Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Measurement and quota pricing of post-installed (bonded) rebar: counted by piece, the 15d embedment-depth basis, and adjustment by each +/-1 cm sub-item (consumption standards and railway quota calibers)

Post-installed rebar quantities are counted by "piece" per the design drawings or approved construction scheme (SJG 181.2-2024 Clause 5.2.9); consumption-standard sub-items are compiled at 15d embedment depth (d = bar diameter), adjusted by corresponding increase/decrease sub-items when actual depth differs, and comprehensively cover drilling directions including drilling, hole cleaning, bar fabrication/installation, and in-hole adhesive injection (SJG 181.2-2024 Clause 5.1.9); Beijing DB11/T 2382-2024 provides "embedment depth 15d" and "each +/-1 cm" adjustment sub-items (both by piece); the railway building-repair quota's "post-installed bars" are per 10 pieces, tiered D10-D40 (TB/T 10831-2024, FY-1163-FY-1167). Post-installed bars not required by design are not listed separately (the process is in the corresponding rebar work content, GB/T 50854-2024 E.7.9; GB/T 50860-2024 A.15.11); design-required ones are listed under the member's rebar item with an embedment-requirement description.

Applicable Codes

  • GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准
  • GB/T 50860-2024 构筑物工程工程量计算标准
  • SJG 181.2-2024 市政工程消耗量标准 Vol. 2 桥涵工程
  • DB11/T 2382-2024 建设工程施工消耗量标准
  • TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程

Topic Positioning

From measurement and pricing angles, this card answers "how to measure and price post-installed rebar": counted by "piece" under dedicated sub-items, adjusted by increase/decrease sub-items when embedment depth differs from the 15d basis; it also distinguishes post-installed bars from ordinary anchorage bars (merged into member rebar quantities) in listing and measurement.

Core Conclusions

1. Measurement unit and quantity

  • Post-installed rebar is counted by "piece" per the design drawings or approved construction scheme (SJG 181.2-2024 Consumption Standard for Municipal Works, Vol. 2: Bridges and Culverts, Clause 5.2.9).
  • Contrast: anchorage bars projecting from cast members are determined in length per design and merged into that member's rebar quantity (GB/T 50854-2024 Appendix E, E.7.9, Item 10).

2. BOQ listing

  • Post-installed bars not required by design are not listed or measured separately; where design requires, list under the member's rebar item and add the embedment-requirement description (GB/T 50854-2024 Appendix E, E.7.9, Item 13).
  • For bars not design-required, all processes are included in the corresponding embedded-bar work content (GB/T 50860-2024 Standard for Measurement of Structures Works, A.15.11).

3. Quota pricing (consumption-standard caliber)

  • Work content: sub-items comprehensively cover drilling directions, including drilling, hole cleaning, bar fabrication/installation, and adhesive injection (SJG 181.2-2024 Clause 5.1.9, Item 1). Beijing's work contents include positioning, drilling, hole cleaning, bar forming, adhesive injection, planting, curing (DB11/T 2382-2024 Appendix G rail transit).
  • Depth basis and adjustment: sub-items compiled at 15d (d = bar diameter); where actual depth differs, adjust by the corresponding increase/decrease sub-items (SJG 181.2-2024 Clause 5.1.9, Item 2). Beijing likewise provides "embedment 15d" and "each +/-1 cm" sub-items, e.g., G1-4-146 "post-installed rebar, embedment 15d, D10" and G1-4-154 "each +/-1 cm, D10", both per "piece".
  • Railway caliber: TB/T 10831-2024 Vol. 10, Chapter 1, Section 9 repair works, "post-installed bars" (FY-1163-FY-1167, D10-D40), per "10 pieces"; work content: straightening, cutting, stacking; hole setting, drilling, aligning, removing dust, cleaning and drying; bar polishing, acetone wiping; mixing structural adhesive, injecting, planting, curing.

4. Practice points

  • Pricing contrast: cast-in anchorage is converted to mass by length, merged into member rebar and priced with the member; design-required post-installed bars are counted by piece under dedicated sub-items covering drilling-cleaning-injecting-planting-curing, adjusted by depth sub-items.
  • Settlement: check drawing depth vs the 15d basis and compute adjustments for the difference; non-design bars are neither listed nor priced (process already in rebar work content).

Applicable Boundaries

  • Sub-item structure and the 15d basis are local/industry consumption-standard calibers (Shenzhen SJG 181.2-2024, Beijing DB11/T 2382-2024, railway TB/T 10831-2024); not directly transferable across regions — follow the project's current standard and its increase/decrease rules.
  • Listing rules per the national GB/T 50854-2024 and GB/T 50860-2024; item characteristics per the drawings.
  • Structural design of embedment depth (per JGJ 145-2013, GB 50367-2013) is out of scope.

Further Reading

  • GB/T 50854-2024 Appendix E, E.7.9 notes on rebar, bolts and inserts (Items 10, 13)
  • GB/T 50860-2024 A.15.11
  • SJG 181.2-2024 Vol. 2: Bridges and Culverts, Clauses 5.1.9 and 5.2.9
  • DB11/T 2382-2024 Appendix G rail transit, Table G.1.21-4 post-installed rebar (G1-4-146, G1-4-154)
  • TB/T 10831-2024 Vol. 10: Buildings, Chapter 1 Section 9 "post-installed bars" (FY-1163-FY-1167)

Keywords

  • 植筋
  • 植筋计价
  • 按根计量
  • 消耗量标准
  • 后植钢筋
  • 15d
  • 增减子目
  • 植筋定额