conversion of quota items to suit conditions
- 01
Re-derivation of the all-in unit rate when a changed construction method makes the quota machine-shift consumption inapplicable: the three-path quota conversion test, the hierarchy of bases for recalculating plant consumption, the requirements for recasting the all-in unit rate analysis sheet, and the procedure for confirmation by the employer
Changes of construction method and plant usage are factors expressly lis…
GB/T 50500-2024 建设工程工程量清单计价标准 第8.9.1条、第8.9.6条、第8.10.2条、第8.10.3条、第8.1.2条、第8.1.3条、第2.0.9条、第6.2.1条、第6.2.12条、第6.2.13条及App. EGB/T 51095-2015 建设工程造价咨询规范 第5.3.2条、第5.3.9条、第5.3.12条及App. CGB/T 50875-2013 工程造价术语标准 第2.3.3条、第2.3.5条、第2.3.6条2026-10-25 - 02
Treating unit-works pile foundation (bored pile) quantities below the quota table's listed amounts: labour and plant of the corresponding items x 1.25, with no separate small-works addition
Building and decoration consumption quotas handle 'unit-works pile quant…
陕西省《新编消耗量定额》(2024 年征求意见稿)第三章 桩基工程 说明第五条、第六条、表3-1湖南省《房屋建筑与装饰工程消耗量标准》(2025 版)第三章 桩基工程 说明第六条江苏省《建筑与装饰工程消耗量》(2026 版)第三章 桩基工程 说明第四条2026-10-24 - 03
Quota conversion coefficients and item adjustment rules for masonry and vertical-surface insulation works (wall over-height, curved masonry, double fair-faced boundary walls, rubble slope protection over-height, curved wall / column-surface insulation labour and material coefficients)
TB/T 10831-2024 Volume 10 Buildings, volume notes: where masonry wall he…
TB/T 10831-2024 · Budget Quota of Railway Engineering (Volume 10: Housing Works) 册说明 第三节 砌筑工程 第 1~14 条TB/T 10831-2024 · Budget Quota of Railway Engineering (Volume 10: Housing Works) 册说明 第三节 立面保温隔热 第 1~4 条陕西省新编消耗量定额(征求意见稿)砌筑工程说明(地方系数对照)2026-10-08 - 04
Whether conversion is allowed when the actual construction process differs from the quota norms: general principle, permitted situations, prohibited red lines, and the step-down path for missing items
General principle: quota norms are compiled on the basis of a rational p…
DB63/T 2013-2022 公路养护工程预算定额DB63/T 2006-2021 公路钢筋混凝土装配式结构定额SJG 111.2-2022 城市地下综合管廊工程消耗量标准2026-09-25 - 05
Audit of pricing by applying quota line items: identifying over-application, misapplication, and duplicate application via the three-way comparison
Identify problems of pricing by applying quota line items using the "thr…
GB/T 51095-2015 建设工程造价咨询规范DL/T 5468-2013 输变电工程施工图预算编制导则DBJ51/T 048-2015 四川省建设工程造价电子数据标准2026-09-25 - 06
Checklist of permitted quota-conversion situations and prohibited red lines: when conversion is allowed and how to convert
Quota conversion takes "express permission in the quota provisions" as t…
DB63/T 2013-2022 公路养护工程预算定额DB63/T 2006-2021 公路钢筋混凝土装配式结构定额TB/T 10834-2024 铁路工程预算定额 Vol. 13 站场工程2026-09-25 - 07
Triage rules when quota materials differ from actually used materials: variety/species per express quota rules or via design change; same material — adjustment for price differentials only
First triage the type of "different material": for a variety/species cha…
DB63/T 2013-2022 公路养护工程预算定额TB/T 10834-2024 铁路工程预算定额 Vol. 13 站场工程TB 10801-2024 铁路基本建设工程设计概(预)算编制办法2026-09-25 - 08
Conversion judgment and methods when a quota item's work content differs from site reality (no conversion for aggregated content; convert by difference type; supplementary valuation for missing items; "换" mark traceability)
Before converting, judge "whether conversion is allowed": content alread…
GB/T 51095-2015 建设工程造价咨询规范DL/T 5468-2013 输变电工程施工图预算编制导则TB/T 10831-2024 铁路工程预算定额 房屋工程2026-09-25 - 09
Avoiding mispricing when material names are similar but specifications differ: three lines of specification-checking defense across preparation, pricing, and audit
The three forms of mispricing (specifications missing from item characte…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 51095-2015 建设工程造价咨询规范DB42/T 823-2021 建设工程造价咨询质量控制规范2026-09-25 - 10
Red-line checklist of situations where norm resource consumption must not be adjusted: no adjustment except where conversion is expressly permitted; adjusting quantity is not adjusting price
Quota norms are compiled on the basis of a rational project execution pl…