Quota pricing route for micro-disturbance cement mixing piles (IMS piles): workmanship classification, quota-gap determination and cement-content conversion

Micro-disturbance cement mixing piles (IMS piles) are a workmanship variant of deep cement mixing piles (T/ZS 0141-2020 Article 2.1.1); pricing lands in the deep cement mixing pile items of the ground-treatment chapter, not a new pile type; because the rig and workmanship parameters differ from conventional triaxial practice (high-pressure air-assisted cutting shall not be used; dedicated combined augers), triaxial items cannot be casually applied, nor pin-type items misattributed - where no matching item exists, treat as a quota gap (first adapt the nearest similar workmanship, else compile a supplementary unit-rate build-up schedule on quota principles for approval); where the cement content differs from the quota basis, stack the per-additional-1%-cement or plus-minus-5-kg/m adjustment items instead of editing consumptions directly.

Applicable Codes

  • T/ZS 0141-2020 微扰动水泥搅拌桩设计与施工技术规程(第1.0.1、2.1.1、2.1.2、3.0.2、4.3.1、5.3.6条)
  • TB/T 10831-2024 铁路工程预算定额 Vol. 10 房屋工程(FY-211~FY-216)
  • TB/T 10822-2024 铁路工程预算定额 Vol. 1 路基工程(LY-251~LY-255)
  • 浙建建发〔2026〕90号 公布浙江省建设工程计价依据(2025版)第一阶段八部成果
  • https://jst.zj.gov.cn/col/col1229129246/art/2026/art_2d41e689d738dfc3f22b558687a3f1dc.html

Scope of the question

Where micro-disturbance cement mixing piles (IMS piles) sit in the current pricing quota system: what pile class they are, whether quotas carry a matching item, how to convert where none exists, and how cement-content differences are adjusted. For pricing and review of new-workmanship piles and quota-gap piles.

Core conclusions

1) Classify the workmanship first - a variant of deep cement mixing piles, not a new pile type. T/ZS 0141-2020 Technical Specification for Design and Construction of Micro-Disturbance Cement Mixing Piles, Article 2.1.1: micro-disturbance cement mixing pile, soil-cement mixing pile with weak disturbance - a deep cement mixing pile built with a dedicated rig and optimised parameters balancing slurry pressure against ground pressure so as to reduce the disturbance of pile construction on surrounding soil and the environment. Article 2.1.2 defines the rig: the mixing auger combines bottom cutting blades, top orthogonally arranged mixing blades and intermediate free blades, with natural slurry-discharge channels on the drill stem ... classified as types I, II and III.

2) The differences from conventional triaxial practice lie in rig and parameters; the pile-forming sequence itself matches the quota work content. The quota cement-mixing items' work content - rig positioning, slurry injection while drilling and mixing, mixing withdrawal, repeated injection-drilling-mixing, repeated mixing withdrawal, pile completion, shifting - is identical for micro-disturbance piles. Differences: conventional mixing and jet grouting generally use high-pressure air-assisted cutting, disturbing the surroundings; micro-disturbance Article 5.3.6 forbids high-pressure air-assisted cutting when mixing soil, using combined augers instead, with water jets from added outlets reducing mixing resistance for pile diameters over 1200 mm. Equipment: high power, low self-weight (type III 24.45 t, max torque 71.2 kN.m, max treatment depth about 35 m, auger 800-1600 mm, total machine mass far below the roughly 120 t of triaxial rigs), verticality to 1/250, full numeric control, downward auger surcharge controllable within 15 kPa - hence suited to sensitive settings: adjacent metro shield tunnels, river revetments, shallow-founded buildings (Article 3.0.2). Cement content: Article 4.3.1 requires not less than 15%, more for muck and mucky soils; 18-22% is common in practice.

