Cutting length of rectangular closed stirrups in beams (columns) for bar fabrication (outside perimeter + hook allowance - bend deduction), selection of seismic hooks, concrete cover values, and stirrup count build-up over the densified zones at the beam ends
The cutting length of a rectangular closed stirrup is L = 2[(b - 2c) + (h - 2c)] + n x (1.9d + Lp) - B, with n = 2, seismic Lp = max(10d, 75mm) and non-seismic Lp = 5d, and for a rectangular stirrup B is the total bend deduction of four 90-degree corners. Here c is the concrete cover to the outermost layer of steel (the stirrup), so b - 2c and h - 2c give the outside dimensions of the stirrup directly (GB 50010-2010 clause 8.2.1; commentary on GB 50204-2015 clause 5.3.5). Counts are summed segment by segment over the beam-end densified zones: grade 1 densified length max(2hb, 500), grades 2 to 4 max(1.5hb, 500) (GB 50011-2010 table 6.3.3); the first stirrup sits no more than 50mm from the joint edge (GB 50010-2010 clause 11.3.9), and the spacing in the non-densified zone is no more than twice that in the densified zone.
Applicable Codes
- GB 50666-2011 混凝土结构工程施工规范 第5.3.6条
- GB 50204-2015 混凝土结构工程施工质量验收规范 第5.3.3条、第5.3.5条及Table 5.3.5
- GB 50010-2010(2015年版)混凝土结构设计规范 第8.2.1条及Table 8.2.1、第11.1.8条、第11.3.9条
- GB 50011-2010 建筑抗震设计规范 第6.3.3条及Table 6.3.3
- GB 55002-2021 建筑与市政工程抗震通用规范 第5.2.2条
- GB 50162-92 道路工程制图标准 附录二 附表2.1(钢筋标准弯折修正表)
- DB 51/T 5046-2007 混凝土结构工程施工工艺规程 第3.3.2条及表3.3.2
What this card covers
The fabrication (bar bending schedule) cutting length and stirrup count algorithms for rectangular closed stirrups in beams and columns: the full cutting length formula and its variables, selection between seismic and non-seismic hooks, the effect of the cover c on the outside dimensions of the stirrup, the values taken for the hook allowance and the bend deduction, and the beam-end densified zone length with segment-by-segment stirrup counts over the 'densified + non-densified' zones. This is the fabrication take-off basis, upstream and downstream of the rebar quantity measurement basis (length x unit theoretical mass).
Core conclusions
1) The full cutting length formula (rectangular closed stirrup, two legs; four-leg stirrups decompose per the design details)
L(cutting) = 2[(b - 2c) + (h - 2c)] + n x (1.9d + Lp) - B
| Variable | Meaning | Source/unit |
|---|---|---|
| b, h | beam (column) section width and depth | design, mm |
| c | concrete cover to the outermost layer of steel (the stirrup) | GB 50010-2010 clause 8.2.1, table by exposure class, mm |
| d | stirrup bar diameter | design, mm |
| n | number of hooks, 2 for a closed stirrup | - |
| Lp | straight length of the hook | seismic max(10d, 75mm); non-seismic 5d |
| B | total bend deduction = number of corners x deduction per bend (a rectangular stirrup has four 90-degree corners) | fabrication tables (DB 51/T 5046-2007 table 3.3.2; GB 50162-92 Annex II table 2.1) |
The leading term 2[(b - 2c) + (h - 2c)] is the outside perimeter of the stirrup, not the inside perimeter. Basis: the commentary on GB 50010-2010 clause 8.2.1 - 'for durability against carbonation of the concrete, depassivation and corrosion of the steel, the cover is measured no longer to the edge of the longitudinal steel but to the edge of the outermost layer of steel (including stirrups, structural bars and distribution bars)'; and the commentary on GB 50204-2015 clause 5.3.5 - 'GB 50010-2010 has defined the concrete cover by reference to the outermost layer of steel (the stirrup), so the section size minus twice the cover gives the outside dimensions of the stirrup directly; this clause therefore replaces the former inside dimensions of the stirrup with its outside dimensions'. If c is habitually taken to the edge of the longitudinal steel (the former basis), what is computed is the inside dimension and must be converted before the formula is applied; the two bases must not be mixed.
