Measurement of the "empty bore" quantity of bored piles under the 2024 railway quota system: the compilation rules carry no independent item, the empty-bore section is already included in the boring length computed over the full depth from the commencement surface to the designed pile toe level, and it is not billed as a separate item

Under the 2024 railway quota system the empty bore of bored piles is not billed separately: TB/T 10823-2024 (bridge and culvert works volume) provides that the bored depth is computed from the ground level on land, the riverbed level over water, the island top level for island construction, or the finished subgrade shoulder level in cutting sections, down to the designed pile toe level; the empty-bore (empty hole) section from the commencement surface to the pile top is already included in the full depth, is priced under the corresponding boring (hole formation) items and must not be listed again; where a split check is needed, empty bore = (commencement surface level minus designed pile top level) x cross-sectional area of the designed pile diameter. Neither the main text of the TB 10801-2024 compilation rules nor its Annex A carries an "empty bore" item - bored piles are listed only in metres, on land / over water (sonic logging pipes included). Where tubular piles serve as the boring casing, the depth penetration of the tubular pile is deducted from the bored depth.

Applicable Codes

  • TB 10801—2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects
  • TB/T 10823—2024《铁路工程预算定额 第二册 桥涵工程》
  • TB/T 10831—2024 · Budget Quota of Railway Engineering (Volume 10: Housing Works)
  • 国家铁路局公告2024年第28号(发布18项铁路工程建设标准,废止TZJ 1001—2017等21项)

Topic Positioning

This card answers, for budgets of bored piles compiled under the 2024 railway quota system (TB 10801-2024 compilation rules plus TB/T 10823-2024 "Railway Works Budget Quota, Volume 2, Bridge and Culvert Works"), the measurement and pricing conventions of the "empty bore" (empty hole section): whether the compilation rules carry an empty-bore item, on what basis the quota measures it, and how boundary cases are treated.

Core Conclusions

  1. No "empty bore" item at compilation-rules level; bored piles are listed only in metres, on land / over water. TB 10801-2024 "Rules for Compiling Design Estimates and Budgets of Railway Capital Construction Works" (published by National Railway Administration Announcement No. 28 of 2024, effective 1 January 2025; 21 former standards including TZJ 1001-2017 simultaneously repealed) carries no "empty bore" clause or detail item in its main text or in the chapter schedule of comprehensive estimates and budgets in Annex A; Annex A lists bored piles as: "5) bored piles - metre (sonic logging pipes included); 1 on land - metre; 2 over water - metre". Clause 2.4.1 of those rules provides that design estimates and budgets shall be compiled with the railway works quota - the quantity rules for the empty bore therefore follow the railway budget quota designated for use.

  2. Quota convention: the empty-bore section is included in the full bored depth and not measured separately. Volume notes of TB/T 10823-2024 "Railway Works Budget Quota, Volume 2, Bridge and Culvert Works", quantity take-off rules item 1 (original text): the bored depth of bored piles is computed from the ground level on land, the riverbed level over water, the island top level for island construction, or the finished subgrade shoulder level in cutting sections, down to the designed pile toe level; where tubular piles serve as the boring casing, the depth penetration of the tubular pile is deducted from the bored depth.

Hence:

  • Bored quantity = full depth from the commencement surface level to the designed pile toe level x cross-sectional area of the designed pile diameter (by volume); the quota items for boring slurry and removal of drill cuttings are used in matching sets, both quantities being the bored volume: V = 0.25 x pi x D x D x H (cubic metres), D being the designed pile diameter and H the bored depth.
  • Where the designed pile top level is below the commencement surface, the section from the commencement surface to the pile top (the empty bore / empty hole section in works parlance) is already included in that full depth and priced under the corresponding boring (hole formation) items; where a split check is needed, empty bore = (commencement surface level minus designed pile top level) x cross-sectional area of the designed pile diameter, merged into the bored quantity, and must not be listed once more (a separate listing would duplicate the bored quantity).
  • The commencement surface follows the working condition: on land = ground level; over water = riverbed level; island construction = island top level; cutting sections = finished subgrade shoulder level of the designed formed section.
  • The empty-bore section is not concreted into the shaft: shaft concrete quantity = designed pile length (pile top to pile bottom) plus 1 m, multiplied by the cross-sectional area of the designed pile diameter; over-boring factors must not enter the quantity.
  • Pile head (over-placed section) treatment is not the same matter as the empty bore: separate "cropping of concrete pile heads" quota items QY-229 to QY-231 (banded by pile diameter not over 1.0 / 2.0 / 3.0 m, counted per pile; work content includes pile head ring cutting, cropping concrete, stripping rebar, grinding the pile head and hoisting the head out of the pit); the ring-cutting item excludes haulage of the cropped heads, which is priced additionally by analogy with rock haulage.

Applicability Boundaries

  • Applies to bored pile works whose design estimates and budgets are compiled under the 2024 railway quota system; the "merged into full depth, no separate listing" convention comes from item 1 of the quantity take-off rules in the volume notes.
  • "Empty bore" is works parlance; neither the compilation rules nor the quota carries it as an independent item; budgets must not set up and price an item in the name of "empty bore", otherwise it duplicates the bored (hole formation) quantity.
  • The commencement surface is set per working condition (on land / over water / island / cutting); where tubular piles serve as the boring casing, the depth penetration of the tubular pile is deducted from the bored depth.
  • The empty-bore section affects only the hole formation (boring) quantity, not the shaft concrete quantity; pile head treatment is counted separately under the "cropping of concrete pile heads" items (QY-229 to QY-231) - do not mix the two.
  • For station-area building piles compiled under TB/T 10831-2024 "Railway Works Budget Quota, Volume 10, Building Works", the hole formation quantity is the hole formation length from the natural ground level before pile formation to the designed pile bottom level multiplied by the cross-sectional area of the designed pile diameter - the same convention as the bridge volume; over-placing length and other details follow the volume notes of Volume 10.
  • Where the current quota does not cover works urgently needed by a project, supplementary unit-rate analyses are organized by the investor per clause 2.4.3 of the compilation rules and copied to the standards administration body of the industry.

Further Reading

  • TB/T 10823-2024 "Railway Works Budget Quota, Volume 2, Bridge and Culvert Works": volume notes quantity take-off rules items 1 to 11 (bored depth, shaft concrete, steel casing and double-wall steel cofferdams, slurry and cuttings removal V = 0.25 x pi x D x D x H, sonic logging pipes, pile head ring cutting etc.); chapter 1 substructure works, section 4 bored and hand-dug piles, item 1 bored piles (including item 11, cropping of concrete pile heads, quota items QY-229 to QY-231); section 5 reinforced concrete square piles and tubular piles; section 6 tubular pile columns.
  • TB 10801-2024 "Rules for Compiling Design Estimates and Budgets of Railway Capital Construction Works": Annex A chapter schedule of comprehensive estimates and budgets (bored piles: metre, sonic logging pipes included; on land / over water); clauses 2.4.1 to 2.4.3 (quota adoption and supplementary unit-rate analyses).
  • TB/T 10831-2024 "Railway Works Budget Quota, Volume 10, Building Works": volume notes item 18, quantity take-off rules item 2, non-displacement piles.
  • Publication basis: National Railway Administration Announcement No. 28 of 2024 (18 railway engineering construction standards published 25 September 2024; 21 standards including TZJ 1001-2017 simultaneously repealed).

Keywords

  • 空钻量
  • 空孔
  • 钻孔桩钻孔深度
  • 钻孔灌注桩工程量
  • TB/T 10823
  • 桥涵工程预算定额
  • TB 10801-2024
  • 铁路2024定额