Rebar quantity calculation: length x theoretical weight, lap/merge/deduction rules, and post-tensioning length adjustments

Rebar quantity = design-drawn rebar length (centerline length) x unit theoretical weight (t). The BOQ caliber counts only laps specified by design and codes, not construction laps; the quota caliber, where drawings/codes do not specify, counts one lap per 12 m for diameters up to 10 mm and per 9 m above 10 mm, with mechanical connections not counted separately. Post-tensioned prestressed rebar lengths are adjusted by reserved duct length and anchorage type. Embedded iron parts are measured by ton, rebar splices by number, post-installed rebar by piece.

Applicable Codes

  • GB/T 50857-2024 市政工程工程量计算标准
  • GB/T 50860-2024 构筑物工程工程量计算标准
  • GB/T 50861-2024 城市轨道交通工程工程量计算标准
  • SJG 181.2-2024 市政工程消耗量标准 Vol. 2 桥涵工程
  • SJG 111.2-2022 城市地下综合管廊工程消耗量标准 Vol. 2
  • TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程

Topic Positioning

Rebar quantity calculation rules: design-drawn length x unit theoretical weight in tons, including laps, merge/deduction items, and post-tensioning length adjustments, distinguishing the BOQ/quota dual calibers.

Core Conclusions

  1. Quantity = design-drawn rebar centerline length x unit theoretical weight (t); the weight of holes <= 0.3 sqm is not deducted; the weight of welding rods, rivets, and bolts is not added.
  2. Laps: the BOQ counts only laps specified by design and codes; where the quota has no specification, count one lap per 12 m for diameters up to 10 mm and per 9 m above 10 mm; mechanical connections are not counted separately.
  3. Anchorage bars, precast lifting hooks, and fixing/support bars are merged; chair bars and shim irons are merged per design/codes/project execution plan (the BOQ does not count non-design measure bars). Embedded iron parts and bolts are measured by ton with supports merged; splices by number; post-installed rebar by piece.
  4. Post-tensioning adjusts by duct length: both-ends screw-rod anchorage -0.35 m (screw rods counted separately); upset-head insert plate at one end and screw rod at the other, by duct length; upset head at one end and tie-bar anchorage at the other +0.15 m; tie-bar anchorages at both ends +0.30 m; self-anchoring +0.35 m. Carbon steel wire with cone-type anchorage <= 20 m +1 m, > 20 m +1.8 m; upset-head anchorage +0.35 m; steel strand with JM/XM/OVM/QM <= 20 m +1 m, > 20 m +1.8 m.

Applicable Boundaries

The BOQ is governed by the GB/T 50854/50857/50860/50861-2024 series; the quota figures are cited from Shenzhen SJG 181.2-2024, SJG 111.2-2022, SJG 84-2020, and railway TB/T 10831-2024 — other regions follow the local current quota; the 12 m/9 m rule applies only when the drawings and codes do not specify laps.

Further Reading

BOQ: GB/T 50857-2024 Appendix J.2.1, GB/T 50860-2024 Appendices A.15.6/A.15.10, GB/T 50861-2024 Appendix B.9.3; quotas: SJG 181.2-2024 Clauses 5.2.1, 5.2.6; SJG 111.2-2022 Clause 3.2.3; TB/T 10831-2024 volume notes 10(12).