installation, and quality-control requirements for [filter screens] and [filter pack (gravel pack)] in dewatering wellpoint (large-diameter wellpoint) construction, combining the Beijing local standard DB11/T 1832.1-2021 "Construction work procedure specifications for building works, Part 1: foundation engineering", the national standard GB 50296-2014 "Technical code for water wells", the Shanxi local standard DBJ04/T 405-2020 "Technical standard for dewatering of building excavations", and JGJ 167-2009 - for direct use in work procedures, technical disclosure, and quality acceptance.
Core Conclusions
I. Filter screen (casing) requirements
Material and porosity (DB11/T 1832.1-2021 Clause 31.1.2): filter screens should be sand-free concrete filter pipes, UPVC pipes, rebar-cage pipes, steel pipes, or geosynthetic pipes, with porosity greater than 15%; a sediment trap not shorter than 1000mm shall be provided at the bottom of the casing.
Casing installation (DB11/T 1832.1-2021 Clause 31.4.7, key points):
- When lowering the casing, it shall stand vertical at the hole center; joints shall be concentric and the top end horizontal;
- No gaps are allowed on casing pipes; lift and lower gently; never force a blocked casing down;
- With direct lifting, the casing's self-weight or buoyant weight shall not exceed the pipe's allowable tensile strength or the rig's safe load; add pulley blocks if the rig's lifting capacity or wire-rope strength is insufficient, or use the drill-rod tray method if the casing is too weak;
- The screen top shall always stay below the design dynamic water level; installation-depth tolerance preferably +/-300mm;
- Casing top preferably at least 300mm above ground;
- The bottom sediment trap shall be sealed and the casing seated firmly;
- For wells with gravel-pack filters, centralizers shall be set at screen joints and on the casing every 6m, their diameter 25mm-50mm smaller than the hole diameter.
- Well structure (JGJ 167-2009 Clause 9.2.9, collapsible loess regions): casing OD preferably not less than 200mm, ID preferably 50mm larger than the pump OD; sediment pipe not shorter than 3m; porosity of sand-free concrete, steel, cast-iron, and rebar-cage screens preferably not less than 15%, 30%, 23%, and 50% respectively.
II. Filter pack (gravel) requirements
Timing and preparation (GB 50296-2014 Clause 7.5.1; DBJ04/T 405-2020 Clause 6.2.8): gravel packing shall follow casing installation promptly to prevent wall caving; before packing, the mud in the well shall be thinned (except in artesian aquifers) to a density of preferably 1.05-1.10 g/cm3, still thick enough to keep the wall stable.
Quantity calculation: V = pi/4 x (Dk^2 - Dg^2) x L x alpha, where V = gravel volume (m3), Dk = hole diameter over the packed interval (m), Dg = screen OD (m), L = packed length (m), alpha = oversize coefficient, preferably 1.2-1.5.
Gravel quality (DBJ04/T 405-2020 Clause 6.2.8): (1) gravel shall be screened, off-spec quantity not exceeding 15% of design; (2) particles sub-rounded or better - angular crushed stone prohibited; (3) mud content not greater than 3%, free of debris; (4) siliceous gravel preferred. JGJ 167-2009 Clause 9.2.9 adds: use well-rounded hard rock; angular crushed rock, weathered material, or argillaceous rock should not be used.
Gravel sizing (JGJ 167-2009 Clause 9.2.9): set from the aquifer gradation - (1) sand aquifers by the relation between pack D50 and aquifer d50 (the particle size at 50% passing on the cumulative curve); (2) gravelly aquifers with d20 < 2mm by the d20 relation; (3) gravelly aquifers with d20 >= 2mm may take 10-20mm gravel; (4) pack uniformity coefficient below 2.
Applicable Boundaries
- Applies to filter-screen and gravel-pack quality control of wellpoint (large-diameter wellpoint) dewatering; not applicable to light wellpoint or ejector wellpoint systems.
- DB11/T 1832.1-2021 is Beijing's local standard (applicable there, reference elsewhere); DBJ04/T 405-2020 is Shanxi's; GB 50296-2014 and JGJ 167-2009 are national/industry standards, Clause 9.2.9 applying only to collapsible-loess excavations.
- Porosity values differ by screen material: sand-free concrete >=15%, steel >=30%, cast iron >=23%, rebar cage >=50% (JGJ 167-2009); DB11/T 1832.1's "porosity greater than 15%" is the general floor.
- The quantity formula applies to gravel-pack filter wells; the oversize coefficient alpha (1.2-1.5) is chosen per actual hole over-sizing.
- The mud-thinning density 1.05-1.10 g/cm3 does not apply to artesian aquifers.
Further Reading
- Casing installation: DB11/T 1832.1-2021 Clause 31.4.7 (also 31.1.2 for screen material and sediment trap).
- Gravel packing: GB 50296-2014 Clause 7.5.1; DBJ04/T 405-2020 Clause 6.2.8 (quality and quantity formula; sizing also in 5.3.14).
- Well structure: JGJ 167-2009 Clause 9.2.9.