Engineering Knowledge Cards.
Confidence HighUpdated 2026-10-25

Work-item quantity take-off for pile foundation (bored pile) rebar cages: the three formulas for main bars, helical links and stiffening rings with their variable definitions, the convention for taking the centreline diameter D of helical links, the BOQ itemisation code for the 'rebar cage' item, and the measurement boundary of laps and non-design reinforcement

The billed quantity of a pile rebar cage = the design-drawn rebar length (centreline) x the unit theoretical mass (tonnes): main bars G_main = (L_cage + L_anchor + L_end) x n_main x w; helical links L_helix = sum over i of (Hi / si) x sqrt((pi x D)^2 + si^2), with D = diameter over the outside of the main bars + link diameter, i.e. pile diameter - 2 x cover + d_link; stiffening rings G_stiff = (pi x D_stiff + lap) x n_stiff x w. GB/T 50854-2024 Table E.6.1 (code 010506) requires the rebar of bored piles and diaphragm walls to be coded and listed under the 'rebar cage' item; laps and anchorage marked on the design (including those required by codes) are absorbed, while stock-length laps and non-design chair bars, raking prop bars, anti-floating bars, spacers and the like are not measured; sonic tubes are not merged into the cage and are listed separately.

Applicable Codes

  • GB/T 50854-2024 房屋建筑与装饰工程工程量计算标准 Table E.6.1(code 010506)、App. E说明第2/3/9/10/11/12/13条、App. C第C.3.14条、App. B第B.3.13条
  • GB/T 50857-2024 市政工程工程量计算标准 Table J.1.1(code 040901)、第J.2.1条
  • GB/T 50861-2024 城市轨道交通工程工程量计算标准 第B.9.1条、第B.9.3条
  • SJG 111.1-2022 城市地下综合管廊工程消耗量标准(Vol. 1)第3.2.2条第4款
  • SJG 181.2-2024 市政工程消耗量标准 Vol. 2 桥涵工程 第5.2.2条
  • DBJ 52/T 088-2018 贵州省建筑桩基设计与施工技术规程 第6.4.2条
  • JGJ/T 419-2018 长螺旋钻孔压灌桩技术标准 第4.3.4条、第5.7.2条
  • DBJ/T 15-236-2021 旋挖成孔灌注桩施工技术规程 第6.2.3条
  • DB11/T 1832.1-2021 建筑工程施工工艺规程 第1部分:地基基础工程 第16.4.9条
  • DBJ/T 36-055-2019 旋挖成孔灌注桩施工技术标准 第5.1.2条
  • JGJ 106-2014 建筑基桩检测技术规范 第10.3.2条
  • TB 10218-2019 铁路工程基桩检测技术规程 第5.3.1条
  • TB/T 10823-2024 铁路工程预算定额 Vol. 2 桥涵工程 Ch. 1第四节(七)QY-210~QY-213
  • DB11/T 2382-2024 建设工程施工消耗量标准 App. A Table A.3.2 子目A-3-16

Topic positioning

This card covers the work-item quantity take-off of rebar cages for bored piles (including diaphragm walls): the three formulas for main bars, helical links and stiffening rings with their variable definitions, the analysis of the convention for taking the centreline diameter D of helical links, the BOQ itemisation code for the 'rebar cage' item, and the measurement boundaries of laps, non-design reinforcement, sonic tubes and positioning bars.

