Rebar quantity calculation: length x theoretical weight, lap/merge/deduction rules, and post-tensioning length adjustments
Rebar quantity = design-drawn rebar length (centerline length) x unit theoretical weight (t). The BOQ caliber counts only laps specified by design and codes, not construction laps; the quota caliber, where drawings/codes do not specify, counts one lap per 12 m for diameters up to 10 mm and per 9 m above 10 mm, with mechanical connections not counted separately. Post-tensioned prestressed rebar lengths are adjusted by reserved duct length and anchorage type. Embedded iron parts are measured by ton, rebar splices by number, post-installed rebar by piece.
Applicable Codes
- GB/T 50857-2024 市政工程工程量计算标准
- GB/T 50860-2024 构筑物工程工程量计算标准
- GB/T 50861-2024 城市轨道交通工程工程量计算标准
- SJG 181.2-2024 市政工程消耗量标准 Vol. 2 桥涵工程
- SJG 111.2-2022 城市地下综合管廊工程消耗量标准 Vol. 2
- TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程
Topic Positioning
Rebar quantity calculation rules: design-drawn length x unit theoretical weight in tons, including laps, merge/deduction items, and post-tensioning length adjustments, distinguishing the BOQ/quota dual calibers.
Core Conclusions
- Quantity = design-drawn rebar centerline length x unit theoretical weight (t); the weight of holes <= 0.3 sqm is not deducted; the weight of welding rods, rivets, and bolts is not added.
- Laps: the BOQ counts only laps specified by design and codes; where the quota has no specification, count one lap per 12 m for diameters up to 10 mm and per 9 m above 10 mm; mechanical connections are not counted separately.
- Anchorage bars, precast lifting hooks, and fixing/support bars are merged; chair bars and shim irons are merged per design/codes/project execution plan (the BOQ does not count non-design measure bars). Embedded iron parts and bolts are measured by ton with supports merged; splices by number; post-installed rebar by piece.
- Post-tensioning adjusts by duct length: both-ends screw-rod anchorage -0.35 m (screw rods counted separately); upset-head insert plate at one end and screw rod at the other, by duct length; upset head at one end and tie-bar anchorage at the other +0.15 m; tie-bar anchorages at both ends +0.30 m; self-anchoring +0.35 m. Carbon steel wire with cone-type anchorage <= 20 m +1 m, > 20 m +1.8 m; upset-head anchorage +0.35 m; steel strand with JM/XM/OVM/QM <= 20 m +1 m, > 20 m +1.8 m.
Applicable Boundaries
The BOQ is governed by the GB/T 50854/50857/50860/50861-2024 series; the quota figures are cited from Shenzhen SJG 181.2-2024, SJG 111.2-2022, SJG 84-2020, and railway TB/T 10831-2024 — other regions follow the local current quota; the 12 m/9 m rule applies only when the drawings and codes do not specify laps.
Further Reading
BOQ: GB/T 50857-2024 Appendix J.2.1, GB/T 50860-2024 Appendices A.15.6/A.15.10, GB/T 50861-2024 Appendix B.9.3; quotas: SJG 181.2-2024 Clauses 5.2.1, 5.2.6; SJG 111.2-2022 Clause 3.2.3; TB/T 10831-2024 volume notes 10(12).
Keywords
- rebar quantities
- 钢筋工程量计算
- 钢筋搭接
- 搭接长度
- 后张法预应力钢筋
- 锚具
- 钢筋制安
- 中心线长度
Related Cards
- →
Rebar quantity calculation: measurement and pricing treatment of anchorage, splices, measure rebar, and construction wastage
BOQ quantity = net quantity shown on the design drawings (including anchorage and design splices; excluding construction splices, non-design measure rebar, and wastage); measure rebar and construction wastage are absorbed by quota consumption/work content and do not appear in the quantity figures. Based on the 2024 editions of GB/T 50854/50857/50860 etc.
