Splice location and no-splice zone (stirrup densification zone) lengths for frame column longitudinal bars: no less than Hn/3 above the fixed base, max(Hn/6, hc, 500)mm at floor levels, stagger of 35d and no less than 500mm in the same splice zone, splice area percentage bands, plus anchorage in foundations and the basis of staged cutting lengths for column bars
Column longitudinal bars should pass through the intermediate and end joints of intermediate floors, with splices located outside the joint zone (GB 50010-2010 Clause 9.3.6); in structures with seismic precautionary requirements splices should avoid the stirrup densification zones at beam and column ends and lapping must not be used there (GB 50666-2011 Clause 5.4.1). The densification zone, i.e. the no-splice zone, is taken as the largest of the long side of the column section (or the diameter of a circular column), one sixth of the clear column height, and 500mm; at the root of the bottom storey it is no less than one third of the clear height of that storey (GB 50010-2010 Clause 11.4.14). Same splice zone: mechanical and welded splices 35d and no less than 500mm (d is the smaller diameter of the two connected bars), lapped splices 1.3 times the lap length; the splice area percentage in tension should not exceed 50%, in compression it is not limited, and lapped splices in columns should not exceed 50% (mechanical splices are further banded under JGJ 107-2016: Grade III 25% / Grade II 50% / Grade I not limited).
Applicable Codes
- GB 50010-2010(2015年版)混凝土结构设计规范 第8.4.3条、第9.3.6条、第11.4.14条
- GB 50666-2011 混凝土结构工程施工规范 第5.4.1条、第5.4.4条、第5.4.5条、App. C 第C.0.2条
- JGJ 107-2016 钢筋机械连接技术规程 第4.0.3条
- GB 50007-2011 建筑地基基础设计规范 第8.2.2条、第8.2.3条
- DB11/T 1832.3-2021 建筑工程施工工艺规程 第3部分:混凝土结构工程 第15.4.9条
- 22G101-1 混凝土结构施工图平面整体表示方法制图规则和构造详图(现浇混凝土框架、剪力墙、梁、板)
Scope
This card resolves splice location determination and the associated calculations for longitudinal load-bearing bars of cast-in-place reinforced concrete frame columns: how the length of the no-splice zone (the stirrup densification zones at beam and column ends) is taken, how the stagger length within one splice zone is calculated, how the splice area percentage is banded by splice type, and the basis of anchorage length in foundations and staged cutting lengths of column bars.
Core Conclusions
1. Principle of splice location (GB 50666-2011 Clause 5.4.1, original text)
'Reinforcement splices should be located where the stress is low; in structures with seismic precautionary requirements, reinforcement splices should not be located within the stirrup densification zones at beam ends and column ends, and lapping of reinforcement should not be carried out there. One longitudinal load-bearing bar should preferably not carry two or more splices. The distance from the end of a splice to the bend point of the bar should be no less than 10 times the bar diameter.'
Commentary: where a splice has to be placed inside a stirrup densification zone, mechanical or welded splices of better performance should be used; 'one longitudinal load-bearing bar' means a single longitudinal load-bearing bar within one structural storey, one structural span and one supplied stock length; for beams of large span the limit on the number of splices may be relaxed appropriately.
2. Relation between column bars and the joint zone (GB 50010-2010 Clause 9.3.6)
'Column longitudinal bars shall pass through the intermediate joints or end joints of intermediate floors, and splices shall be located outside the joint zone.' At a top-floor intermediate joint the column bars should extend to the column top, with an anchorage length no less than la measured from the beam soffit; where the section is insufficient, a 90-degree bend may be used (vertical projected anchorage length including the bend arc no less than 0.5lab, horizontal projection within the bending plane preferably no less than 12d) or mechanical anchorage with an anchor head (vertical anchorage length including the head no less than 0.5lab); where a cast-in-place slab at least 100mm thick sits on the column top, the bars may also bend outward, with the horizontal projection preferably no less than 12d.
