Rebar BOQ itemization and coding rules: GB/T 50854-2024 Appendix E rebar item classification (cages / secondary-structure rebar / miscellaneous-member rebar / mesh / bolts / post-pour strips / post-installed bars)

Rebar is itemized by member type: cast-in-place rebar coded per member; precast/assembly member rebar included in the member, not listed separately; diaphragm-wall and bored-pile rebar listed as "reinforcement cages"; constructional columns, ring beams, lintels as "cast-in-place secondary-structure rebar"; wells, pools, cable trenches, ditches as "cast-in-place miscellaneous-member rebar"; fabricated rebar mesh and finished steel wire mesh as "rebar mesh" / "steel wire mesh"; embedded bolts, chemical bolts, and non-cycled tie bolts as "bolts" (steel-structure bolts in Appendix F); post-pour-strip rebar merges into the member, not separate; non-design post-installed bars not listed — where the design requires them, list under the corresponding member's rebar item adding the embedding requirement. Per GB/T 50854-2024 Appendix E notes on rebar, bolts, and ironware.

Topic Positioning

Under which item codes rebar is listed in the BOQ — a systematic reading of the 13 rules in the rebar/bolt/ironware notes of Appendix E "Concrete and reinforced concrete works" of GB/T 50854-2024, resolving "which item for bored-pile rebar", "how to list constructional column and ring-beam rebar", "is post-pour-strip rebar separate", "how to count post-installed bars" (distinct from the measurement caliber of "how much rebar quantity").

Core Conclusions

Per GB/T 50854-2024 Appendix E rebar/bolt/ironware notes:

  1. Every rebar item's work content shall include the corresponding measure rebar; fabrication covers cleaning, straightening, cutting, and bending; installation/fixing covers substrate cleaning, positioning, supporting, tying, and welding; connection covers splicing, welding, mechanical connection, and inspection/cleaning (note 1).
  2. Cast-in-place member rebar shall be coded and listed per member; rebar in general precast and assembly precast members is included in the member, not listed or measured separately (note 2).
  3. Diaphragm-wall and bored-pile rebar shall be listed under "reinforcement cage" (note 3).
  4. Constructional columns, ring beams, lintels, etc. under "cast-in-place secondary-structure rebar" (note 4).
  5. Rebar in cast-in-place wells, pools, cable trenches, and ditches under "cast-in-place miscellaneous-member rebar" (note 5).
  6. Fabricated rebar mesh and finished steel wire mesh used in members or divisions under "rebar mesh" / "steel wire mesh" (note 6).
  7. Prestressing bars, wire strands, and strands coded separately by material type and specification characteristics (note 7).
  8. Embedded bolts in cast-in-place concrete, chemical bolts anchored into concrete, and tie bolts left in concrete for special needs and not cycled under "bolts"; steel-structure bolts follow Appendix F metal structure works (note 8).
  9. Post-pour-strip rebar in cast-in-place structures is not listed separately; quantities merge into the corresponding member's rebar (note 9).
  10. Anchorage bars projecting from cast-in-place members: length per design, merged into the member's rebar; apart from laps marked by design (incl. code provisions), other construction laps (e.g., stock-length laps) are not measured; non-design measure bars — chairs, inclined struts, anti-floating bars, spacers — not measured (notes 10-12).
  11. Post-installed bars not required by design are not listed or measured separately; where required, code under the corresponding member's rebar item, adding the embedding requirement description (note 13). Rail transit caliber identical: GB/T 50861-2024 Appendix B.9.3 elevated bridge works — anchorage bars per design merge into rebar quantities; except laps marked by codes or design, construction laps not measured; non-design chairs/struts/anti-floating bars/spacers not measured in BOQ; non-design post-installed bars not listed separately.

Applicable Boundaries

Applies to rebar itemization/coding in building and decoration BOQs per GB/T 50854-2024; municipal (GB/T 50857-2024 Appendix J), structures (GB/T 50860-2024), and rail transit (GB/T 50861-2024 Appendix B) calibers are identical or similar, but item names follow each standard's appendices. This card resolves only "which item"; the measurement caliber (theoretical weight, lap length, anchorage merging, loss treatment) is in referenced cards; quota pricing follows local consumption standards (e.g., Shenzhen SJG 181.2-2024 5.2.1: absent marked laps, one lap per 12 m for bars <= 10 mm, per 9 m beyond 10 mm; mechanical connections not counted extra).

Further Reading

GB/T 50854-2024 Appendix E E.7.9 rebar/bolt/ironware notes (13 rules — the direct source); item mapping in Appendix E rebar tables (cast-in-place rebar, cages, secondary-structure, miscellaneous-member, mesh, wire mesh, bolts); steel-structure bolts in Appendix F; rail transit in GB/T 50861-2024 Appendix B.9.3; quota lap caliber in SJG 181.2-2024 Volume 2 (bridges and culverts) 5.2.1.