- →
Quantity take-off (measurement) follows design-drawn dimensions (measurement per drawings): general principle, rule exceptions, and final account linkage
Quantities are in principle calculated from design-drawn dimensions (measurement per drawings), not from actual site dimensions; only items where the method of measurement "provides otherwise" (e.g. earthwork by natural in-situ (undisturbed) volume, depth taken from surveyed elevation) and site instruction / variation record items not specified in the design (flowing sand and silt provisionally estimated, concealed works) are measured per actual conditions / site instruction / variation record. Parts constructed beyond design dimensions without variation or site instruction / variation record support are generally not measured in the final account.
Cited By
- ←
Re-measurement and price splitting after rebar substitution: re-measure from the variation drawings, count the quantity once only (lap and wastage coverage), the splitting formula of the quantity difference at the contract rate plus the material price difference carrying VAT only, and the 15% clause boundary among adopting the contract rate / converting an analogous rate / building up a new rate (GB/T 50500-2024 cl. 7.4.2, 8.2.1, 8.9.1, 8.9.2 and 3.3.5)
After a rebar substitution, re-measure from the variation instruction and the as-built construction drawings (GB/T 50500-2024 cl. 7.4.2) and count the quantity once only (laps only where shown by the design or by codes; erection wastage enters the quota content). Price splitting: dC = dQ x P1 + Q2 x dp - the quantity difference is priced at the contract (or re-banded) all-in unit rate, and the material price difference carries VAT only, with no overheads or profit (cl. 3.3.5). Rate banding takes 15% as the line: where the billed quantity change does not exceed 15% (inclusive), the five bands of cl. 8.9.1 apply (same conditions and same item description -> the contract rate; analogous description or analogous conditions -> a converted analogous rate; otherwise a negotiated rate build-up); beyond 15% (exclusive), cl. 8.9.2 applies and the rate is lowered or raised for the change in procurement discounts brought by the quantity gain or loss. Routine grade and size substitutions mostly land in the 'adopt the contract rate / convert an analogous rate' bands, not in a new rate build-up.
- ←
Allocation of liability between rebar detailing wastage and stock-length wastage, the selection of wastage rates by splicing method, and the certification and claim route for wastage beyond the quota
Detailing wastage and stock-length wastage are both fabrication wastages already included in the quota; within the effective wastage rate they are borne by the contractor and may not be charged separately (GB/T 50500-2024 Article 3.3.3). The part beyond the effective rate is allocated by cause: for contractor-caused overruns the employer deducts, at the unit price of the relevant supply contract, from the price payable in the interim settlement by construction stage or the final account (Article 3.6.3); for employer-caused causes (such as supplied materials of the wrong specification driving the wastage rate over) the employer bears it. Stock-length laps are not measured (GB/T 50854-2024 Annex E note 11). Railway operating wastage: 1.5% for welded ribbed bar, 1% for mechanically spliced bar, plus 1.5% of lap length for non-coupler splices over 10mm in diameter (TB/T 10821-2024); building and municipal works take about 5% combining wastage and measures rebar (DB11/T 2382-2024 Articles 4.6.5 and 7.1.32). Wastage beyond the quota can be recovered only where the cause is not the contractor's, and must be raised in writing within the contractual time limit (where the contract is silent, 14 days for the employer to request particulars and 28 days to reply); a late claim may be deemed waived (Article 8.11.5).
- ←
Rebar BOQ itemization and coding rules: GB/T 50854-2024 Appendix E rebar item classification (cages / secondary-structure rebar / miscellaneous-member rebar / mesh / bolts / post-pour strips / post-installed bars)
Rebar is itemized by member type: cast-in-place rebar coded per member; precast/assembly member rebar included in the member, not listed separately; diaphragm-wall and bored-pile rebar listed as "reinforcement cages"; constructional columns, ring beams, lintels as "cast-in-place secondary-structure rebar"; wells, pools, cable trenches, ditches as "cast-in-place miscellaneous-member rebar"; fabricated rebar mesh and finished steel wire mesh as "rebar mesh" / "steel wire mesh"; embedded bolts, chemical bolts, and non-cycled tie bolts as "bolts" (steel-structure bolts in Appendix F); post-pour-strip rebar merges into the member, not separate; non-design post-installed bars not listed — where the design requires them, list under the corresponding member's rebar item adding the embedding requirement. Per GB/T 50854-2024 Appendix E notes on rebar, bolts, and ironware.
