Engineering Knowledge Cards.
Confidence HighUpdated 2026-10-13

Computing rebar bending deductions (setting-out differences) and hook add-on lengths: methods, formulas and code bases

Cutting length = cumulative outside (envelope) dimensions - sum of bending deductions at each bend + sum of hook add-on lengths at each end, the cutting length computed on the bent centre-line length (DBJ50/T-331-2019 Article 8.2.4; DB 51/T 5046-2007 Article 3.1.4). The bending deduction is the tangent-length-minus-arc-length difference (GB 50162-92 Article 4.2.6 commentary); per bend, delta = 2r tan(a/2) - pi x r x a/180, r = (D+d)/2 being the centre-line bend radius; bars over 10 mm diameter correct per GB 50162-92 Article 4.2.6 - 45 and 90 degrees from Appendix 2, 135 degrees without correction. Hook add-on lengths read from GB 50162-92 Appendix 1 (hook growth), their end build-up (inside bend diameter D, straight tail length) per GB 50666-2011 Articles 5.3.4-5.3.6.

Applicable Codes

  • GB 50162-92 道路工程制图标准 第4.2.6条、附录一附表1.1、附录二附表2.1
  • DB 51/T 5046-2007 混凝土结构工程施工工艺规程 第3.1.4条、第3.3.2条表3.3.2
  • DBJ50/T-331-2019 轨道交通U形梁结构技术标准 第8.2.4条
  • GB 50666-2011 混凝土结构工程施工规范 第5.3.4、5.3.5、5.3.6条
  • GB 50204-2015 混凝土结构工程施工质量验收规范 第5.3.3条
  • DB11/T 1832.3-2021 建筑工程施工工艺规程 第3部分 第12.4.7条
  • TB 10064-2019 铁路工程混凝土配筋设计规范 第3.4.1~3.4.3条、Table 3.4.2
  • GB/T 50860-2024 构筑物工程工程量计算标准 App. A.15.6
  • T/BIAS 13-2025 预制混凝土构件生产与运输标准 第6.3.1条
  • DB/T 29-75-2018 天津市城市桥梁工程施工及验收标准 第5.2.4条

Scope of the question

The two opposite, easily confused quantities in rebar fabrication (cutting): the bending deduction (setting-out difference, to subtract) and the hook add-on length (to add) - their bases, formulas, end-build-up values and code references.

Core conclusions

1. Basis and formula Cutting length = cumulative outside (envelope) dimensions of the bar - sum of bending deductions + sum of hook add-on lengths, computed on the bent centre-line length.

  • DBJ50/T-331-2019 Technical Standard for Rail Transit U-beam Structures, Article 8.2.4: before cutting, check grade, size, dimensions and count, compute cutting lengths and compile bar lists; cutting length follows the bent centre-line length, allowing for hook add-ons and bending deductions.
  • DB 51/T 5046-2007 Article 3.1.4: cutting length generally follows the cumulative outline dimensions on the design or standard drawings, including setting-out differences, inclined lengths of bent bars and end hook growth.
  • Quantity basis in kind: GB/T 50860-2024 Appendix A.15.6 - the drawn rebar length in the rules means the centre-line length.
  • T/BIAS 13-2025 Article 6.3.1 commentary: cut strictly per the bar list, fixing bending deductions, hook add-ons and stirrup adjustments for precise, rational cutting.

2. Computing the bending deduction GB 50162-92 Standard for Road Engineering Drawings, Article 4.2.6: for bars over 10 mm diameter, the bend length shall be corrected; 45- and 90-degree corrections per Appendix 2; other angles draw the detail with the tangent-arc difference shown. Commentary: ignoring the correction (tangent minus arc) causes fabrication error and waste; at 135 degrees the arc is added directly, so no 135-degree correction exists. Per bend: with a the bend angle, D the inside bend (mandrel) diameter and d the bar diameter, centre-line radius r = (D+d)/2: delta = 2r tan(a/2) - pi x r x a / 180 - the sum of the two tangents less the centre-line arc. Example: plain bar, 90-degree bend, D = 2.5d, r = 1.75d: delta = 2 x 1.75d x tan45 - pi x 1.75d x 90/180 = 3.50d - 2.75d = 0.75d, deducting 0.75d per 90-degree bend. A different D changes the deduction. D per GB 50666-2011 Code for Construction of Concrete Structures, Article 5.3.4: plain bars not under 2.5d; 335 / 400 MPa ribbed not under 4d; 500 MPa ribbed under 28 mm not under 6d, 28 mm and above not under 7d; top-storey end-node beam top and column outer bars bending at the node corner not preferably under 12d (under 28 mm) / 16d (28 mm and above); stirrup bends also not under the main bar diameter (per lapped or bundled layout). Quick tables: DB 51/T 5046-2007 Article 3.3.2 Table 3.3.2 (bending deductions, d the diameter); GB 50162-92 Appendix 2 (standard bend corrections, Table 2.1, 45 and 90 degrees, from its formula summary).

