The three rebar quantities (drawing quantity -> cutting quantity -> procurement quantity): stage-by-stage measurement bases, the quota chapter where the wastage rate is taken, and the conversion procurement quantity = budget quantity x (1 + wastage rate)
Drawing quantity = design centreline length x theoretical unit mass (includes anchorage and design laps; excludes construction laps / auxiliary bars / wastage); cutting quantity = drawing quantity + end hook growth values, bend deduction values (elongation as a deduction), stock-length laps and splice lengths, auxiliary bars and the inclined length of bent-up bars; procurement quantity = budget quantity x (1 + wastage rate), the wastage rate being taken item by item by bar type and splice method. In the railway system the reinforcement wastage rate is taken uniformly from Chapter 10 'on-site material handling and operation wastage rates' of the 'Railway basic quota manual' TB/T 10821-2024 (welding 1.5%, mechanical splices 1%, prestressing tendons 4% excluding the external-tensioning working length), not from the concrete chapter or the reinforcement fabrication chapter.
Applicable Codes
- TB/T 10821-2024 · Basic Quota of Railway Engineering 总说明 一、四;Ch. 3「钢筋」说明 二~五;Ch. 10「材料工地搬运及操作损耗率」
- TB/T 10823-2024 · Budget Quota of Railway Engineering (Volume 2: Bridge and Culvert Works) 册说明 十二、工程量计算规则 第3、4条
- GB/T 50860-2024 · Standard for Measurement of Quantities of Structures Works App. A 钢筋项目说明
- DB 51/T 5046-2007《混凝土结构工程施工工艺规程》第3.1.4条
- DBJ50/T-331-2019《轨道交通U形梁结构技术标准》第8.2.4条
- DB/T 29-75-2018 · Standard for Construction and Acceptance of Urban Bridges of Tianjin 第5.2.4条及Table 5.2.4
- DB11/T 2382-2024 · Standard for Construction Consumption of Construction Works (Beijing) 第4.6.5条
Scope of the Topic
Why the rebar 'drawing quantity', 'cutting quantity' (detailing output) and 'procurement quantity' never agree: the three quantities serve three different purposes and use three different measurement bases - they are not three precision levels of one quantity. The card sets out the stage-by-stage basis of each quantity, the quota chapter and location where the wastage rate is taken, and the conversion relationship and variable definitions of the procurement quantity.
Core Conclusions
I. Stage-by-stage bases of the three quantities
- Drawing quantity (pricing / measurement basis, the 'design net quantity') = length of reinforcement shown on the design drawings x unit theoretical mass.
- GB/T 50860-2024 'Structures works quantity take-off standard', Appendix A: 'The design-shown reinforcement length in the measurement rules means the centreline length of the bar.' 'Apart from laps indicated in the design (including those required by codes), other construction laps (such as stock-length laps) shall not be measured.'
- TB/T 10823-2024 'Railway works budget quota manual, volume 2, bridges and culverts', volume notes, XII, measurement rules, clause 3: 'The mass of non-prestressed reinforcement is calculated as the design length of the bars (spacer and positioning bars included) multiplied by the theoretical unit mass. Welding consumables, binding wire, splice sleeves, spacers and similar materials shall not be counted into the quantities.' Clause 4: 'The mass of prestressed reinforcement (wire, strand) is calculated as the design cutting length multiplied by the theoretical unit mass. Anchors, ducts, anchor plates and connecting steel plates, anchor sealing, binding and welding materials and the like shall not be counted into the quantities.'
- Key points: anchorage, design (and code-required) laps, spacer bars and positioning bars enter the drawing quantity; stock-length and other construction laps, non-design auxiliary bars (chairs, diagonal braces, packing pieces), wastage, welding consumables, binding wire, sleeves and spacers do not.
- Cutting quantity (detailing and batching basis, the 'physical fabrication length') = drawing quantity + the net sum of additions / deductions.
- DB 51/T 5046-2007 clause 3.1.4: 'When calculating reinforcement cutting lengths, the cumulative overall dimensions of the bars on the design or standard drawings should generally be used; the cutting length calculation includes bend deduction values, the inclined length of bent-up bars and end hook growth values.'