2) Cover values (GB 50010-2010 table 8.2.1, 50-year design working life, mm)
| Exposure class | Slabs, walls, shells | Beams, columns, bars |
|---|---|---|
| I | 15 | 20 |
| IIa | 20 | 25 |
| IIb | 25 | 35 |
| IIIa | 30 | 40 |
| IIIb | 40 | 50 |
Notes to the table: where the concrete strength grade is no more than C25, the tabulated cover values increase by 5mm; for structures with a 100-year design working life, the cover to the outermost layer of steel is no less than 1.4 times the tabulated value; the cover to stressed steel is no less than the nominal diameter d of the bar; reinforced concrete foundations should have a concrete blinding layer, and the cover of steel in foundations is measured from the top of the blinding and is no less than 40mm.
3) Hooks: seismic 135 degrees / max(10d, 75mm) versus non-seismic 90 degrees / 5d
GB 50666-2011 clause 5.3.6 (paragraph 1), original: 'for general structural members, the bend angle of stirrup hooks shall be no less than 90 degrees and the straight length after the bend no less than 5 times the stirrup diameter; for structural members with seismic requirements or special design requirements, the bend angle shall be no less than 135 degrees and the straight length after the bend no less than the larger of 10 times the stirrup diameter and 75mm'; paragraph 2, for circular stirrups, 'the lap length shall be no less than the tensile anchorage length, and both ends shall carry hooks of no less than 135 degrees ... for structural members with seismic requirements, no less than the larger of 10 times the stirrup diameter and 75mm'; paragraph 3: 'where tie bars act as single-leg stirrups in the composite stirrups of beams and columns, or as ties between the side bars of beams, both end hooks shall bend no less than 135 degrees ... where tie bars act as ties in shear walls, floor slabs and the like, the end hooks may be 135 degrees at one end and 90 degrees at the other, with a straight length after the bend no less than 5 times the tie diameter'.
GB 50204-2015 clause 5.3.3 (acceptance side), original: 'for general structural members, the bend angle of stirrup hooks shall be no less than 90 degrees and the straight length after the bend no less than 5 times the stirrup diameter; for structural members with seismic requirements or special design requirements, the bend angle shall be no less than 135 degrees and the straight length after the bend no less than 10 times the stirrup diameter'; inspection frequency 'not fewer than 3 pieces per work shift for the same type of steel processed on the same equipment'; method 'measuring'. Note that the acceptance clause states only 10d and omits the 75mm floor.
GB 50010-2010 clause 11.1.8 (design side), original: 'stirrups should be welded closed stirrups, continuous spiral stirrups or continuous composite spiral stirrups. Where non-welded closed stirrups are used, the ends shall carry 135-degree hooks with a straight length beyond the hook of no less than 10 stirrup diameters; within the lap length of the longitudinal steel the stirrup spacing shall be no more than 5 times the smaller diameter of the lapped bars, and preferably no more than 100mm.'
Selection basis (commentary, original): 'structural members with seismic requirements mean structural members for which a seismic grade is specified in the design drawings and the relevant standards'; 'special design requirements in this clause mean members in torsion or in combined bending-shear-torsion states, and also columns whose total longitudinal steel ratio exceeds 3%'. Hence: where the drawings assign a seismic grade, control at 135 degrees and Lp = max(10d, 75mm) (d6 -> 75mm, d8 -> 80mm, d10 -> 100mm); general members at 90 degrees and Lp = 5d. Fabrication controlled per GB 50666-2011 by 'the larger of 10d and 75mm' is stricter than the acceptance basis and never oversteps it.