- ←
Work-item quantity take-off for pile foundation (bored pile) rebar cages: the three formulas for main bars, helical links and stiffening rings with their variable definitions, the convention for taking the centreline diameter D of helical links, the BOQ itemisation code for the 'rebar cage' item, and the measurement boundary of laps and non-design reinforcement
The billed quantity of a pile rebar cage = the design-drawn rebar length (centreline) x the unit theoretical mass (tonnes): main bars G_main = (L_cage + L_anchor + L_end) x n_main x w; helical links L_helix = sum over i of (Hi / si) x sqrt((pi x D)^2 + si^2), with D = diameter over the outside of the main bars + link diameter, i.e. pile diameter - 2 x cover + d_link; stiffening rings G_stiff = (pi x D_stiff + lap) x n_stiff x w. GB/T 50854-2024 Table E.6.1 (code 010506) requires the rebar of bored piles and diaphragm walls to be coded and listed under the 'rebar cage' item; laps and anchorage marked on the design (including those required by codes) are absorbed, while stock-length laps and non-design chair bars, raking prop bars, anti-floating bars, spacers and the like are not measured; sonic tubes are not merged into the cage and are listed separately.
- ←
Cost split and variation difference formula for changing rebar from tied lapping to straight-thread mechanical connection: lap length and deductible steel quantity, new coupler and thread-cutting costs, labour changes, joint sampling and testing costs, plus the measurement bases for rebar quantity and joint count and the wastage rate
Changing rebar from tied lapping to mechanical connection is split across four accounts: (1) deduct the lapped steel quantity = joint count x lap length ll x unit theoretical mass (ll = zl x la, the correction factor taken per GB 50010-2010 clause 8.4.4 and the lap no less than 300mm), with the material cost deduction multiplied by (1 + wastage rate; fabrication wastage and spacer bars such as chairs are best taken at 5%); (2) new straight-thread coupler and thread-cutting cost = joint count x all-in rate per joint, or rate build-up from the quota line item consumptions (e.g. DB11/T 2382-2024 item A-5-113: labour 0.0250 workdays per joint, couplers 1.0100 nos per joint); (3) labour up and down: the new thread-cutting labour follows the item labour consumption, while tying labour is normally already included in the installation item and is not deducted separately; (4) joint sampling and testing costs are taken per JGJ 107-2016 technique inspection (no fewer than 3 specimens per bar specification) and site inspection (500 joints per acceptance lot, 3 specimens drawn, retest of 6 where only 1 fails) and split under the testing-cost attribution rules. The variation difference = new joint cost + labour delta - deducted lap steel quantity x rebar unit price x (1 + wastage rate); positive means an increase to the contract price, negative a decrease. The joint count is measured as the design-shown quantity (9m per joint for bars over d10, 12m per joint for bars up to d10, by stock-length interval), and no additional lap steel is measured for mechanical connections.
- ←
Classification of reinforcement in slab-type members: negative moment bars, distribution bars, temperature bars and opening trimming bars are design reinforcement to be counted into quantities, while chair bars (iron horses, support bars), ladder bars, positioning bars, shims, diagonal brace bars and anti-buoyancy bars are construction-aid bars not measured separately; including the two-branch test for chair bars 'detailed on the drawings / not detailed', the constructional practice, the mass calculation formula and the evidentiary requirements for certification at final account
The governing logic: bars shown on the design drawings (including bars fixing positions as required by the codes) -> counted into the rebar quantities; purely constructional aids -> not counted, their cost absorbed by the work content or consumption of the rebar items. Slab negative moment bars (top bars), distribution bars, temperature bars, drawn trimming bars at openings and anchorage bars are design reinforcement, counted at centreline length x theoretical mass (bends follow the centreline into the count; laps marked by design or the codes are counted; anchorage lengths into supports are merged in); chair-type support bars: where the design drawings (or atlas nodes) detail them, they are merged in tonnes as drawn into the slab rebar quantities; where the drawings are silent, they are non-design construction-aid bars and no BOQ quantity is calculated (GB/T 50854-2024 Appendix E item 12, GB/T 50857-2024 Appendix J.2.1, GB/T 50860-2024 Appendix A.15.8); where an approved project execution plan exists and the contract agrees measurement by the plan, they are merged in tonnes per the plan (SJG 181.2-2024 clause 5.2.2).
