adjustment for price differentials
- 01
Railway 2024 quota plant rate per machine-shift composition: Class 1 (fixed) vs Class 2 (variable) cost division and price adjustment rules (TB 10801-2024 clauses 3.3/4.1.2; TB 10811-2024 clause 2.3)
Under the railway 2024 quota system, of the seven components of the cons…
TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects 第3.3节、第4.1.2条TB 10811-2024 · Fee schedule for design estimates and budgets of capital railway works 第2.3节TB/T 10814-2024 · Quota for Shift Costs of Construction Machinery and Tools of Railway Engineering2026-09-25 - 02
Railway estimate (budget) price adjustment rules: the labour/materials/plant three-line adjustment method and its place in the item-estimate procedure (TB 10801-2024 section 4.1, Table 2.6.2)
TB 10801-2024 clause 4.1.1: price adjustment means the reasonable adjust…
TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects 第4.1节、第3.2节、第3.14节、第2.6节及Table 2.6.2TB 10811-2024 · Fee schedule for design estimates and budgets of capital railway worksTB/T 10813-2024 · Base Period Prices of Materials for Railway Engineering2026-09-25 - 03
GB/T 50500-2024 rules for adjusting price differences, management fee, and tax after the actual price of provisionally priced materials/equipment is determined (Section 8.4)
Per GB/T 50500-2024 Section 8.4, once the actual price of provisionally…
GB/T 50500-2024 第 8.4.1、8.4.5、8.4.6 条GB/T 50500-2024 第 2.0.14、3.2.11、8.1.8 条2026-09-25 - 04
Triage rules when quota materials differ from actually used materials: variety/species per express quota rules or via design change; same material — adjustment for price differentials only
First triage the type of "different material": for a variety/species cha…
DB63/T 2013-2022 公路养护工程预算定额TB/T 10834-2024 铁路工程预算定额 Vol. 13 站场工程TB 10801-2024 铁路基本建设工程设计概(预)算编制办法2026-09-25 - 05
Steel price adjustment calculation: price-information adjustment formula, per-specification per-period threshold checks with adjustment on actual basis, and tax treatment (GB/T 50500-2024 Appendix A.2)
Steel price adjustment uses the price-information adjustment method (GB/…
GB/T 50500-2024 App. A.2GB/T 50500-2024 第3.3.5条GB/T 50500-2024 第8.7.2条2026-09-25 - 06
Railway 2024 quota-norm system price fluctuation provision: formula, annual growth-rate selection, and distinction from compilation-period adjustment for price differentials (TB 10801/10811-2024)
The price fluctuation provision (TB 10811-2024 clause 2.14.1) is compute…
TB 10801-2024 铁路基本建设工程设计概(预)算编制办法 第3.14节、第4.1节、第2.5.1条、Table 2.6.2TB 10811-2024 铁路基本建设工程设计概(预)算费用定额 第2.14节(公式2.14.1)2026-09-25 - 07
Framework of causes for the gap between quota norms and actual market construction costs: social-average vs contractor-specific levels, base-period vs market prices, six source dimensions, and practical responses
Quota norms are a pricing benchmark compiled under normal construction c…
GB/T 50875-2013 工程造价术语标准GB 50501-2007 水利工程工程量清单计价规范TB 10801-2024 铁路基本建设工程设计概(预)算编制办法2026-09-25 - 08
Determining material cost within the all-in unit rate: the two-step norm resource consumption × material unit price method, special situations, and the tax-exclusive boundary
Material cost = norm material consumption × norm-based material price fo…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 50875-2013 工程造价术语标准GB/T 51095-2015 建设工程造价咨询规范2026-09-25