Whether conversion is allowed when the actual construction process differs from the quota norms: general principle, permitted situations, prohibited red lines, and the step-down path for missing items
General principle: quota norms are compiled on the basis of a rational project execution plan (construction methodology and site organization) and normal conditions; except where the quota norms expressly allow conversion, no change to the quota norms is permitted because the project execution plan, operating method, or material consumption differs from the quota norms (DB63/T 2013-2022 Clause 5.5). Permitted conversions require express written rules (strength grades per mix-ratio tables; dry-to-wet mortar at 1.75 t + 0.3 m3 water = approx. 1.0 m3 wet mix plus deduction of the tank mixer shift; fair-faced wall labour cost coefficients 1.15/1.30; admixtures counted separately; ready-mixed concrete deducts the mixing equipment); different mix ratios, cement types, or machinery types/specifications are never convertible. Where conversion is impossible, step down: adjusted application -> quota of similar processes -> compiling a supplementary quota item submitted for approval.
Applicable Codes
- DB63/T 2013-2022 公路养护工程预算定额
- DB63/T 2006-2021 公路钢筋混凝土装配式结构定额
- SJG 111.2-2022 城市地下综合管廊工程消耗量标准
- DL/T 5468-2013 输变电工程施工图预算编制导则
- DL/T 5464-2013 火力发电工程初步设计概算编制导则
Topic Positioning
When the actual construction process, material type, or machinery configuration differs from the quota line item provisions, whether the norm resource consumption or unit price can be adjusted: the general principle of judgment, permitted situations, and prohibited red lines.
Core Conclusions
General principle: quota norms are compiled on the basis of a rational project execution plan (construction methodology and site organization) and normal conditions; except where the quota norms expressly allow conversion, no change is permitted because the project execution plan, operating method, or material consumption differs (DB63/T 2013-2022 Clause 5.5). Permitted conversions require express written rules: different strength grades are converted per the mix-ratio tables; converting dry-mixed to wet-mixed mortar follows 1.75 t dry mix + 0.3 m3 water = approx. 1.0 m3 wet mix, deducting the tank mixer shift and the skilled labour cost per the local standard; changing a common (plastered) brick wall to a fair-faced brick wall multiplies the labour cost by 1.15 for one face and 1.30 for two faces; admixture costs are counted separately with the cement quantity adjusted; changing site mixing to ready-mixed concrete deducts the material and mixing-equipment consumption. Prohibited red lines: different mix ratios, different cement types, and different machinery types/specifications are never convertible.
Applicable Boundaries
Applies to judging the application and conversion of budget quota norms, consumption quotas (resource norms), and maintenance quota norms; specific conversion coefficients and skilled-labour cost deductions follow the current quota norms of the project location. Content already comprehensively included in the quota norms (e.g., formwork covering both steel and timber supports) must not be adjusted; contractor's in-house norms are set by the contractor itself.
Further Reading
DB63/T 2013-2022 Clauses 5.5, 5.6, 5.8; DB63/T 2006-2021 Clause 4.3; SJG 111.2-2022 general provisions 0.3.5, masonry 4.1.8; for the missing-item step-down path see DL/T 5468-2013 Clause 4.1.4 and DL/T 5464-2013 Clause 4.1.5 (supplementary quota items submitted to the quota administration agency for approval before use).