Anchorage and lap details of longitudinal reinforcement at frame beam-column joints: straight, mechanical-anchor and 90-degree-bend anchorage of beam top bars at middle-floor exterior joints (la, 5d, 0.4lab, 15d), the anchorage basis for bottom bars, diameter limits for beam bars passing through interior columns (1/25, 1/20), and labE / llE values in the joint zone (GB 50010-2010 clauses 9.3.4, 11.6.7 and 11.1.7)
Beam top bars at a middle-floor exterior joint of a frame: straight anchorage no less than la, extending past the column centre line by preferably no less than 5d; where the column section is insufficient, a mechanical anchor (horizontal projection including the anchor head no less than 0.4lab, preferably reaching the inner edge of the outer column bars) or a 90-degree bend (horizontal projection including the bend arc no less than 0.4lab, projection within the bend plane no less than 15d) may be used. Bottom bars follow the same rules where their tensile strength is fully used, and the interior joint rules of clause 9.3.5 where it is not used or is used only in compression. Seismic joints (clause 11.6.7): beam top bars shall run through middle-floor interior joints, and for beam bars passing through a column - for intensity-9 frames of all types and grade-1 frame structures, the diameter is preferably no larger than 1/25 of the column section dimension in that direction (rectangular columns) or 1/25 of the chord length at the bar position (circular columns); for seismic grades 1, 2 and 3, preferably no larger than 1/20 of the section dimension or 1/20 of the chord length; llE in the joint zone follows clause 11.1.7, and labE is obtained as zeta aE x lab. At roof-floor exterior joints the negative-moment bars are lapped straight on the outer face of the joint (the former 12d inward horizontal bend of the column bars at the top is cancelled). Splices in the joint zone should avoid the stirrup-densified zones at the beam and column ends, and the splice area ratio should not exceed 50%.
Applicable Codes
- GB 50010-2010 · Code for Design of Concrete Structures (2015年版)第9.3.4条、第11.6.7条、第11.1.7条
- GB/T 50010-2010 · Standard for Design of Concrete Structures (2024年版)
Topic positioning
Anchorage and lap construction of longitudinal reinforcement at frame beam-column joints: the three anchorage options for beam top bars at middle-floor exterior joints (straight, mechanical anchor, 90-degree bend) and their lengths (la, 0.4lab, 5d, 15d), the anchorage basis for bottom bars, the relative limits on the diameter of beam bars passing through interior joints, and the values of labE and llE plus the lap arrangement at roof-floor exterior joints under seismic rules. For checking frame structural design drawings and rebar joint details.
Core conclusions
1. Beam top bars into a middle-floor exterior joint (GB 50010-2010 clause 9.3.4 item 1)
- Straight anchorage: 'Where a straight anchorage form is used, the anchorage length shall be no less than la, and the bar shall extend past the column centre line by preferably no less than 5d, where d is the diameter of the beam top longitudinal bar.'
- Mechanical anchor: 'Where the column section dimensions do not satisfy the straight anchorage requirement, the beam top longitudinal bars may use the end mechanical anchor form of clause 8.3.3 of this code. The beam top longitudinal bars should reach the inner edge of the outer longitudinal bars of the column, and the horizontal projection of the anchorage length including the mechanical anchor head shall be no less than 0.4lab.'
- 90-degree bend anchorage: 'The beam top longitudinal bars shall reach the inner edge of the outer longitudinal bars of the column and bend into the joint; the horizontal projection length including the bend arc shall be no less than 0.4lab, and the projection length of the bent bar within the bend plane including the arc segment shall be no less than 15d.' The commentary gives the mechanism: 'the anchorage force of such an anchorage end consists of the bond anchorage of the horizontal segment and the bearing anchorage of the arc-to-vertical segment' and 'when the projection length of the horizontal segment is no less than 0.4lab and the projection length of the arc-to-vertical segment is 15d, the anchorage strength and the anti-slip stiffness of the beam bars are reliably secured'.
2. Beam bottom bars into an exterior joint (item 2 of the same clause)
- Where the tensile strength of the bar is fully used in the calculation, the anchorage form and length follow the same rules as for the top bars;
- Where its strength is not used, or is used only in compression, the anchorage length into the joint shall comply with clause 9.3.5 on the anchorage of beam bottom bars at interior joints.