- ←
Cutting length of rectangular closed stirrups in beams (columns) for bar fabrication (outside perimeter + hook allowance - bend deduction), selection of seismic hooks, concrete cover values, and stirrup count build-up over the densified zones at the beam ends
The cutting length of a rectangular closed stirrup is L = 2[(b - 2c) + (h - 2c)] + n x (1.9d + Lp) - B, with n = 2, seismic Lp = max(10d, 75mm) and non-seismic Lp = 5d, and for a rectangular stirrup B is the total bend deduction of four 90-degree corners. Here c is the concrete cover to the outermost layer of steel (the stirrup), so b - 2c and h - 2c give the outside dimensions of the stirrup directly (GB 50010-2010 clause 8.2.1; commentary on GB 50204-2015 clause 5.3.5). Counts are summed segment by segment over the beam-end densified zones: grade 1 densified length max(2hb, 500), grades 2 to 4 max(1.5hb, 500) (GB 50011-2010 table 6.3.3); the first stirrup sits no more than 50mm from the joint edge (GB 50010-2010 clause 11.3.9), and the spacing in the non-densified zone is no more than twice that in the densified zone.
- ←
The three rebar quantities (drawing quantity -> cutting quantity -> procurement quantity): stage-by-stage measurement bases, the quota chapter where the wastage rate is taken, and the conversion procurement quantity = budget quantity x (1 + wastage rate)
Drawing quantity = design centreline length x theoretical unit mass (includes anchorage and design laps; excludes construction laps / auxiliary bars / wastage); cutting quantity = drawing quantity + end hook growth values, bend deduction values (elongation as a deduction), stock-length laps and splice lengths, auxiliary bars and the inclined length of bent-up bars; procurement quantity = budget quantity x (1 + wastage rate), the wastage rate being taken item by item by bar type and splice method. In the railway system the reinforcement wastage rate is taken uniformly from Chapter 10 'on-site material handling and operation wastage rates' of the 'Railway basic quota manual' TB/T 10821-2024 (welding 1.5%, mechanical splices 1%, prestressing tendons 4% excluding the external-tensioning working length), not from the concrete chapter or the reinforcement fabrication chapter.
- ←
Aggregating rebar quantities by size and the measurement boundaries: grouping by bar type / diameter band / member; hooks, design laps and anchorage included; construction laps and measures bars not measured; mechanical couplers counted as units without laps; in t to three decimal places
Rebar quantity W(t) = Sum(ni x Li x wi) / 1000, with lengths taken as the centre-line lengths of the bars shown on the design drawings (GB/T 50860-2024 Annex A.15.6), aggregated at three levels: bar type / grade, diameter band (quota manuals commonly d10 and below / above d10) and member location (cast-in-place, rebar cages, secondary structure, sundry members, mesh). Included in the BOQ quantity: anchorage bars projecting from members as designed (GB/T 50854-2024 Annex E note 10) and laps marked in the design or required by the code (lap length ll corrected for the splice-area percentage and no less than 300mm, GB 50010-2010 Clause 8.4.4). Excluded: construction laps such as stock-length laps, non-designed chair bars, diagonal brace bars, anti-floating bars and spacers, and non-designed post-installed bars; rebar at post-cast strips is not itemised separately. Where the drawings require mechanical connection, the straight-thread sleeve coupler item applies and no lap quantity is calculated; couplers are counted as units by the number shown on the design. Rounding of totals: quantities in t are stated to three decimal places, the fourth being rounded (GB/T 50861-2024 Clause 3.0.3).