- DBJ50/T-331-2019 clause 8.2.4: 'Reinforcement cutting lengths shall be calculated on the centreline lengths after bending, with hook growth lengths and bend adjustment values taken into account.'
- DB/T 29-75-2018 clause 5.2.4: '1 Where the bar length falls short of the design length, the cutting length shall add the length required for connection under the splice method used. 2 In cutting, the cutting length shall be determined from the lengths required by bar diameter and hook form and from the elongation values produced on bending.'
- Additions: end hook growth values, stock-length laps and splice lengths, auxiliary construction bars, inclined length of bent-up bars. Deductions: bend deduction values (bend elongation, because the outside-face dimension exceeds the centreline arc length). The net effect usually puts the cutting quantity about 1% to 5% above the drawing quantity, depending on splice ratio, auxiliary bar content and member type; a guaranteed increase is not implied.
- Procurement quantity (supply / delivery basis) = budget quantity x (1 + wastage rate).
- Variable definitions: budget quantity = the net-quantity base consistent with the quota basis (i.e. the drawing quantity / quota net quantity); the wastage rate is taken item by item by bar type, size and splice method, never as one blended figure; the procurement quantity serves ordering, material requisition against quota limits and over-consumption assessment and does not enter pricing.
- Basis: TB/T 10821-2024 'Railway basic quota manual', general notes, IV: 'The material consumption in this volume covers both net quantities and wastage. Wastage covers on-site handling and operation losses, meaning all losses from the site material store or stockpile to the place of installation (or operation), including transport, construction and site storage losses. Laps arising from construction technology and operation losses arising on site are detailed in the specialist quota manuals. On-site handling and operation wastage rates are given in Chapter 10 of this volume; except where otherwise stated, the material quantities in this volume include wastage.'
II. Where the wastage rate is taken (which chapter to consult) Railway system: the on-site handling and operation wastage rates for reinforcement (and all other materials) are taken uniformly from Chapter 10 'on-site material handling and operation wastage rates' of the 'Railway basic quota manual' TB/T 10821-2024 (laid out as Chapter 10 of the volume, appendix in nature, applicable to this volume and to all volumes of the 'Railway works budget quota manual' other than building works) - not from the concrete chapter and not from the reinforcement fabrication chapter. General note I states that the volume covers 'formwork and auxiliary structures, reinforcement, concrete, masonry, manufactured sand and aggregate, short-haul material transport, mix designs, amortisation of auxiliary structural materials and semi-finished products, and on-site material handling and operation wastage rates'; of these, 'reinforcement transport', 'concrete mixing', 'concrete transport' and 'short-haul material transport' apply to railway estimate (budget) preparation other than building works. Chapter 10, 'I. metal products -> 1. reinforcement and connectors', principal values:
- plain round bars d<10, wire (wire line), strand, wire rope: 1.5%;
- plain round bars d no less than 10, deformed bars (welded): 1.5%;
- plain round bars d no less than 10, deformed bars (mechanical splices): 1%;
- small finished products and semi-finished products made of reinforcement: 0.5%;
- prestressing bars (wire), cold-drawn wire, prestressing strand, wire rope: 4% (note: excluding the working length required for tensioning outside the structure);
- wire mesh 3%; barbed wire 2%; structural steel sections 5% (3% for the four electrical systems and for mechanical works); steel plate 5% (3% for the four electrical systems and for mechanical works); rock bolts, grouting pipes and fittings 1%; steel fibre 3%. 'XIII. concrete and products': (in-situ) concrete 2%, precast concrete 1%, self-compacting concrete for ballastless track 10%.
III. How wastage rates attach to quota line items TB/T 10821-2024 Chapter 3 'Reinforcement' notes: the chapter covers reinforcement fabrication and reinforcement transport; the fabrication items are compiled for centralised CNC processing, unit t, meaning the fabrication of 1 t of formed reinforcement; the transport items carry a unit of 10 t; 'The reinforcement fabrication items in this chapter do not include reinforcement consumption; when invoked, supplement them by work location and bar type and add operation wastage. For non-sleeve-spliced bars over 10 mm diameter, add a further 1.5% lap quantity.' 'The fabrication item for mesh applies to bars below d10.' - i.e. quota reinforcement consumption = net quantity x (1 + Chapter 10 wastage rate) + (where required) the 1.5% lap quantity, the two being listed separately.
