Railway 2024 quota plant rate per machine-shift composition: Class 1 (fixed) vs Class 2 (variable) cost division and price adjustment rules (TB 10801-2024 clauses 3.3/4.1.2; TB 10811-2024 clause 2.3)

Under the railway 2024 quota system, of the seven components of the construction-plant shift price (depreciation/overhaul/maintenance/erect-dismantle/labor/power/other), depreciation, overhaul, maintenance and erect-dismantle are Class 1 (fixed) costs and labor, power and other are Class 2 (variable); likewise the four components of instrument shift prices (depreciation/maintenance/calibration/power). Compilation-period price differences adjust only labor and power (recomputed as compilation-period composite labor / fuel / utility prices x shift consumptions); Class 1 costs and other fees stay at base-period quota values; difference = quota shift consumption x (compilation-period shift price − base-period shift price) — adjust price only, never quantity — mutually exclusive with the labor and material difference lines (shift-internal labor and utilities must not be double-adjusted).

Applicable Codes

  • TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects 第3.3节、第4.1.2条
  • TB 10811-2024 · Fee schedule for design estimates and budgets of capital railway works 第2.3节
  • TB/T 10814-2024 · Quota for Shift Costs of Construction Machinery and Tools of Railway Engineering
  • TB/T 10813-2024 · Base Period Prices of Materials for Railway Engineering

Topic Positioning

Under the railway 2024 quota system (TB 10801-2024 "Measures for compiling design estimates (budgets) of railway capital construction projects" + TB 10811-2024 "norms for on-costs and expenses" + TB/T 10814-2024 "Railway works construction plant and small tools machine-shift fee quota"): the cost composition of construction plant rate per machine-shift, the Class 1 (fixed)/Class 2 (variable) division, and the practical rules of "which parts are adjusted and how" in compilation-period price adjustment.

Core Conclusions

  1. Cost composition (TB 10801-2024 clauses 3.3.1-3.3.2): plant and small tools cost = construction plant cost + instrument cost; construction plant cost = sum(quota construction-plant machine-shift consumptions x machine-shift rate); instrument cost = sum(quota instrument machine-shift consumptions x machine-shift rate).

  2. The seven components of the construction-plant machine-shift rate (clause 3.3.4 verbatim): depreciation, overhaul, maintenance, erect/dismantle, labour, power, and other fees — depreciation recovers the budget price over total durable machine-shifts; overhaul restores function at prescribed overhaul intervals; maintenance includes all levels of maintenance, temporary fault clearance, amortization of replacement equipment and random tools/attachments, lubricants and wiping materials, and maintenance during standdown; erect/dismantle includes on-site labour, materials, plant, trial runs and auxiliary facilities; labour means "wages of personnel specifically operating the plant, not listed in the works quotas"; power means fuels plus water and electricity consumed in operation; other fees mean vehicle/vessel tax, insurance and inspection fees paid per state regulations.

  3. Class 1/Class 2 division (per the column layout of TB/T 10814-2024 cost-composition tables): Class 1 (fixed) = depreciation + overhaul + maintenance + erect/dismantle, set from plant budget prices and durable machine-shifts, unaffected by compilation-period prices; Class 2 (variable) = labour + power + other, where labour = machine-shift worker-days x composite labour rate and power = petrol/diesel/electricity/gas/water consumptions x unit prices, moving with compilation-period prices, while other fees are quota-fixed and join no adjustment. Instrument machine-shift rates have four components (clause 3.3.5): depreciation, maintenance, calibration, power — the first three fixed, power variable.

  4. Price adjustment method (clause 4.1.2 item 3 verbatim): "Construction plant and small tools cost price adjustment: computed as the quota-tabulated construction-plant and instrument machine-shift consumptions times the difference between the corresponding compilation-period and base-period machine-shift rates." The compilation-vs-base-period difference in plant and small tools cost is listed as plant and small tools cost price difference in the item estimate (budget) (clause 3.3.3) — price only, never quantity.

  5. Setting base- and compilation-period machine-shift rates (TB 10811-2024 clause 2.3.2 verbatim): "Machine-shift rates computed from the fuel prices of TB/T 10813 'Railway works material base-period prices' plus this quota's base-period composite labour rate and base-period utility prices serve as base-period machine-shift rates; those computed from compilation-period composite labour, fuel and utility prices serve as compilation-period machine-shift rates." Practical rule: compilation-period machine-shift rate = base-period Class 1 costs (depreciation + overhaul + maintenance + erect/dismantle, unchanged) + compilation-period labour (compilation-period composite labour rate x machine-shift worker-days) + compilation-period power (compilation-period fuel/electricity/water/gas prices x machine-shift consumptions) + base-period other fees (unchanged) — the price adjustment effectively arises only from labour and power within Class 2.

  6. Mutual-exclusion clauses against double adjustment (clause 4.1.2 items 1-2): the labour cost differential on quota labour consumption "excludes labour within construction-plant machine-shifts"; the water/electricity price adjustment "excludes water and electricity consumed by construction plant and small tools machine-shifts" — machine-shift-internal labour and utilities are already adjusted through the machine-shift rate's labour and power and must not be re-listed under labour or material price adjustments.

  7. Basis linkage (clause 3.3.6): machine-shift rates are set per TB 10811; for plant absent from TB/T 10814, supplementary machine-shift fee quotas shall be compiled as the basis (TB 10811-2024 clause 2.3.1).

Applicable Boundaries

Applies to compiling and auditing railway capital construction design estimates (budgets) under the new system effective 2025-01-01 (TB 10801-2024, TB 10811-2024, TB/T 10814-2024). "Price adjustment covers only labour + power; Class 1 unchanged" is a railway-system conclusion; other sectors follow their own machine-shift fee quotas (highway JTG/T 3833 has a like-structured machine-shift rate but pricing and adjustment follow sector documents). Plant and small tools cost price difference belongs to the estimate (budget) "price difference" category — a different mechanism from contract adjustment for cost fluctuation (GB/T 50500-2024 Appendix A adjustment based on published price information); do not mix, and it does not apply to material or labour cost differentials — three lines computed and summed separately.

Further Reading

  • TB 10801-2024: section 3.3 (plant and small tools cost, clauses 3.3.1-3.3.6: composition definitions, Class 1/2 division, price difference listing), clause 4.1.2 (price adjustment methods for the three lines and the exclusion clauses).
  • TB 10811-2024: section 2.3 (clauses 2.3.1-2.3.2: bases for base- and compilation-period machine-shift rates).
  • TB/T 10814-2024 cost-composition tables (Class 1/2 columns; verify the labour, power, other and fixed-cost columns in chapter tables such as track works plant), clauses 1.0.4-1.0.6 (machine-shift rate composition, erect/dismantle fee, residual-value rate).
  • TB/T 10813-2024 "Railway works material base-period prices" (base-period fuel prices).