Theoretical mass per meter of rebar: values from GB 50666-2011 Appendix B Table B.0.1, the 0.00617 x d-squared shortcut, and lap-measurement reminders
Rebar mass per meter is taken by nominal diameter from GB 50666-2011 Appendix B Table B.0.1 (identical in GB 50010-2010 Appendix A), regardless of surface pattern (plain/ribbed); shortcut g = about 0.00617 x d^2 (d in mm; from density 7.85 g/cm3; phi20 -> 2.47 kg/m); measurement by "design length x unit theoretical mass" in tonnes, laps per the quota volume's rules (e.g., SJG 181.2-2024: one lap per 12m for phi<=10, per 9m for phi>10; mechanical splices not counted).
Applicable Codes
- GB 50666-2011 混凝土结构工程施工规范(App. B Table B.0.1)
- GB 50010-2010 混凝土结构设计规范(App. A)
- SJG 181.2-2024 市政工程消耗量标准 Vol. 2 桥涵工程(5.2.1 钢筋工程)
- GB/T 50854-2024 房屋建筑与装饰工程工程量计算规范(清单量口径)
- GB/T 1499.2-2018 钢筋混凝土用钢 第2部分:热轧带肋钢筋
Topic Positioning
The most reused single page in rebar cost work: the phi6-phi50 mass-per-meter table (with source), the 0.00617 x d^2 shortcut, and the lap and measurement bases to mind after lookups - for estimates, settlements, and checking rebar contents.
Core Conclusions
"The computational cross-sectional areas and theoretical masses of rebar shall comply with Table B.0.1." - GB 50666-2011 "Code for construction of concrete structures" Appendix B Table B.0.1 (same in GB 50010-2010 Appendix A). Mass is by nominal diameter regardless of pattern. Common values (kg/m): phi6=0.222, phi8=0.395, phi10=0.617, phi12=0.888, phi14=1.21, phi16=1.58, phi18=2.00, phi20=2.47, phi22=2.98, phi25=3.85, phi28=4.83, phi32=6.31, phi36=7.99, phi40=9.87, phi50=15.42.
Shortcut: mass/m = about 0.00617 x d^2 (d nominal, mm), from area pi x d^2/4 x 7.85 g/cm3 / 1000; e.g., phi20 -> 0.00617 x 400 = 2.47 kg/m; for small bars, memorize 0.222/0.395/0.617/0.888 and scale. Reverse: meters per tonne = 1000 / mass-per-meter.
Measurement reminders (per the applicable quota volume):
- Fabrication and installation by "design length x unit theoretical mass" in tonnes; lap length included.
- Quota basis (SJG 181.2-2024 Vol.2 bridges, 5.2.1): where drawings/codes do not show laps, one lap per 12m for phi<=10 and per 9m for phi>10; mechanical (straight-thread/sleeve) splices add no lap quantity.
- BOQ basis (GB/T 50854 series 2024): only design net quantities (anchorage and design laps included); construction laps and non-design bars are absorbed by quota consumptions - the two ledgers differ by design; do not mix.
- Do not add loss twice: quota consumptions already include fabrication/tying loss - follow item consumptions; BOQ quantity carries no extra loss.
- Plain (HPB300) and ribbed (HRB400/500E) take different items, tiered by diameter within a grade - not one tier for all; price seismic-E bars distinctly.
Applicable Boundaries
- Table values are "computational/theoretical" masses (nominal diameter, 7.85 g/cm3), not weighed masses: product standards (e.g., GB/T 1499.2) allow negative deviation of actual vs theoretical per bar, so weighed batches may run light; settlement by theoretical or weighed mass must be agreed in advance in the contract/tender documents - a classic rebar dispute.
- Lap rules differ by region/volume (per 12m/9m is Shenzhen municipal SJG 181.2-2024 and only a default when design is silent); whether mechanical splices or joints are separate items follows the volume; obsolete sizes like phi6.5 on old drawings - convert or borrow adjacent items.
- The table gives single-bar mass per meter; multi-bar areas and finer tiers require the full standard table.
Further Reading
- GB 50666-2011 Appendix B Table B.0.1 (nominal diameters, areas, computational areas, theoretical masses); GB 50010-2010 Appendix A.
- SJG 181.2-2024 Vol.2 Sec. 5.2.1 (lap default); BOQ basis in GB/T 50854-2024 and the 2024 list standards.
- Splice-zone lengths and percentages: GB 50666-2011 Clause 5.4.4, JGJ 107-2016 Clause 4.0.3; loss baselines from the applicable quota consumptions.
Keywords
- 钢筋理论重量
- 钢筋每米重量
- 0.00617
- GB 50666-2011
- Appendix B
- 表B.0.1
- 钢筋搭接
- rebar quantities