3. Length of the no-splice zone (stirrup densification zone) (GB 50010-2010 Clause 11.4.14, original text)
'The length of the stirrup densification zone of a frame column shall be taken as the largest of the long side of the column section (or the diameter of a circular section), one sixth of the clear column height, and 500mm; corner columns of seismic grade 1 or 2 shall have stirrups densified over the full column height. The length of the densification zone at the root of a bottom-storey column shall be no less than one third of the clear height of that storey; where a rigid ground floor exists, stirrups shall also be densified over a height of 500mm above and below the rigid ground in addition to the densification zones at the column ends.'
This yields the determination basis:
- first-storey column root above the fixed base: the no-splice zone runs from the fixed base (the foundation top, or the basement roof acting as the fixed base of the superstructure; for columns on beams, the beam top; for columns on walls, the wall top) for no less than Hn/3;
- floor levels (not at the fixed base): max(Hn/6, hc, 500mm) at each of the upper and lower ends;
- corner columns of seismic grade 1 or 2 are densified over the full height, so the whole column height is a no-splice zone;
- where a rigid ground exists, 500mm above and below it is also densified, and splices should avoid it.
Definitions of variables: Hn is the clear column height (from the floor of the storey concerned - for the lowest storey measured from the fixed base - to the beam soffit of the floor above, or to the slab soffit where there is no beam), not the storey height; hc is the long side of the column section (the diameter for circular columns), not the short side or the diagonal.
Worked example: with a storey height of 3600mm and a beam depth of 700mm, Hn = 2900mm and hc = 600mm; the end no-splice zone of a typical floor column = max(2900/6 = 483, 600, 500) = 600mm; the no-splice zone at the first-storey column root (from the fixed base) = 2900/3, approximately 967mm.
4. The same splice zone and the stagger length
- Mechanical and welded splices (GB 50666-2011 Clause 5.4.4): 'the length of the splice zone is 35d and shall not be less than 500mm; every splice whose midpoint falls within this splice-zone length belongs to the same splice zone; d is the smaller diameter of the two connected bars.' Where the splice-zone lengths calculated for different connected bars within one member differ, the larger value governs. JGJ 107-2016 Clause 4.0.3 likewise takes 35d, calculated on the smaller diameter when the diameters differ.
- Lapped splices (GB 50666-2011 Clause 5.4.5, GB 50010-2010 Clause 8.4.3): 'the length of the splice zone is 1.3 times the lap length; every splice whose midpoint falls within this splice-zone length belongs to the same splice zone; the lap length may be calculated on the smaller diameter of the two connected bars.' The lateral clear spacing s between splices should be no less than the bar diameter and no less than 25mm.
- Stagger back-calculated for adjacent bars: for mechanical or welded splices the distance between the midpoints of adjacent batches should be no less than max(35d, 500mm); for lapped splices the midpoint distance of adjacent batches should be no less than 1.3ll (that is, the lap ends are staggered by about 0.3ll), consistent with the commentary to GB 50010-2010 Clause 8.4.3, 'when the distance between the ends of lapped bars is no more than 30% of the lap length, the laps all belong to the same splice zone'.
- Controlling values of 35d versus 500mm: at d = 12, 35d = 420mm < 500, so 500mm governs; at d = 14, 35d = 490mm < 500, so 500mm governs; at d = 16 take 560mm; d = 18 take 630mm; d = 20 take 700mm; d = 22 take 770mm; d = 25 take 875mm; d = 28 take 980mm; d = 32 take 1120mm. In short, for d no more than 14mm the 500mm minimum governs, and for d of 16mm and above 35d governs.
5. Splice area percentage
Definition: within one splice zone, the splice area percentage of longitudinal load-bearing bars is the ratio of the cross-sectional area of the spliced longitudinal load-bearing bars to the total cross-sectional area of all longitudinal load-bearing bars (calculated on the smaller diameter where the diameters differ).
- Mechanical and welded splices (GB 50666-2011 Clause 5.4.4): tension splices should not exceed 50%; compression splices are not limited; tension mechanical splices in slabs, walls and columns, and tension splices at the connections of precast concrete members, may be relaxed according to actual conditions; welding should not be used in members directly carrying dynamic loads, and where mechanical splices are used there the percentage should not exceed 50%.
