Railway 2024 quotas: linking the basic-quota rebar fabrication items (YY-30~34) with the budget-quota rebar fabrication-erection items, and preventing double pricing (TB/T 10821-2024)
The composite "rebar fabrication-erection / fabrication-tying-erection" items in the budget quotas (e.g., bridge volume QY-210~213 rebar cages) already include fabrication (sourced from basic-quota Chapter 3 YY-30~34) — adding the fabrication items again within the same BOQ item double-counts labor and plant. TB/T 10821-2024's general notes state that only "rebar transport, concrete mixing, concrete transport, and short-haul material transport" apply to estimate (budget) compilation; rebar fabrication is a compilation basis for the discipline budget quotas, not a pricing library; fabrication items exclude rebar consumption — when cited for missing items, add materials with operating waste, add 1.5% lap for non-coupled bars over 10 mm, and "mesh" fabrication applies only to bars <=10 mm.
Applicable Codes
- TB/T 10821-2024 · Basic Quota of Railway Engineering
- TB/T 10823-2024 · Budget Quota of Railway Engineering (Volume 2: Bridge and Culvert Works)
Topic Positioning
The linkage between the rebar fabrication items (YY-30~YY-34) of TB/T 10821-2024 Chapter 3 and the discipline budget quotas' composite "rebar fabrication-erection / fabrication-tying-erection" items (e.g., bridge volume QY-210~QY-213 rebar cages): the basic quotas are a compilation basis, not a pricing library — applying fabrication items again in ordinary estimates double-prices.
Core Conclusions
- Positioning: compilation basis vs compiled result. TB/T 10821-2024 general note 1 states the volume "serves the compilation of discipline quotas for railway works (buildings excepted) and the compilation of railway estimates (budgets)", of which only "rebar transport", "concrete mixing", "concrete transport", and "short-haul material transport" apply to estimate (budget) compilation for railway works excluding buildings — rebar fabrication is not among them. Chapter 3's fabrication items are a basis for compiling discipline quotas, not for direct pricing.
- Budget-quota rebar items already include "fabrication". Bridge volume QY-210 single-layer cage fabrication-erection: "including rebar fabrication and tying, welding, placing, positioning, correcting"; QY-212 double-layer: "including fabrication and tying, coupler connection, placing, positioning, correcting"; the track volume's ballastless cast-in-place rebar: "fabrication and tying, including straightening, rust removal and protection, cutting, bending, bundling, stacking, welding and tying"; the buildings and water volumes likewise. Adding YY-30~YY-34 within the same BOQ item counts fabrication labor and plant twice — double pricing.
- Numerical corroboration (base-period data): YY-30 cage fabrication's labor + plant is markedly below QY-210 (land) single-layer fabrication-erection's labor + plant — the composite item is precisely "fabrication (from basic-quota Chapter 3) + tying and erection + placing", its material cost being the rebar itself (with waste), fabrication consumptions already inside.
- Correct use: (1) Ordinary estimates: apply the budget-quota composite item directly (bored-pile cages QY-210/211/212; sonic tubes QY-213); do not add YY-30~YY-34. (2) Where the budget quotas have no matching item (new materials/processes needing self-analysis): price with YY-30~YY-34 fabrication consumptions (labor + plant) + rebar material + tying/erection. Note Chapter 3's note (as written): fabrication items "exclude rebar consumption — when cited, supplement per the works part and rebar kind, with operating waste; for non-coupled bars over 10 mm, add 1.5% lap"; "mesh" fabrication applies only to bars <=10 mm. (3) Rebar transport (Chapter 3 Section 2, unit 10 t): expressly applicable to estimate (budget) compilation — transport from the central yard to site may be booked separately, no conflict with fabrication. (4) Confusable exceptions: the track volume's "mesh installation" and "formed-rebar hoisting" items cover only installation/hoisting (for factory-formed semi-finished rebar) — site-fabricated rebar needs separate fabrication analysis, purchased formed rebar prices as a finished material, but neither may return to the "fabrication + tying" composite items. Also: basic-quota fabrication assumes "centralized CNC processing" (Chapter 3 note 2) — hand processing on site needs measured consumptions, not direct copying.
Applicable Boundaries
- Only the railway 2024 system (TB/T 10821-2024 + discipline volumes such as TB/T 10823-2024, TB/T 10831-2024); other sectors or editions need their own rules.
- The conclusions target whether "fabrication" is double-booked; transport, tying and welding, and cage placing follow their own items.
- Units: fabrication per t (fabricating 1 t of formed rebar); transport per 10 t.
- This card does not cover rebar quantity rules (lap lengths, theoretical weights, post-tensioning adjustments) — see the cited card.
Further Reading
- TB/T 10821-2024: general notes 1-10 (scope and the four estimate-applicable contents; labor/material consumption composition; HT-0/CL-0 items; prices per TB 10811-2024, TB/T 10813-2024, TB/T 10814-2024; "within/below/~ includes the upper limit"); Chapter 3 "rebar" notes; Section 1 fabrication YY-30~YY-34 (cage, cap cage, mesh, small members, other), Section 2 transport.
- TB/T 10823-2024 Volume 2: Chapter 1 Section 4 (7) cage fabrication-erection QY-210~QY-213.
- Companion cards: the quota system and base-period price mechanism (TB 10801/10811/10813/10814-2024); the five-way framework for detecting double pricing; general pile pricing calibers (empty holes, rock sockets, slurry, cages, head cropping); bored-pile steel casing pricing rules.
Keywords
- 基本定额
- 钢筋制作
- TB/T 10821
- 钢筋笼制安
- QY-210
- double counting
- YY-30
- 预算定额衔接