Splice zone length for mechanically spliced/welded longitudinal structural rebar (35d and not less than 500mm) and splice area percentage limits (GB 50666-2011 5.4.4, JGJ 107-2016 4.0.3)

When mechanical/welded splices are staggered within one member, the splice zone length L = 35d and shall not be less than 500mm, d being the smaller diameter of the two connected bars (GB 50666-2011 cl. 5.4.4; JGJ 107-2016 cl. 4.0.3); splices whose midpoints fall within the zone belong to the same splice zone; tension splice area percentage should not exceed 50% and compression is unlimited (JGJ 107 also by grade: high-stress locations grade III <=25%, grade II <=50%, grade I essentially unlimited); members directly bearing dynamic/repeated loads: mechanical splices shall not exceed 50% and welding is unsuitable. Beijing DB11/T 1832.3-2021 cl. 2.3.8 words it as "35d of the larger diameter longitudinal structural rebar", inconsistent with the national "smaller diameter" caliber — acceptance follows the national standard and the design drawings.

Topic Positioning

For longitudinal structural rebar with mechanical or welded splices in concrete structures: computation of the splice zone length when splices are staggered within one member (35d and not less than 500mm) and the splice area percentage limits, per GB 50666-2011 cl. 5.4.4 and JGJ 107-2016 cl. 4.0.3, flagging the diameter-caliber difference in Beijing local standard DB11/T 1832.3-2021 cl. 2.3.8.

Core Conclusions

  1. Splice zone length: L = 35d and not less than 500mm; d is the smaller diameter of the two connected bars (GB 50666-2011 cl. 5.4.4 item 2: the splice zone length is 35d and not less than 500mm; JGJ 107-2016 cl. 4.0.3 same caliber: "where bars of different diameters are connected, compute by the smaller-diameter bar"). Where splice zone lengths computed for different connected bars within one member differ, take the larger (GB 50666-2011 commentary).
  2. Same-zone determination: any splice whose midpoint lies within the splice zone length belongs to the same splice zone (judge by the splice midpoint, not the full splice length).
  3. Splice area percentage = ratio of the cross-sectional area of spliced longitudinal rebar within the zone to the total cross-sectional area of all longitudinal rebar (GB 50666-2011 cl. 5.4.4 item 3): tension splices should not exceed 50%; compression splices may be unlimited; tension mechanical splices in slabs, walls and columns and tension splices at connections of precast concrete members may be relaxed per actual conditions; welding is unsuitable in members directly bearing dynamic loads, and mechanical splices there shall not exceed 50%.
  4. JGJ 107-2016 cl. 4.0.3 (for mechanical splices, by splice grade): splices should be located where tensile stress of the rebar is low; at high-stress locations, grade III splice area percentage within one zone shall not exceed 25%, grade II not 50%, grade I unlimited except the cases of items 2 and 4; splices should avoid the stirrup-densified zones at beam ends and column ends of seismic frames; where unavoidable, grade II splices or grade I splices with area percentage not over 50% shall be used; unlimited at low tensile stress locations or for longitudinal compression rebar; not over 50% in members directly bearing repeated loads.
  5. Computation examples (L = max(35d, 500)): d=14mm -> 35d=490mm, take 500mm (governed by the minimum); d=20mm -> 700mm; d=25mm -> 875mm; d=32mm -> 1120mm. Critical diameter about 14.3mm — for common d>=16mm, 35d always exceeds 500mm; only d<=14mm is governed by the 500mm minimum.
  6. Beijing local difference: DB11/T 1832.3-2021 Construction Work Procedure Part 3: Concrete Structure Works, cl. 2.3.8 item 1 states "the connection zone length shall be 35d of the larger diameter longitudinal structural rebar and not less than 500mm", inconsistent with the national "smaller diameter" rule; for construction acceptance, follow GB 50666-2011 / GB 50204-2015 (smaller diameter) and the design drawings — computing the zone by the smaller diameter is more conservative and satisfies both codes. The same clause also provides: splices of beam top continuous bars should lie within the middle 1/3 of the span, non-frame beams within the 1/4 near supports, and the splice area percentage within one zone should not exceed 50%.

Applicable Boundaries

  • Applies to mechanical (parallel-thread, swaged coupler etc.) and welded splices of longitudinal structural rebar; not to tied laps — the lap splice zone length is 1.3 times the lap length, and the lateral clear spacing of lap splices shall not be less than the bar diameter nor 25mm (DB11/T 1832.3-2021 cl. 2.3.8 item 2).
  • Taking d as the smaller diameter is the national caliber of GB 50666-2011 and JGJ 107-2016; in Beijing, note DB11/T 1832.3-2021's "larger diameter" wording differs — follow the national standard and design documents.
  • Precast concrete structures are integral structures assembled from precast members; batch-wise staggering is impossible at member connections, and 100% same-section connection is common; the tension splice percentage may be relaxed, but measures shall ensure connection quality (GB 50666-2011 commentary).
  • The two codes' percentage limits differ in focus and shall both be met: GB 50666-2011 by tension/compression (tension <=50%, compression unlimited); JGJ 107-2016 by splice grade (grade I essentially unlimited, grade II <=50%, grade III <=25%); splices should avoid stirrup-densified zones at seismic frame beam and column ends.

Further Reading

  • GB 50666-2011 cl. 5.4.4 and commentary (setting of mechanical/welded splices: batch-wise staggering, 35d and >=500mm, midpoint determination, percentage limits).
  • JGJ 107-2016 cl. 4.0.3 (splice application and grade percentages); Chapter 7 of that specification covers site inspection and acceptance batches (see also knowledge card card_177f6a1e-fb18-4960-b9fe-cf5ee36cf8f8).
  • Acceptance level: GB 50204-2015 cl. 5.4.6.
  • DB11/T 1832.3-2021 cl. 2.3.8 (Beijing local work procedure; note the larger/smaller diameter caliber difference from the national standard).
  • Railway works follow TB 10424-2018 Standard for Constructional Quality Acceptance of Railway Concrete Engineering, cl. 5.4.3 (tension-zone splice percentage of flexural members <=50%, axially tensioned members <=25%; splice zone length 35d and >=500mm).

Keywords

  • 机械连接
  • 接头等级
  • I级接头
  • 接头面积百分率
  • 35d
  • 连接区段
  • JGJ 107-2016
  • 接头应用