Core conclusions

1. BOQ itemisation and unit convention

  • GB/T 50854-2024, measurement standard for building works and decoration works: the BOQ item setting, item description, unit of measurement and measurement rules for rebar, bolts and metal fittings follow Table E.6.1 (code: 010506).
  • Annex E notes, item 3, original text: 'The rebar of diaphragm walls and bored piles should be coded and listed under the rebar cage item'; item 2: 'The rebar of cast-in-place concrete members should be coded and listed by the rebar item of each member; the rebar of ordinary precast concrete members and of assembled precast concrete members is contained in the corresponding members and is not separately listed or measured'; item 9: 'Rebar at post-cast strips in cast-in-place concrete structures is not separately listed or measured; its quantity is merged into the rebar quantity of the corresponding cast-in-place member'.
  • Pile foundation linkage: Annex C Clause C.3.14: 'The fabrication and installation of rebar cages for cast-in-place concrete piles should be coded and listed under the relevant items of Annex E of this standard'; Annex B Clause B.3.13: 'The rebar mesh and steel wire mesh of shotcrete (mortar) should be listed under the rebar mesh and steel wire mesh items of Annex E of this standard; the rebar cages of diaphragm walls and concrete piles should be listed under the rebar cage item of Annex E ... wherever the above rebar fabrication and installation uses the relevant item codes of Annex E of this standard, the location of use must be described.'
  • Unit: pile rebar cages are computed in tonnes as the design-drawn rebar length in use multiplied by the unit theoretical mass, and the helical reinforcement of the cage is included (SJG 111.1-2022 Clause 3.2.2 item 4). The unit theoretical mass w is about 0.00617 x d^2 (d in mm); common values: d8 = 0.395, d16 = 1.58, d20 = 2.47 kg/m.

2. The three formulas side by side (variables fully defined)

  1. Main bars

G_main = (L_cage + L_anchor + L_end) x n_main x w

  • L_cage: the design length of the cage (pile top to pile toe, including the toe closing section required by the design);
  • L_anchor: the anchorage (seating) length of the main bars into the pile cap / capping beam, taken per the design;
  • L_end: the toe closing / bend increment; where the design imposes no requirement the main bars are generally not hooked (DBJ 52/T 088-2018 Clause 6.4.2 item 6);
  • n_main: the number of main bars; w: the unit theoretical mass (kg/m).
  1. Helical links

L_helix = sum over i of (Hi / si) x sqrt((pi x D)^2 + si^2), with D = diameter over the outside of the main bars + link diameter, i.e. pile diameter - 2 x cover + d_link

  • Hi: the winding height of the helical link over segment i; si: the pitch of that segment; D: the centreline diameter of the helical link.
  • Densified and non-densified zones must be computed segment by segment and then summed: links within 5d below the pile top should be densified with a spacing of no more than 100mm, and the rest preferably 200mm~300mm (DBJ 52/T 088-2018 Clause 6.4.2 item 2 sub-item 1; JGJ/T 419-2018 Clause 4.3.4 item 3).
  • Additional lengths (counted where required by the design / codes): horizontal segments at the start and end of the helix, each no shorter than one and a half turns; end hooks of no less than 135 degrees with a straight leg of no less than 10d; lap length no less than la or laE and no less than 300mm (same clause, item 2, sub-items 2 to 4).
  • Convention analysis for D: where the cover is measured to the outside of the main bars (cage cover generally means from the main bar surface to the pile surface), D = pile diameter - 2 x cover + d_link (the link lies outside the main bars); where the cover is defined to the outside of the links, D = pile diameter - 2 x cover - d_link. Confirm which layer the drawing cover dimension refers to before computing, to avoid double counting or missing one link diameter.
  1. Stiffening rings

G_stiff = (pi x D_stiff + lap length) x n_stiff x w_stiff, with D_stiff = pile diameter - 2 x cover - 2 x d_main - d_stiff (the stiffening rings sit inside the main bars)

  • n_stiff = floor(H / 2) + 1 (one ring every 2m where the cage exceeds 4m in length, including both ends).
  • Detailing: stiffening ring diameter no less than 12mm (DBJ 52/T 088-2018 Clause 6.4.2 item 3; DBJ/T 15-236-2021 Clause 6.2.3 item 1, where for pile diameters of no less than 1500mm the internal bracing should preferably be well-shaped or triangular); JGJ/T 419-2018 Clause 4.3.4 item 2: stiffening ring spacing no more than 2.0m and diameter no less than 14mm. The lap length is taken per the design or as a welded lap (the worked example takes 10d).

Worked example (pile diameter 1.0m, cover 50mm, cage length 20m, main bars 12d20, helical links d8@200, stiffening rings d16@2m, anchorage into the cap 0.8m): single main bar 20.8m, total 249.6m, 616.512kg; helical link centreline D = 0.908m, one-turn development 2.86m, 100 turns, total 285.96m, 112.95kg; stiffening ring centre diameter 0.844m, one ring 2.812m (including the 10d lap), 11 rings, total 30.93m, 48.86kg; cage total 0.778t (excluding end horizontal segments, hooks and extra-long laps).