3. Hook add-on lengths (end build-up parameters)

  • GB 50162-92 Appendix 1 (hook growth), Table 1.1 - values for drawing / cutting.
  • DB 51/T 5046-2007 Article 3.3.2: HPB235 ends take 180-degree hooks, D not under 2.5d, straight tail preferably not under 3d; HRB335 / HRB400 135-degree hooks, D not under 4d, tail per design; bends up to 90 degrees, D not under 5d; cold-rolled ribbed may omit hooks, 90 / 135-degree bends D not under 5d. Stirrup hook D also not under the main bar diameter; angles not under 90 degrees generally, 135 degrees for seismic; tails not under 5x (general) / 10x (seismic) stirrup diameter.
  • GB 50666-2011 Article 5.3.5: 180-degree hooks on plain bars with tails not under 3d; Article 5.3.6: stirrup and tie hooks - general members not under 90 degrees with tails not under 5x diameter; seismic or specially required members not under 135 degrees with tails not under the greater of 10x diameter and 75 mm; circular stirrup laps not under the tension anchorage with both ends hooked not under 135 degrees; single-leg stirrups and wall / slab ties both ends not under 135 degrees (or one 135 one 90 for wall / slab ties), tails not under 5x diameter. GB 50204-2015 Article 5.3.3 acceptance agrees.
  • DB11/T 1832.3-2021 Article 12.4.7: HPB300 180-degree hooks, D not under 2.5d (3.5d in lightweight concrete), tails preferably not under 3d; HRB400 90 / 135-degree bends D not under 4d; HRB500 under 28 mm D not under 6d, 28 mm and above 7d; end-node corner bends 12d / 16d; cocked-bar mid bends D not under 5d; seismic and torsion stirrups 135 degrees, tails not under the greater of 10x and 75 mm.
  • TB 10064-2019 Article 3.4.2 Table 3.4.2 end hooks: 180 degrees (HPB300) D not under 2.5d, tails not under 3d (tension and constructional); 135 degrees (HRB400) D not under 4d (5d over 25 mm), tails not under 5d tension / 3d constructional; (HRB500) D not under 6d (7d over 25 mm), tails not under 6d; 90 degrees (HRB400) D not under 4d (5d), tails not under 10d; (HRB500) D not under 6d (7d), tails not under 12d. Article 3.4.3: save welded-closed stirrups, stirrup ends hook, hook D exceeding the enclosed main bar diameter and per Table 3.4.2; tails not under 5x stirrup diameter.
  • DB/T 29-75-2018 Article 5.2.4: cutting lengths per diameter and hook form plus elongation at bending; Table 5.2.4 gives hook elongations by form.

Applicability limits

  • The formulas rest on the cumulative outside-dimension basis: drawings marked outside deduct bending and add hooks to reach the centre line; where the drawing / measurement rules already say centre line (e.g. GB/T 50860-2024 A.15.6), no double deduction.
  • The GB 50162-92 Article 4.2.6 correction is only for bars over 10 mm; 135-degree bends carry no correction (arc added directly); angles other than 45 / 90 standard bends draw details with the tangent-arc difference - no standard-table borrowing.
  • Deductions and add-ons vary with D, taken per the executed code (concrete works per GB 50666-2011 5.3.4). Handbook and local quick tables may differ - match the executed code and quota version.
  • Railway works follow TB 10064-2019 Table 3.4.2 (bracket values over 25 mm); highway, municipal and local standards differ slightly in D and tails - follow the project's standards.
  • Stirrup (and tie) cutting adds stirrup adjustments per the relevant standard or manual; complex shapes sample and trial-bend before batch cutting.

Further reading

  • GB 50162-92 Appendix 1 Table 1.1 (hook growth); Appendix 2 Table 2.1 and the formula summary; Article 4.2.6.
  • DB 51/T 5046-2007 Articles 3.3.2 (Table 3.3.2) and 3.1.4.
  • GB 50666-2011 Articles 5.3.4-5.3.6; GB 50204-2015 Article 5.3.3.
  • DB11/T 1832.3-2021 Article 12.4.7; T/BIAS 13-2025 Article 6.3.1; DB/T 29-75-2018 Article 5.2.4.
  • TB 10064-2019 Articles 3.4.1-3.4.3 and Table 3.4.2; GB/T 50860-2024 Appendix A.15.6; DBJ50/T-331-2019 Article 8.2.4.

Keywords

  • 钢筋弯曲调整值
  • 弯折量度差值
  • 弯钩增加长度
  • 钢筋下料长度
  • 弯弧内直径
  • 钢筋弯钩增长
  • 钢筋配料
  • 中心线长度