3. Seismic anchorage in the joint zone and the diameter limits for beam bars through interior columns (clause 11.6.7)
- At middle-floor interior joints, the beam top bars of the frame shall run through the interior joint. For each beam bar passing through a column: 'for intensity-9 fortification frames of all types and grade-1 seismic frame structures, where the column is of rectangular section the diameter is preferably no larger than 1/25 of the column section dimension in that direction, and where of circular section no larger than 1/25 of the chord length of the column section at the position of the longitudinal bar; for seismic grades 1, 2 and 3, where the column is of rectangular section preferably no larger than 1/20 of the column section dimension in that direction, and for circular column sections no larger than 1/20 of the chord length at the position of the longitudinal bar.'
- At middle-floor interior joints, middle-floor exterior joints, roof interior joints and roof exterior joints, the anchorage and laps of the beam and column longitudinal bars at the joint shall comply with the relevant details of figure 11.6.7; in that figure llE is taken per clause 11.1.7, and labE is obtained as zeta aE x lab (zeta aE = 1.15 for grades 1 and 2, 1.05 for grade 3, 1.00 for grade 4).
- Roof exterior joints: the 2015 edition cancelled the requirement of the former code that, when the negative-moment bars of beam and column lap on the outer side of a roof exterior joint, the column bars bend horizontally inwards 12d at the top of the joint; the negative-moment bars now lap in a straight line on the outer side of the joint (easier to build; the basis is that roof joints usually have lower ductility demand and lighter earthquake damage than middle-floor joints).
4. Splice positions and splice ratio in the joint zone (clause 11.1.7) Splices of longitudinal bars should avoid the stirrup-densified zones at the beam and column ends; where a splice there is unavoidable, mechanical splices or welding shall be used; within one splice zone the splice area ratio of the longitudinal bars should not exceed 50%. The commentary reasons that the beam and column ends are potential plastic hinge locations, and the post-yield elongation of the bars there must not be disturbed or weakened by the splice.
Applicability boundaries
- Clause 9.3.4 addresses anchorage of beam bars at 'middle-floor exterior joints' of frames; roof exterior joints, middle-floor interior joints and roof interior joints follow the corresponding details of clause 11.6.7 and figure 11.6.7 - they must not be mixed.
- 0.4lab (horizontal projection) and 15d (bend-segment projection) are two parallel controls, both required; the horizontal projection length already includes the bend arc.
- Mechanical-anchor anchorage must satisfy the forms and technical requirements of clause 8.3.3 (matching materials, fabrication and installation), and once the reduction under that clause is taken, the zeta a correction of clause 8.3.2 may not be stacked on top.
- The relative diameter limits for beam bars (1/25, 1/20) are detailing caps governed by the 'column section dimension / chord length'; they do not replace the anchorage-length calculation; the 2015 edition is slightly stricter than the 2002 edition for high-intensity zones and grade-1 seismic frames, because bond degradation at joints comes earlier and heavier with 400MPa and 500MPa grade bars.
- Version status: the clauses come from GB 50010-2010 (2015 edition), since revised into the 'Standard for Design of Concrete Structures' GB/T 50010-2010 (2024 edition, effective 2024-08-01); in execution, check against the new edition text and figure 11.6.7.
Further reading
- GB 50010-2010 'Code for Design of Concrete Structures' (2015 edition) clause 9.3.4 (anchorage of beam bars at middle-floor exterior joints and figures 9.3.4a/9.3.4b), clause 9.3.5 (anchorage of beam bottom bars at interior joints), clause 11.6.7 (anchorage and laps in the joint zone and figure 11.6.7), clause 11.1.7 (laE, llE, splice positions and splice ratio), clause 8.3.3 (forms and technical requirements of hooks and mechanical anchorage).
- GB 55008-2021 'General Code for Concrete Structures' clause 4.4.5 (mandatory rebar anchorage requirements).
- National standard design atlases such as 22G101-1 (plane-notation atlases with joint-zone anchorage and lap details and quick-reference tables) - cross-check them against the formula chain of this card and against the current code edition.