3) Pricing landing point and the pile-type red line. Apply the deep cement mixing pile items (single, twin, triaxial, pin-type etc.) of the ground treatment / soil-cement improvement chapter. As a workmanship variant with identical forming sequence it should not stand as a new pile type; but with big rig and parameter differences it should neither casually take a triaxial item nor be misattributed to pin-type items. Zhejiang is strict on pile-type / item correspondence (review practice: bidirectional mixing piles wrongly under deep mixing items, correct under pin-type mixing items) - IMS piles should accordingly be treated as a gap, not forced onto an item.

4) Order of handling where no item matches. Quota-gap rules: 1) first adapt the nearest similar workmanship item (cross-volume / cross-industry allowed within that quota's rules); 2) absent any reference, compile a supplementary unit-rate build-up schedule on quota compilation principles and submit for approval by the quota authority - no up-rating, no splitting of operations into double counting.

5) Conversion form for differing cement content. Mixing-pile items are compiled at stated contents with companion content-adjustment items. Illustrating the invocation form only: TB/T 10831-2024 Volume 10 Buildings FY-211 single-shaft mixing pile at 13% cement, FY-212 single-shaft per additional 1%, FY-213 triaxial at 18%, FY-214 triaxial per additional 1%, FY-215 triaxial empty bore, FY-216 section steel insert and withdraw; TB/T 10822-2024 Volume 1 Roadbed Works LY-251 mixing pile at 55 kg/m, LY-252 content plus-minus 5 kg/m, LY-253 pin-type mixing pile at 16%, LY-254 / LY-255 bidirectional mixing piles (diameter d50 / d60 cm, 70 kg/m). Where the design content sits above or below the quota basis, stack the per-additional-1% or plus-minus-5-kg/m items (or deduct in reverse), adjusting only materials and the related charges - never edit the quota's consumption standards directly.

6) Version-timing check first (Zhejiang). The first-phase eight documents of the Zhejiang 2025 pricing basis were published by Zhe Jiang Jian Jian Fa [2026] No. 90, effective 1 November 2026, repealing the 2018 Zhejiang building / decoration and municipal budget quotas; in transition, tendered works are judged by the tender-notice date and non-tendered by the contract date - determine the applicable version by those dates, not by the current calendar year.

Applicability limits

  • The workmanship classification (a deep cement mixing variant) holds nationwide; specific item numbers and content-adjustment items must be verified in the industry / local quota volume of the project - the FY-* and LY-* here only illustrate the adjustment form; cross-industry use must satisfy the quota concerned.
  • Where the full 2025 item tables are unpublished, no claim can be made that 2025 adds a micro-disturbance / IMS item; this card concludes only no dedicated item has been seen and a gap treatment applies - verify the current volume text and chapter notes before relying on it.
  • Gap treatment must not serve up-rating (taking IMS piles onto higher-priced items) or operation-splitting double counting; supplementary quotas need approval by the quota authority before serving as a pricing basis.
  • Content adjustment touches only materials and related charges; consumptions are quantity standards and are not altered at will for design content or site conditions.

Further reading

  • T/ZS 0141-2020 Technical Specification for Design and Construction of Micro-Disturbance Cement Mixing Piles: Articles 1.0.1 (background and rig parameters), 2.1.1 / 2.1.2 (terms and rig types), 3.0.2 (uses and sensitive settings), 4.3.1 (cement content), 5.3.6 (no high-pressure air-assisted cutting).
  • TB/T 10831-2024 Railway Works Budget Quota Manual, Volume 10 Buildings, Chapter 1 Section 2 piles and foundations - other piles - cement mixing piles, FY-211 to FY-216.
  • TB/T 10822-2024 Railway Works Budget Quota Manual, Volume 1 Roadbed Works, Chapter 3 Section 5 soil-cement piles - cement mixing piles, LY-251 to LY-255.
  • Zhejiang 2025 pricing basis notice (Zhe Jiang Jian Jian Fa [2026] No. 90): https://jst.zj.gov.cn/col/col1229129246/art/2026/art_2d41e689d738dfc3f22b558687a3f1dc.html