4) Hook allowance and inner bend diameter The 135-degree (and 90-degree) hook allowance follows the common fabrication formula 1.9d + Lp: the allowance consists of the curved part (1.9d) and the straight part (Lp), with max(10d, 75mm) substituted for Lp in the seismic case. DB 51/T 5046-2007 clause 3.3.2 paragraph 7 requires the inner bend diameter of stirrup hooks, beyond satisfying paragraph 6 of the same clause, to be no less than the diameter of the stressed bars; paragraph 6: for HPB bars with 180-degree end hooks 'the inner bend diameter D shall be no less than 2.5 times the bar diameter d, and the straight length of the hook preferably no less than 3 times the diameter'; where HRB335 and HRB400 bars need 135-degree end hooks, 'D no less than 4 times d, and the straight length as required by the design'; for bends of no more than 90 degrees, 'D no less than 5 times d'; cold-rolled ribbed bars may omit end hooks, and where 90- or 135-degree bends are needed, D is no less than 5d.
5) Bend deduction (measuring difference) by angle band The deduction for one 90-degree bend: the DB 51/T 5046-2007 table 3.3.2 basis takes 2d (a rectangular stirrup with four 90-degree corners totals 4 x 2d = 8d); GB 50162-92 Annex II table 2.1, 'standard bend correction table for steel bars', computed from the formula summary table, gives 1.29d for a 90-degree bend of a deformed bar (with figure 1.1, the sketch of standard bar bends). The two tables differ in basis; one worked example must take one set throughout, never mixing them. The correction values for the 30, 45, 60 and 135-degree bands must be read band by band from GB 50162-92 Annex II table 2.1 or from the measuring-difference table of a fabrication manual; when computing the cutting length, 'the bend deduction of the steel shall be deducted' (DB 51/T 5046-2007 clause 3.3.2 paragraph 3).
6) Beam-end densified zones and count build-up GB 50011-2010 clause 6.3.3: the densified-zone length, maximum spacing and minimum diameter of stirrups at the beam ends follow table 6.3.3; the notes read '1 d is the longitudinal bar diameter and hb is the beam section depth' and '2 where stirrup diameters exceed 12mm, with no fewer than 4 legs and leg spacing no more than 150mm, the maximum spacing for grades 1 and 2 may be relaxed, but not beyond 150mm'; where the tension steel ratio at the beam end exceeds 2%, the tabulated minimum stirrup diameter increases by 2mm. Densified length: grade 1 takes max(2hb, 500)mm, grades 2, 3 and 4 take max(1.5hb, 500)mm; grade 1 densified-zone spacing takes min(hb/4, 6d, 100), where d is the longitudinal bar diameter (not the stirrup diameter) - the commonest error here; substituting the stirrup diameter yields absurd spacings such as 48mm.
Companion detailing (GB 50010-2010 clause 11.3.9): 'The first stirrup placed at the beam end shall be no more than 50mm from the edge of the frame joint. The stirrup spacing in the non-densified zones should not exceed twice the stirrup spacing in the densified zones.'
Count build-up (a set of layout formulas that can be applied directly):
- densified-zone length Ld (one run at each end), non-densified length Lu = clear span Ln - 2 x Ld;
- stirrups in one end densified zone n1 = ceil[(Ld - 50)/sd] + 1 (laid out from the first stirrup 50mm from the joint edge);
- stirrups in the non-densified zone n2 = ceil(Lu/su) - 1 (dropping the one step overlapping the last stirrup of the adjoining densified zones at each end);
- total stirrup count N = 2 x n1 + n2.
7) Worked example (beam 300mm x 600mm, d8 stirrups, seismic grade 1, exposure class I, C30 and above, clear span 6000mm)
c = 20 -> outside width 300 - 2 x 20 = 260, outside depth 600 - 2 x 20 = 560, outside perimeter 2 x (260 + 560) = 1640; Lp = max(10 x 8, 75) = 80; one hook 1.9 x 8 + 80 = 95.2, two hooks 190.4; bend deduction 4 x 2 x 8 = 64; cutting length L = 1640 + 190.4 - 64 = 1766.4mm (about 1.77m). Checked on the GB 50162-92 basis: 1640 + 190.4 - 4 x 1.29 x 8 = 1789.1mm, for basis comparison only. Counts: Ld = max(2 x 600, 500) = 1200, sd = 100 and su = 200 -> n1 = ceil[(1200 - 50)/100] + 1 = 13; Lu = 6000 - 2400 = 3600, n2 = ceil(3600/200) - 1 = 17; N = 2 x 13 + 17 = 43 stirrups.