- ←
Computing rebar bending deductions (setting-out differences) and hook add-on lengths: methods, formulas and code bases
Cutting length = cumulative outside (envelope) dimensions - sum of bending deductions at each bend + sum of hook add-on lengths at each end, the cutting length computed on the bent centre-line length (DBJ50/T-331-2019 Article 8.2.4; DB 51/T 5046-2007 Article 3.1.4). The bending deduction is the tangent-length-minus-arc-length difference (GB 50162-92 Article 4.2.6 commentary); per bend, delta = 2r tan(a/2) - pi x r x a/180, r = (D+d)/2 being the centre-line bend radius; bars over 10 mm diameter correct per GB 50162-92 Article 4.2.6 - 45 and 90 degrees from Appendix 2, 135 degrees without correction. Hook add-on lengths read from GB 50162-92 Appendix 1 (hook growth), their end build-up (inside bend diameter D, straight tail length) per GB 50666-2011 Articles 5.3.4-5.3.6.
- ←
Cutting length of spiral stirrups (bored piles / circular columns): the Pythagorean development formula, the centreline-diameter basis, and the setting of horizontal ends, hooks and laps
Spiral stirrups compute by geometric development (Pythagoras): one-turn true length l1 = root of [(pi D)2 + p2] (D the stirrup centreline winding diameter, p the pitch); one bar totals L = sum of (segment height / pitch) x one-turn length + horizontal ends + hook additions + laps - dense and plain zones must be computed segment by segment and summed. D = member diameter - 2 x cover + stirrup diameter (cover measured from main-bar skin to member face; where noted to the stirrup skin, D = d - 2c - dstirrup). The starting and ending horizontal turns each run not less than one and a half turns (three turns over both ends); each 135-degree hook adds 11.9d by trade convention; laps run not less than la or laE and not less than 300 mm, hooking the longitudinal bars. The G101 albums give the DETAILING only, never the length formula.
- ←
Measurement and quota pricing of post-installed (bonded) rebar: counted by piece, the 15d embedment-depth basis, and adjustment by each +/-1 cm sub-item (consumption standards and railway quota calibers)
Post-installed rebar quantities are counted by "piece" per the design drawings or approved construction scheme (SJG 181.2-2024 Clause 5.2.9); consumption-standard sub-items are compiled at 15d embedment depth (d = bar diameter), adjusted by corresponding increase/decrease sub-items when actual depth differs, and comprehensively cover drilling directions including drilling, hole cleaning, bar fabrication/installation, and in-hole adhesive injection (SJG 181.2-2024 Clause 5.1.9); Beijing DB11/T 2382-2024 provides "embedment depth 15d" and "each +/-1 cm" adjustment sub-items (both by piece); the railway building-repair quota's "post-installed bars" are per 10 pieces, tiered D10-D40 (TB/T 10831-2024, FY-1163-FY-1167). Post-installed bars not required by design are not listed separately (the process is in the corresponding rebar work content, GB/T 50854-2024 E.7.9; GB/T 50860-2024 A.15.11); design-required ones are listed under the member's rebar item with an embedment-requirement description.
- ←
Pricing steel ladders and the built-in ladders (steps) of inspection chambers: quantities by mass at design-shown dimensions, quota item attribution, and the "already inside the chamber item, not charged again" test
Steel ladders are measured by mass (t) at design-shown dimensions, without deducting holes and without adding welding rods, rivets or bolts (DB11/T 2382-2024 clause 4.7.17 item 1; municipal networks clause 7.4.17); steel ladders execute as "stepped steel ladders", embedded or welded-to-insert rolled-angle treads may execute as sundry steel members (clause 4.7.10). The steps / ladders inside inspection chambers are mostly already in the standard-chamber items' work content (e.g. D4-6-178 "chamber step and cover installation"; railway LY-441 "rung installation") and may not be listed again; where a separate item is truly needed, count in kg by design-shown weight (SJG 111.2-2022 clause 3.2.4); finished steps count by design-shown number (DB11/T 2382-2024 clause 9.3.5 item 6). Standard-chamber ladders are compiled in plastic-steel - differing designs convert the ladder material only, all else unchanged (SJG 181.4-2024 clause 3.1.3).
