Treating unit-works pile foundation (bored pile) quantities below the quota table's listed amounts: labour and plant of the corresponding items x 1.25, with no separate small-works addition

Building and decoration consumption quotas handle 'unit-works pile quantities below the table thresholds' by quota-consumption conversion - labour and plant of the corresponding items x 1.25 (materials excluded) - not by creating a 'small-works addition' fee item; the two are different layers, and the same quantities may never take both the factor and the addition. The bored-pile measurement base differs by volume (quantities per the measurement rules / concrete from the cap interface to the toe excluding bore protection / placed concrete volume) - check the threshold table of the volume in use.

Applicable Codes

  • 陕西省《新编消耗量定额》(2024 年征求意见稿)第三章 桩基工程 说明第五条、第六条、表3-1
  • 湖南省《房屋建筑与装饰工程消耗量标准》(2025 版)第三章 桩基工程 说明第六条
  • 江苏省《建筑与装饰工程消耗量》(2026 版)第三章 桩基工程 说明第四条
  • SJG 111.1-2022 · Consumption Standard for Urban Utility Tunnel Works (Shenzhen) 第 3.1.2 条、Table 3.1.2

Positioning

When unit-works pile foundation quantities (rotary bored piles etc.) are small, the building and decoration consumption quotas put the 'sub-scale' compensation inside quota-consumption conversion (labour and plant x 1.25), not into a separate 'small-works addition'. This card gives the clause texts of several quotas, the threshold tables, the bored-pile measurement differences, and the separation from companion factors (test piles, raking piles).

Core conclusions

1. Clause texts and locations (citable)

  1. Shaanxi New Consumption Quota (2024 draft), chapter 3 pile foundations, note 5 + Table 3-1: 'Where the unit works' pile quantities fall below the amounts of Table 3-1, the corresponding items take labour and plant x 1.25. For bored piles the unit works' pile quantities mean those computed per the measurement rules.' Table 3-1: precast concrete square piles 200m3; prestressed concrete pipe piles 1000m; precast concrete sheet piles 100m3; rotary, rotary-bored and helical bored piles 150m3; impact, punch-hole, reamed and driven-tube bored piles 100m3; steel pipe piles 50t.
  2. Hunan 2025, chapter 3, note 6: 'Where the unit works' pile quantities fall below the table, the corresponding items take labour and plant x 1.25. Pile quantities mean the concrete of the load-bearing part from the pile-cap interface to the toe (excluding bore protection), the mass of steel pipe piles and the length of precast piles.'
  3. Jiangsu 2026, chapter 3, note 4: 'Where the driven (bored) pile quantities of a unit works fall below the table, labour and plant (including pile-following) take the corresponding items x 1.25.'
  4. SJG 111.1-2022 (utility tunnels, Vol. 1), clause 3.1.2 item 1: 'Where the unit works' pile-foundation quantities are within the amounts of Table 3.1.2, the corresponding pile items take labour cost and plant consumption x 1.25; for bored piles the unit works' pile quantities mean the placed concrete volume.'

2. How the conversion runs

  1. Labour and plant only: labour cost and machine-shift consumption x 1.25 together; materials (concrete, slurry, turnover) never - material wastage and work content unchanged.
  2. Measured over the whole unit works: the trigger is the unit works' total pile quantity below the threshold; single piles or single sub-items never trigger; different pile types compare against their own thresholds within the same unit works.
  3. Leave a trail: suffix the converted item with 'conv.' and note in the compilation statement 'chapter x note x of xx quota: unit-works pile quantities below the table, labour and plant x 1.25'.

3. The bored-pile measurement base (decides triggering; differs by volume)

  • Shaanxi: quantities per that quota's measurement rules (bored piles), no separate bore-protection deduction.
  • Hunan: the concrete of the load-bearing part from the cap interface to the toe (excluding bore protection); steel pipe piles by mass, precast piles by length.
  • Shenzhen SJG 111.1-2022: placed concrete volume; item 3 of the same clause adds that boring depth includes the empty-bore depth, pricing not distinguishing empty from solid bores - empty bores take the corresponding items with materials per design.

4. The '1000' confusion

In Shaanxi's Table 3-1, '1000' is the prestressed concrete pipe pile threshold in metres, not a bored-pile volume; bored piles run 150m3 (rotary / rotary-bored / helical) and 100m3 (impact / punch / reamed / driven-tube). Where a volume's table does list a bored-pile volume threshold, that is only a different gate - the treatment stays labour-and-plant x 1.25, never an addition fee.

5. Companion factors in the same notes (never mix)

  • Shaanxi: standalone test piles and anchor piles - driving labour and plant x 1.50; rake up to 1:6 x 1.25, over 1:6 x 1.43; driving on slopes over 15 degrees x 1.15; driving in pits (over 1.5m deep, up to 500m2) or trenches (over 1m deep) x 1.11; within 3 degrees of rake, vertical-pile items.
  • Jiangsu: test piles - labour and plant of the driving items x 2; idle machine-shifts during testing trued up at settlement.

6. Layer separation from the 'small-works addition'

The 'small / minor works addition' is an independent fee item in some sectoral estimate regulations, running base x rate; the building-pile 1.25 is a quota-consumption conversion. Different layers - the same quantities never take both factor and addition, else double charging. Rates and gates follow the applicable sectoral regulations.

Applicable boundaries

  • For pile works under building and decoration (including municipal-building) consumption quotas; whether highway, railway, water or transport quotas set such factors or separate small-works additions follows their own regulations - never copy this card's factors.
  • The factor touches labour and plant consumption only - not materials, not work content; and it never replaces separately charged items (site levelling, surface compaction, obstruction clearance, coring, load tests, dynamic tests - excluded in every volume's notes).
  • Threshold values are each volume's own - never across volumes or editions; clause numbers may shift between editions - cite the edition in use.
  • How 'one unit works' is drawn follows the contract and pricing bases; different divisions change whether thresholds trigger.

Further reading

  • Shaanxi 2024 draft chapter 3 notes 5-6 and Table 3-1; Hunan 2025 chapter 3 note 6 and its table; Jiangsu 2026 chapter 3 notes 1-5 and the per-unit pile quantity table; SJG 111.1-2022 clause 3.1.2 items 1-3 (Table 3.1.2).
  • Comparison directions: empty bore / rock entry / slurry / rebar cages / head cropping charged apart; per-pile-type measurement rules.