Applicable boundaries
- Applies only to rectangular closed stirrups (including single-leg ties used in composite stirrups, with both 135-degree ends counted separately); welded closed stirrups and continuous spiral or continuous composite spiral stirrups have no end hooks and are outside this formula.
- The formula holds where c is the cover to 'the edge of the outermost layer of steel (the stirrup)'. Where the drawings give the cover to the edge of the longitudinal steel under the former basis, or give the inside dimensions of the stirrup directly, convert first and then apply the formula.
- The bend deduction bands vary with the standard and the inner bend diameter (2d and 1.29d are two different bases); adopt one set whole; measuring-difference tables from different sources must not be mixed in one computation.
- Seismic hook selection follows whether the design drawings/standards assign a seismic grade, not any subjective view of 'whether there is seismic action'; in non-seismic members, members in torsion or combined bending-shear-torsion and columns whose total longitudinal steel ratio exceeds 3% are still controlled at 135 degrees and max(10d, 75mm).
- GB 55002-2021 clause 5.2.2 provides that 'the potential plastic hinge zones of frame beams and frame columns shall have densified stirrups ...' (a principle); the mandatory effect of GB 50011-2010 table 6.3.3 has been superseded by that general code, but its detailing values remain the technical basis for design and fabrication; stricter design documents prevail.
- Cutting length is the fabrication length; it excludes lap splices, construction wastage and couplers; quantity measurement follows the BOQ/quota rules separately (length shown on the design x unit theoretical mass); the two are not interchangeable.
- The 50mm start distance and the merging of the last non-densified stirrup in the count formulas must be checked against the actual layout; in densified-zone spacing the 6d uses the longitudinal bar diameter.
Further reading
- GB 50666-2011 Code for Construction of Concrete Structures, clause 5.3.6 and its commentary (stirrup and tie hook details, selection for seismic/special design requirements); inner bend diameters in clause 5.3.4 of the same code.
- GB 50204-2015 Code for Acceptance of Construction Quality of Concrete Structures, clause 5.3.3 (hook acceptance, sampling frequency and method), clause 5.3.5 and table 5.3.5 (tolerances on fabrication shape and size, stirrups accepted on outside dimensions).
- GB 50010-2010 (2015 edition) Code for Design of Concrete Structures, clause 8.2.1 and table 8.2.1 with commentary (cover to the outermost steel layer, 1.4 times for 100 years, plus 5mm for C25 and below, no less than 40mm from the top of the blinding in foundations); clause 11.1.8 (135-degree hooks on non-welded closed stirrups, straight length no less than 10d); clause 11.3.9 (first stirrup no more than 50mm from the joint edge, non-densified spacing no more than twice the densified, stirrup area ratio along the beam length).
- GB 50011-2010 Code for Seismic Design of Buildings, clause 6.3.3 and table 6.3.3 (beam-end densified length, maximum spacing, minimum diameter and the notes) with commentary (damage concentrates within 1.5 to 2.0 times the beam depth; minimum stirrup diameter plus 2mm where the steel ratio exceeds 2%).
- GB 55002-2021 General Code for Seismic Resistance of Buildings and Municipal Works, clause 5.2.2 (densified stirrups in potential plastic hinge zones; principle of ductility measures).
- GB 50162-92 Standard for Road Engineering Drawings, Annex II table 2.1 'standard bend corrections for steel bars' and figure 1.1 'sketch of standard bar bends' (the source for reading measuring differences band by band).
- DB 51/T 5046-2007 Technical Specification for Construction Technology of Concrete Structures Works, clause 3.3.2 paragraphs 2, 6 and 7 and table 3.3.2 'steel bend deductions', figures 3.3.2-1 to 3 (deduction at cutting, inner bend diameters for each steel grade and the stirrup hook rules).
- The general derivation of the bend deduction (measuring difference) and the principle of the hook allowance: see the related thematic cards.