3. Measurement of laps, anchorage and splices

  • Annex E notes, item 10: 'Anchorage bars projecting from each cast-in-place member should have their length determined per the design and be merged into the rebar quantity of that member'.
  • Item 11: 'Apart from the laps marked on the design (including those required by codes), other construction laps (such as stock-length laps) are not measured'.
  • Item 12: 'No rebar item measures the quantity of non-design chair bars, raking prop bars, anti-floating bars, spacers and other such reinforcement'.
  • Item 13: 'Post-installed bars not required by the design are not separately listed or measured. Where the design requires them, they should be coded and listed under the rebar item of the corresponding member, with an added description of the embedment requirement'.
  • Splices between cage sections: where the longitudinal bars of bored pile cages are designed as welded splices, the lap length is computed per the design; extra-long laps of helical links are already comprehensively allowed for and are not recomputed when they occur; a single bar whose continuous length exceeds 9m counts one splice per 9m for the time being (Chapter 5 notes of the Jiangsu building and decoration consumption standard). Fabrication laps and construction wastage beyond the design and the codes are already contained in the line item contents and are not recomputed (SJG 111.1-2022 Clause 3.2.2 item 4).
  • Splice detailing: welded splices of main bars in one section must not exceed 50%; double-sided lap weld length no less than 5d, single-sided no less than 10d (DBJ/T 36-055-2019); the stagger of splices between adjacent main bars is no less than 35d, and splices should preferably be avoided in the anchorage zone at the cage top (DB11/T 1832.1-2021 Clause 16.4.9); cages longer than 10m must be assembled in sections with welded or mechanical connections (DBJ 52/T 088-2018 Clause 6.4.2 item 4).

4. Itemisation boundary of sonic tubes and positioning (non-design) bars

  • Sonic tubes are not merged into the cage mass and are listed separately / under separate quota line items: in the railway quota, sonic tube fabrication and installation is measured in tonnes (TB/T 10823-2024 Volume 2 Bridge and Culvert Works QY-213, work content covering sonic tube fabrication and lifting together with the cage); in some regional quotas sonic tube embedment is measured in metres (e.g. DB11/T 2382-2024 Annex A Table A.3.2 item A-3-16) - verify the unit of measurement of the region before applying.
  • Sonic tube construction and numbers: symmetrically arranged along the inside of the cage and firmly fixed; metal tube inner diameter no less than 40mm and wall thickness no less than 3.0mm, closed at the lower end and capped at the upper end, with the tube mouth standing no less than 100mm above the concrete top surface (TB 10218-2019 Clause 5.3.1); numbers by pile diameter class - no fewer than 2 tubes for d no more than 800mm, no fewer than 3 for d above 800mm and up to 1600mm, no fewer than 4 for d above 1600mm, with additional tubes preferable for d above 2500mm (JGJ 106-2014 Clause 10.3.2; TB 10218-2019 Clause 5.3.1).
  • Positioning and non-design reinforcement conventions differ: under the BOQ convention, non-design chair bars, raking prop bars, anti-floating bars and spacers are not measured (Annex E notes item 12; GB/T 50861-2024 Clause B.9.3; GB/T 50857-2024 Clause J.2.1 same convention); under the quota convention, position-fixing support bars (such as steel horses, chair bars, spacers), anchorage bars projecting from members and hanger bars are measured in tonnes and merged into the rebar quantity per the design, the codes or the approved project execution plan (SJG 181.2-2024 Clause 5.2.2); the mass of cage hanger bars is merged into the cage mass (Chapter 5 notes of the Jiangsu consumption standard).

