Quantity rules for triaxial cement deep-mixing piles: measuring by 'panel', no double counting of the three-circle overlaps inside a panel, and the three paradigms for inter-panel laps (one-hole re-stacking / full-section re-stacking), with a d850@600 panel-section worked example
Triaxial cement mixing pile quantities count by 'panel' (the three shafts of one driving pass): panel = panel cross-section x pile length (plus over-cast); the mutual overlaps of the three circles inside a panel never count twice (Shaanxi deducts the overlap volume, Jiangsu bars double-counting overlap area, Shenzhen takes the per-panel unit section, Fujian counts 3 circles for the opening panel and 2 thereafter), group-pile overlaps not deducted; inter-panel laps follow the quota rules - full-section re-stacking labour and plant x 1.50 (railway, Shaanxi), the re-mixed lap holes charged as empty boring (Shenzhen), or the re-stacked quantity not deducted with cement based on the design reinforced-soil volume (Jiangsu); pile counts are whole panels, not single shafts x 3. For d850@600: one panel net of internal overlaps 1.4949 m2; a panel after a one-hole lap adds 1.1349 m2.
Applicable Codes
- 陕西省2024新编消耗量定额 工程量计算规则第5条
- 江苏省2026版建筑与装饰工程消耗量标准 工程量计算规则第2条
- SJG 111.1-2022 城市地下综合管廊工程消耗量标准(Vol. 1)2.2.6
- TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程 Ch. 1第二节(五)水泥搅拌桩
- https://zjt.fujian.gov.cn/hygl/gczj/gczj/202012/t20201201_5470163.htm
Positioning
The measurement basis of triaxial cement deep-mixing piles (SMW method): 'panel' or 'single shaft'; whether the mutual overlaps of the three circles inside a panel are deducted; how inter-panel laps (one-hole / full-section re-stacking) measure; the geometry of a d850@600 panel section; and the bases for cement and inserted H sections.
Core conclusions
1. The basis is the 'panel' One panel = the three shafts of one pass. Quantity in m3 = panel section x length (+ over-cast); counts are whole panels, the opening panel 3 shafts and later panels 2 shafts under one-hole re-stacking - never single shafts x 3.
2. In-panel overlaps never count twice (wording varies; follow the executing quota)
- Shaanxi 2024 rules: 'Triaxial piles standing alone deduct the overlap volume. The overlaps between successive panels and between group piles are not deducted. Inserted / extracted H sections are measured by design mass.'
- Jiangsu 2026: 'Deep mixing and powder-jet piles: design length plus 500mm (or as designed) x design section in m3 (overlap area not double-counted); group-pile overlaps not deducted; where the design top is under 500mm from ground, add to ground level.' 'Inserted H by design mass.'
- Shenzhen SJG 111.1-2022: 'Non-lapped triaxial deep mixing: per-panel unit section x length, overlaps not deducted. Lapped: design section x length, the re-mixed lap holes charged extra as empty boring.' 'SMW inserted H by design mass in tonnes.'
- Fujian provincial Q&A: the opening panel counts 3 full circles, later panels 2, mutual circle overlaps not deducted. So 'no double counting within the panel' is common; the forms differ - deduct overlap volume (Shaanxi), no double-counted area (Jiangsu), per-panel section (Shenzhen), 3-then-2 circles (Fujian).
3. Three paradigms for inter-panel laps
- Quantity not deducted, labour and plant factored: railway TB/T 10831-2024 volume notes and Shaanxi - 'full-section re-stacking per design: labour and plant x 1.50, the rest unchanged'.
- Quantity not deducted, lap holes as empty boring: Shenzhen - 'the re-mixed lap holes are charged extra as empty boring in m3'.
- Quantity not deducted, cement on the design reinforced-soil volume: Jiangsu 2026 - 'on one-hole re-stacking, the re-stacked quantity is not deducted and cement is fixed by design injection ratio on the design reinforced-soil volume (including the added length)'.
4. d850@600 worked example (internal overlap deducted) Single circle pi x 0.425^2 = 0.5675 m2; three circles 1.7024 m2; one lens of two adjacent shafts (d = 600mm: 2r^2 x acos(d/2r) - (d/2) x sqrt(4r^2 - d^2)) = 0.1037 m2; two lenses 0.2075 m2 (12.2% of the three circles); panel section net = 1.4949 m2, volume 1.4949 m3 per metre (14.949 m3 over 10m); after a one-hole lap a new panel adds 2 full circles = 1.1349 m2. Cement = injection ratio x reinforced volume x 1800 kg/m3 - about 484 kg per metre at 18% (wastage excluded).
5. Idle-mix / empty-bore sections charged separately, outside the pile volume Jiangsu 2026: items allow for idle mixing within 2m; beyond 2m, the excess volume takes labour, the deep-mixing machine and the powder-jet rig x 0.3, nothing else; under 2m, no deduction. Shaanxi: idle mixing x 0.5 on labour and machines. Shenzhen: empty bore x 0.50 on labour cost and plant consumption, item materials deducted.
Applicable boundaries
- Triaxial (multi-shaft) piles only; single- and twin-shaft deep mixing and powder-jet piles run on design length (+ over-cast) x design outside-diameter section - no 'panel' basis.
- Whether in-panel overlap is deducted follows the executing quota's text (Shaanxi / Jiangsu deduct or bar double counting; Shenzhen does not) - no cross-regional mixing; the three lap treatments require confirming the local rule before bidding and settlement.
- The example assumes d850, 600mm shaft spacing, no re-stacking; other diameters (d650, d1000) or spacings need recomputed lenses.
- Inserted H sections list separately by design mass (t), outside the pile volume; standalone triaxial piles deduct overlap volume; group-pile overlaps stand.
- Over-cast length: as designed, else 0.5m (Jiangsu, Shaanxi).
Further reading
- Shaanxi 2024 rules item 5 (mixing-pile composite ground); Jiangsu 2026 ground-treatment rule 2 and notes (2m idle mix, injection base, insert-only factor); Shenzhen SJG 111.1-2022 rules 2.2.6 (with Figure 2.2.6) and 2.1.7; railway TB/T 10831-2024 Volume 10 items FY-211~FY-216 and volume note 8; Fujian Q&A batch 48: https://zjt.fujian.gov.cn/hygl/gczj/gczj/202012/t20201201_5470163.htm ; Beijing DB11/T 2382-2024 Table A.2.1-2 A-2-10 for cross-checking; conversion where no triaxial item exists: the companion card.
Keywords
- 三轴水泥搅拌桩
- 幅
- 截面面积
- 搭接
- 套打一孔
- 建筑与装饰工程消耗量
- 空搅
- 插拔型钢