- Mechanical splices by grade (JGJ 107-2016 Clause 4.0.3): at high-stress locations, Grade III joints no more than 25%, Grade II no more than 50%, Grade I not limited except in seismic densification zones and under repeated loads; joints should avoid the stirrup densification zones at the ends of beams and columns of seismic frames; where they cannot be avoided, Grade II or Grade I joints should be used and the splice area percentage should not exceed 50%; at locations of low bar tension, and for longitudinal compression bars, the percentage is not limited; for members directly under repeated loads it should not exceed 50%. Provided the percentage is no more than 50%, Grade II joints may be used at any location in a seismic structure.
- Lapped splices (GB 50666-2011 Clause 5.4.5): the splice area percentage of longitudinal compression bars is not limited; for longitudinal tension bars - beam, slab and wall members preferably no more than 25%; foundation rafts preferably no more than 50%; column members preferably no more than 50%; where an increase is truly necessary, beam members should not exceed 50% and other members may be relaxed appropriately. GB 50010-2010 Clause 8.4.3 reads: beams, slabs and walls preferably no more than 25%, columns preferably no more than 50%; where necessary, beams preferably no more than 50%, with slab, wall and column members and precast member joints relaxable.
- Modification of lap length (GB 50666-2011 Annex C, Clause C.0.2): at a splice area percentage of 50%, the minimum lap length is the Table C.0.1 value multiplied by 1.15; at 100%, multiplied by 1.35; intermediate values between 25% and 100% are interpolated within the 25%-50% and 50%-100% segments respectively.
6. Anchorage in foundations and starter bars (GB 50007-2011 Clauses 8.2.2 and 8.2.3)
- The anchorage length la of column and shear-wall longitudinal load-bearing bars within the foundation is determined under the relevant provisions of GB 50010; in areas of seismic precautionary intensity 6 to 9, the seismic anchorage length laE applies (each seismic grade using its own laE formula).
- 'Where the foundation depth is less than la (laE), in addition to meeting the requirements above, the total anchorage length of the longitudinal load-bearing bars shall have a minimum straight-anchorage segment no less than 20d and a bent segment no less than 150mm.'
- Starter bars for cast-in-place columns should match the column longitudinal load-bearing bars in number, diameter and steel type, with anchorage satisfying Clause 8.2.2; their lower ends are preferably formed as right-angle hooks resting on the bottom mat of the foundation. Where the column is axially compressed or compressed with small eccentricity and the foundation depth is no less than 1200mm, or the column is compressed with large eccentricity and the foundation depth is no less than 1400mm, only the four corner starters need extend to the bottom mat, the remaining starters being anchored la or laE below the foundation top surface.
- DB11/T 1832.3-2021 Clause 15.4.9 adds layout requirements: the clear spacing of column starter bars should be no less than 50mm and the centre spacing preferably no more than 300mm; for columns with section dimensions above 400mm the centre spacing is preferably no more than 200mm; the four corner longitudinal bars should extend onto the bottom mat; at least two rectangular closed stirrups at a spacing no more than 500mm should be provided within the length embedded in the foundation.
7. Basis of staged cutting lengths for column bars (fabrication practice, assembled from the above detailing rules)
Cutting length = storey height of this level - projection above this floor + projection above the floor above + lap length (or the take-up of the splice fitting) + end anchorage or bend increments.
- The 'projection' is the no-splice zone length above the floor of this level (Hn/3 from the fixed base for the lowest storey, max(Hn/6, hc, 500mm) for floor levels), plus the stagger of the splice batch concerned;
- for mechanical splices the 'lap length' item becomes the take-up length of the coupling fitting (coupler or threaded sleeve), and for lapped splices it is ll (modified by 1.15/1.35 or by interpolation according to the percentage, and subject to constructive minima such as 300mm as controlled by the design and Annex C);
- first-storey column bars must additionally include the anchorage length in the foundation (la/laE, or, where the foundation is too shallow, the straight segment of no less than 20d plus the bend of no less than 150mm, the horizontal leg after bending following the design or the standard details);
- the ends of top-storey column bars include the anchorage at the top joint (la, 0.5lab + 12d, mechanical anchor head 0.5lab, and so on).