- ←
Overview of quantity take-off for construction works: basis, general rules and per-trade calculation methods
Quantity take-off rests on the four-tier basis "contract agreement -> design drawings -> approved project execution plan (construction methodology and site organization) -> appendix rules of the quota norms/measurement standards"; except where rules provide otherwise, all quantities are computed from the dimensions shown on the design drawings. General rules include: calculation per appendix rules (mandatory provisions of codes); the no-deduction threshold of single holes <=0.3 m2; significant figures of units of measurement (t/km three decimals; m/m2/m3/kg two; counts integer); and dual-track BOQ vs quota-norm quantities. Earthwork, concrete, reinforcement, formwork, masonry, waterproofing, finishes etc. each have standard algorithms.
- ←
Prestressed rebar (wire strand) quantity calculation: pre-tensioning vs post-tensioning calibers, curved segments by true length not projection, anchorage adjustments, and railway/highway/municipal differences
Prestressed rebar mass = design length x theoretical unit mass (t): pre-tensioning by member-dimension length; post-tensioning by design duct length adjusted per anchorage type (screw anchors -0.35m; bearing-plate bars +0.15/+0.30m; self-anchoring +0.35m; conical and JM/XM/OVM/QM anchors <=20m +1.0m, >20m +1.8m); curved segments by true arc length, not projection; field cutting length generally does not enter quantities (railway uses design cutting length; highway estimate caliber includes working lengths) — apply each sector's caliber separately.
- ←
Rebar quantity take-off: outer-surface or centreline length - the 2024 measurement standards expressly adopt the centreline, quota manuals old and new coexist, and how to resolve the difference
Current state of the rebar measurement convention: the 2024 BOQ measurement standards expressly adopt the centreline (GB/T 50854-2024 Table E.6.1; GB/T 50860-2024 Annex A.15.6); quota manuals coexist in old and new editions - Jiangsu 2026 and the new Shaanxi consumption quota adopt the centreline, Hunan 2025 consumption standard computes bent-up bars by outer-surface length without deducting elongation, while Beijing DB11/T 2382-2024 clause 4.6.9 and the like are silent. Resolution principles: BOQ quantities and quota quantities run on two separate tracks and must not be mixed; where the quota is silent, lock "outer surface or centreline" in the explanatory notes or the contract first; the summary-convention setting of the take-off software is a tool-level matter that does not change the applicable rule.
- ←
Railway 2024 quotas: linking the basic-quota rebar fabrication items (YY-30~34) with the budget-quota rebar fabrication-erection items, and preventing double pricing (TB/T 10821-2024)
The composite "rebar fabrication-erection / fabrication-tying-erection" items in the budget quotas (e.g., bridge volume QY-210~213 rebar cages) already include fabrication (sourced from basic-quota Chapter 3 YY-30~34) — adding the fabrication items again within the same BOQ item double-counts labor and plant. TB/T 10821-2024's general notes state that only "rebar transport, concrete mixing, concrete transport, and short-haul material transport" apply to estimate (budget) compilation; rebar fabrication is a compilation basis for the discipline budget quotas, not a pricing library; fabrication items exclude rebar consumption — when cited for missing items, add materials with operating waste, add 1.5% lap for non-coupled bars over 10 mm, and "mesh" fabrication applies only to bars <=10 mm.