Applicable boundaries

  • The three formulas apply to the rebar cages of cast-in-place bored piles and diaphragm walls (BOQ convention: listed under the 'rebar cage' item). Not applicable to: rebar in ordinary precast / assembled precast members (contained in the member, not separately listed); prestressed bars / wire strand bundles / steel strands (coded and listed separately by material type and specification); structural steel bolts (Annex F applies); and bolts pre-embedded in cast-in-place concrete and chemical anchors anchored into concrete (listed under the 'bolts' item).
  • Billed quantity and quota quantity are two conventions: BOQ = design-drawn centreline length x unit theoretical mass, excluding construction laps and non-design support bars; quota line item contents already comprehensively include fabrication laps, construction wastage and some support items, and these must not be counted again when converting. When producing quantities from one formula, state first which convention is being followed.
  • 'Pile length' does not include the length entering the pile cap or capping beam (void bore length = bore depth - pile length, the bore depth being from natural ground or the drawn bore level to the design pile toe, GB/T 50861-2024 Clause B.9.1 items 2 and 9); the anchorage length may enter the rebar quantity but not the pile length - do not mix the two conventions.
  • The extent of densified zones, the cover thickness and the toe closing details follow the design documents; where the design is silent, refer to DBJ 52/T 088-2018 (helical link diameter no less than 6mm, spacing 200mm~300mm; clear spacing between main bars more than three times the coarse aggregate size), DBJ/T 15-236-2021 (clear spacing between main bars no less than 60mm), DB11/T 1832.1-2021 (cover of submerged cast-in-place piles no less than 50mm, dry-bore piles no less than 35mm; spacers one run every 3m~5m, no fewer than 3 per run) and JGJ/T 419-2018 (for continuous flight auger cast-in-place piles, stiffening ring spacing no more than 2.0m, diameter no less than 14mm, helical links connected to every main bar).
  • Additional helical link lengths (end horizontal segments, 135-degree hooks, extra-long laps) are code-marked detailing and are absorbed under the BOQ convention, but most regional quotas already allow for them comprehensively within line item contents and do not add them - confirm the convention before producing quantities.

Further reading

  • GB/T 50854-2024, measurement standard for building works and decoration works, Annex E Table E.6.1 (code 010506) and Annex E notes items 2, 3, 9, 10, 11, 12 and 13; Annex C Clause C.3.14; Annex B Clause B.3.13. This standard has replaced GB 50854-2013; verify the corresponding clause numbers when applying old-edition clauses.
  • GB/T 50857-2024, measurement standard for municipal works, Annex J Table J.1.1 (code 040901) and Clause J.2.1 (anchorage bars, lifting hooks and position-fixing support bars merged in; other laps not counted; non-design support bars not counted).
  • GB/T 50861-2024, measurement standard for urban rail transit works, Clause B.9.1 (pile length; rebar cages listed under Annex B.6) and Clause B.9.3 (rebar merged in; non-design support bars not counted; non-design post-installed bars not listed).
  • Regional consumption standards: SJG 111.1-2022 Clause 3.2.2 item 4 (cages computed in tonnes as design-drawn length in use x unit theoretical mass, including helical reinforcement); SJG 181.2-2024 Clause 5.2.2; Chapter 5 notes of the Jiangsu building and decoration consumption standard (one splice per 9m, hanger bars merged, extra-long helical laps not added).
  • Detailing and construction: DBJ 52/T 088-2018 Clause 6.4.2 (cage fabrication tolerances, helical link detailing, stiffening rings, assembly in sections); DBJ/T 15-236-2021 Clause 6.2.3; DBJ/T 36-055-2019 (splice numbers and weld lengths); DB11/T 1832.1-2021 Clause 16.4.9; JGJ/T 419-2018 Clauses 4.3.4 and 5.7.2; JGJ 106-2014 Clause 10.3.2 (sonic tube numbers and arrangement); TB 10218-2019 Clause 5.3.1 (sonic tube embedment).
  • Railway and regional quota items: TB/T 10823-2024, railway works budget quota manual, Volume 2 Bridge and Culvert Works, Chapter 1 Section 4 (7), rebar cage fabrication and installation QY-210 to QY-213 (single-layer and double-layer cage fabrication and installation, sonic tube fabrication and installation); DB11/T 2382-2024 Annex A Table A.3.2 item A-3-16 (sonic tube embedment, measured in m).
  • The geometric derivation of helical link cutting lengths and the values of end horizontal segments, hooks and laps may be found in the dedicated card on helical link cutting length cited by this card.

Keywords

  • 钢筋笼
  • 螺旋箍筋
  • 加劲箍
  • 主筋
  • 桩基钢筋工程量
  • 单位理论重量
  • GB/T 50854-2024
  • 灌注桩钢筋