8. Effect of adjacent-bar stagger on cutting and wastage
Splices must be staggered in batches, so the longitudinal bars within one column section fall into two batches (more where necessary), each batch with a projection differing by one stagger amount delta: for mechanical or welded splices, delta is no less than max(35d, 500mm); for lapped splices, delta is about 0.3ll (keeping the midpoint spacing no less than 1.3ll). In fabrication, each batch needs its own cutting lengths, its own batching and marking, and a single length cannot serve the whole column. Each column on each floor therefore produces two or more cutting lengths, short offcuts and couplers increase accordingly, and wastage should be counted per batch - the larger the stagger and the smaller the storey height, the more visible the share of offcut loss.
Applicability Boundaries
- Applies to longitudinal load-bearing bars of cast-in-place reinforced concrete frame columns (including analogous vertical members such as columns supporting transfer structures); boundary elements of shear walls may follow the same detailing spirit, but their densification zones and lap requirements must be judged separately under the corresponding clauses of GB 50010.
- Hn/3 and max(Hn/6, hc, 500mm) are no-splice zone requirements carried by seismic detailing (stirrup densification) under GB 50010-2010 Clause 11.4.14; columns not designed for seismic action do not apply this no-splice zone, but remain bound by 'splices located where the stress is low' and by the splice area percentage limits.
- Hn must be the clear column height (from the floor of the storey to the beam or slab soffit above); mistakenly using the storey height makes the no-splice zone too large or too small; hc is the long side (the diameter for circular columns).
- The mechanical splice area percentage must satisfy both GB 50666-2011 Clause 5.4.4 and JGJ 107-2016 Clause 4.0.3, the stricter governing; Grade III joints may not exceed 25% at high-stress locations.
- Where corner columns of seismic grade 1 or 2 are densified over the full height, the no-splice zone covers the whole column and splices can only follow the route of 'low-stress location + Grade I or II mechanical splice + percentage no more than 50%', the location usually being fixed by the design.
- The relaxations for tension mechanical splices in slabs, walls and columns, and for 100% splicing at connections of precast members, are relaxations and must not be extended into unrestricted splicing.
- The 20d straight segment and the 150mm bend applied where the foundation is shallower than la(laE) are supplementary minima and cannot replace the total anchorage length la/laE.
- For the layout and joint details of the plane-notation atlases (22G101-1 series, connection detailing of frame-column longitudinal bars) and of local rules, the current edition and the design documents govern; in case of conflict with the codes, the codes and the design govern.
Further Reading
- GB 50666-2011 Code for Construction of Concrete Structures, Section 5.4 reinforcement works: Clause 5.4.1 (splice location and distance to the bend point), Clause 5.4.4 (splice zones and percentages for mechanical and welded splices), Clause 5.4.5 (splice zones and percentages for lapped splices); Annex C, Table C.0.1 (minimum lap lengths) and Clause C.0.2 (percentage modification factors 1.15/1.35 and interpolation).
- GB 50010-2010 Code for Design of Concrete Structures (2015 edition), Clause 8.4.3 (definition of the lapped splice zone, percentages, lapping of bundled bars), Clause 9.3.6 (column bars through the joints and anchorage at the top intermediate joint), Clause 11.4.14 (densification zone lengths of frame columns).
- JGJ 107-2016 Technical Specification for Mechanical Splicing of Reinforcement, Clause 4.0.3 (application of joints: percentages by grade, avoiding densification zones, limits under repeated loads).
- GB 50007-2011 Code for Design of Building Foundations, Clause 8.2.2 (anchorage of column and wall bars in foundations and the 20d/150mm minima), Clause 8.2.3 (detailing of starter bars for cast-in-place columns and the four-corner-starter conditions).
- DB11/T 1832.3-2021 Specification for Construction Technology of Building Works, Part 3: Concrete Structure Works, Clause 15.4.9 (layout of embedded starter bars for walls and columns and the number of stirrup circuits in the foundation).
- Plane-notation atlas 22G101-1 (rules of plane notation and standard detailing for cast-in-place concrete frames, shear walls, beams and slabs), nodes for the connection detailing of frame-column longitudinal bars (no-splice zones, projection lengths, stagger of adjacent splices, splice percentages); verify the node pages against the current edition.
- Companion quantity basis: rebar quantity = design length x theoretical weight; anchorage and design laps are included, construction laps and wastage are handled through quota consumption, and mechanical splice couplers are counted per piece.