IV. Local quota comparison (building / municipal systems) DB11/T 2382-2024 'Consumption standard for construction works', clause 4.6.5: 1 'The construction consumption for reinforcement fabrication, mesh fabrication and fixing, and diaphragm wall reinforcement fabrication and fixing should be determined with the auxiliary bars - chairs, supports, positioning bars - included, according to building function, design grade and similar factors; where data are insufficient, the combined reinforcement wastage plus auxiliary bars may be taken as 5% of the total reinforcement quantity'; 2 'Connection consumption should be determined with tying and welding combined; where the design requires mechanical splices, the splices follow the corresponding items and no further lap reinforcement quantity is measured'; 3 for reinforcement fixing at the joints of precast concrete members, the labour consumption is multiplied by 1.15.
V. Three red lines that must not be crossed The wastage rate attaches only to the last step (procurement / quota consumption) and must not also be attached to the BOQ (drawing quantity), which would double count; construction laps must not enter the drawing quantity; auxiliary bars already absorbed by the work content / composite wastage content must not be billed as separate items or counted twice.
Applicability Boundaries
- The three quantities widen stage by stage but not proportionally: the bend deduction value is a deduction, and the net increase of the cutting quantity over the drawing quantity varies with splice ratio, auxiliary bar content and member type (usual range 1% to 5%); the drawing quantity must not be used to back-calculate the procurement quantity with no wastage at all.
- Prestressed reinforcement (wire, strand) is the exception: it is measured on the 'design cutting length' in the first place, so its measurement basis merges with the cutting quantity; its wastage rate is 4% and it 'excludes the working length required for tensioning outside the structure', which must be handled separately - the three-quantity logic for non-prestressed bars must not be copied.
- The systems must not be copied across: railway works take their rates from TB/T 10821-2024 Chapter 10; building, municipal and structures works follow the consumption quota of the place (example: Beijing determines auxiliary bars plus wastage as a combined 5% of the total quantity, with no further lap quantity for mechanical splices). Direct cross-system borrowing misplaces the wastage basis.
- Procurement quantity = budget quantity x (1 + wastage rate) serves ordering, material requisition against quota limits and over/under-consumption assessment only; final account and pricing still follow the drawing net quantity and the quota consumption - two ledgers kept apart.
- Where reinforcement is centrally processed and delivered by a specialist contractor (outsourced), the party bearing in-plant fabrication loss and off-site transport loss must be agreed in the contract, and the site execution basis is reduced accordingly.
Further Reading
- TB/T 10821-2024 'Railway basic quota manual', general notes I, III, IV, IX; Chapter 3 'Reinforcement', notes II to V; Chapter 10 'on-site material handling and operation wastage rates', I. metal products, 1. reinforcement and connectors; XIII. concrete and products.
- TB/T 10823-2024 'Railway works budget quota manual, volume 2, bridges and culverts', volume notes, XII, measurement rules, clauses 3 and 4 (and clauses 1, 2 and 5: masonry and concrete by solid volume; test piles counted into the quantities).
- GB/T 50860-2024 'Structures works quantity take-off standard', Appendix A, reinforcement item notes ('design-shown reinforcement length' is the centreline length; construction laps are not measured).
- Cutting length calculation: DB 51/T 5046-2007 clause 3.1.4; DBJ50/T-331-2019 clause 8.2.4; DB/T 29-75-2018 clause 5.2.4 and table 5.2.4 'hook elongation values for different bar forms'.
- Auxiliary bars and composite wastage: DB11/T 2382-2024 clause 4.6.5.
- Related bases: labour and plant make-up of the fabrication / transport items in TB/T 10821-2024 Chapter 3; terms for material net quantity and wastage in GB/T 50875-2013 section 2.3.