- ←
Slab distribution reinforcement: position, function, and construction requirements (GB 50010-2010 (2015 edition) Clause 9.1.7; TB 10064-2019 Clause 4.1.5)
Distribution bars are placed perpendicular to the main bars on their inner side, fixing them, forming the mesh, distributing load, and resisting temperature-shrinkage stresses. GB 50010-2010 (2015 edition) Clause 9.1.7: one-way slab distribution steel per unit width preferably >= 15% of the main steel and ratio >= 0.15%, diameter preferably >= 6 mm and spacing <= 250 mm; under heavy concentrated loads, area increases and spacing <= 200 mm. TB 10064-2019 Clause 4.1.5: trafficable deck distribution bars >= 8 mm, sidewalks and trench covers >= 6 mm, area preferably >= 15% of main steel, distribution bars at bar bends; cantilever distribution >= 15% of transverse tension steel.
- ←
Cable-tray support (bearing frame) quantity calculation: measured in kg, count by support/hanger spacing, unit mass by section-steel theoretical mass
Cable-tray supports are measured by design finished mass in kg and itemized separately (GB/T 50856-2024, 3.0.10; SJG 181.7-2024, SJG 111.4-2022); counts follow support spacing — 1.5-3m horizontal, <= 2m vertical, densified at bends/branches/panel entries/expansion joints (GB 50397-2007, GB 50606-2010, GB/T 51239-2017, DB11/T 1832.17/19, etc.); unit mass = sum(member net length x unit theoretical mass), unit mass (kg/m) = section area (mm2) x 0.00785; factory supports (incl. seismic) count per piece/set without mass conversion.
- ←
Plan-drawing (pingfa) rebar terminology: the formal terms for top bars / bottom bars / additional bars / through bars, their atlas and code basis, and construction requirements
Top bars/bottom bars/additional bars are trade slang; the formal terms are upper (top) reinforcement (face bars in slabs), lower (bottom) reinforcement (bottom bars), and additional reinforcement (the code term is "transverse additional reinforcement"); through bars is a formal atlas/code term: at least two continuous longitudinal bars on the top and bottom over the full beam length (grades 1-2: diameter >= 14mm and >= 1/4 of the larger end section area; grades 3-4: >= 12mm) — "through" permits splices at suitable points. Pingfa (plan-integrated representation) rests on GB/T 50105-2010 Section 3.3 and the atlases approved by Jianke [2000] No. 157; the current general series is 22G101.
- ←
Theoretical mass per meter of rebar: values from GB 50666-2011 Appendix B Table B.0.1, the 0.00617 x d-squared shortcut, and lap-measurement reminders
Rebar mass per meter is taken by nominal diameter from GB 50666-2011 Appendix B Table B.0.1 (identical in GB 50010-2010 Appendix A), regardless of surface pattern (plain/ribbed); shortcut g = about 0.00617 x d^2 (d in mm; from density 7.85 g/cm3; phi20 -> 2.47 kg/m); measurement by "design length x unit theoretical mass" in tonnes, laps per the quota volume's rules (e.g., SJG 181.2-2024: one lap per 12m for phi<=10, per 9m for phi>10; mechanical splices not counted).
- ←
Quantity measurement of chair bars (iron horses, support rebar): the position that auxiliary rebar not required by the design is not measured separately, the setting method when no construction method statement exists (diameter / spacing / height), and per-piece weight conversion (theoretical mass 0.00617d2)
Chair bars, diagonal bracing bars, anti-floating bars, packing steel and other auxiliary rebar not required by the design are excluded from bill-of-quantities measurement (GB/T 50854-2024 Annex E, GB/T 50857-2024 Annex J.2.1, GB/T 50860-2024 Annex A.15.8); support rebar fixing positions where required by the design (including by code) is merged into the rebar quantities. Beijing DB11/T 2382-2024 absorbs chairs, supports and positioning bars into the rebar fabrication consumption (where data is unavailable, taken comprehensively at rebar wastage plus auxiliary rebar together equal to 5% of total rebar). Without a method statement, convert weight per piece: single-piece length about 2 x slab thickness + 0.2 m (120 mm slab = 0.44 m/piece), theoretical mass 0.00617d2 (d8 = 0.395, d10 = 0.617, d12 = 0.888 kg/m); at 1 piece/m2 with d8 about 0.174 kg/m2 (a 5000 m2 example totals 868.736 kg, about 0.869 t).