Triage rules when quota materials differ from actually used materials: variety/species per express quota rules or via design change; same material — adjustment for price differentials only

First triage the type of "different material": for a variety/species change, non-load-bearing materials follow express quota conversion rules for consumption conversion (mix-proportion tables, stabilized-soil mix formulas, dry/wet mortar equivalent interchange, admixture/ready-mixed concrete adjustments), while load-bearing structural materials (rebar/sections/timber) must go through design change and equal-strength/equal-section substitution procedures — not quota conversion; changing only the price of the same material is purely an adjustment for price differentials (consumption fixed; price difference = quota consumption x (compilation-period price - base-period price)). Red lines: cement variety, actual construction mix proportion, and machinery type/species differences are never converted; site losses are already included and not counted again.

Applicable Codes

  • DB63/T 2013-2022 公路养护工程预算定额
  • TB/T 10834-2024 铁路工程预算定额 Vol. 13 站场工程
  • TB 10801-2024 铁路基本建设工程设计概(预)算编制办法
  • DB22/T 5027-2019 混凝土小型空心砌块砌体工程施工技术标准
  • GB/T 50772-2012 木结构工程施工规范
  • GB/T 50875-2013 工程造价术语标准

Topic Positioning

The judgment framework when quota sub-item materials differ from the actually adopted materials: first triage "variety/species change" vs "price change" — the former does consumption conversion or goes through design change, the latter adjusts price only without touching quantity.

Core Conclusions

  1. Same material, different price — adjustment for price differentials only: price difference = quota consumption x (compilation-period price - base-period price), consumption fixed (TB 10801-2024 §3.2, §4.1.2).
  2. Variety/species change requires an express quota rule: different strength grades convert per mix-proportion tables; stabilized-soil base per Ci=[Cd+Bdx(H-H0)]xLi/Ld; dry-mixed to wet-mixed mortar per 1.75t+0.3 m³ water approximately equals 1.0 m³, deducting tank-mixer shifts; admixtures counted separately; site mixing changed to ready-mixed concrete deducts mixing-equipment consumption.
  3. Load-bearing structural materials (rebar/sections/timber) changing variety/species is not quota conversion — a design change is required, with equal-strength/equal-section substitution verified by the design unit (DB22/T 5027-2019 §4.5.5, GB/T 50772-2012 §3.0.5).
  4. Red lines: actual construction mix proportion, cement variety, and machinery type/species differences are never converted; site (within-yard) losses are already in the quota and off-site losses are in the material price — neither may be counted again.

Applicable Boundaries

Common to all specialty consumption-quota systems; specific conversion coefficients follow the volume prefaces; no conversion before the design change is established, and converted sub-items are suffixed "converted" for traceability; provisionally priced materials and brand changes go through the quality-and-price confirmation procedure (see related cards).

Further Reading

DB63/T 2013-2022 Chapter 5 and Appendix B (mix-proportion formulas); TB/T 10834-2024 Volume 13 volume preface Chapter 6 (formula examples); TB 10801-2024 §3.2, §4.1.2 (price differences); DB22/T 5027-2019 §4.5.5; GB/T 50772-2012 §3.0.5; GB/T 50875-2013 Section 2.3.