Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Rules when quota plant differs from the plant actually used on site: machine-shift consumption locked, adjustment for price differentials, and three legitimate paths

Where the type or specification of plant differs from that actually used in construction, the machine-shift consumption (quantity) is locked and no conversion is permitted — higher or lower actual plant efficiency is no ground for adjusting the quantity; the only permissible routes are three: (1) plant adjustments expressly laid down in the quota norms (e.g. layered compaction machine-shifts x 2.0, dry-mixed to wet-mixed mortar deducting mixer machine-shifts, switching to ready-mixed concrete deducting batching-plant machine-shifts); (2) where technical conditions differ materially, adapting and applying a similar quota; (3) where the machine-shift cost quota does not cover the item, compiling a supplementary machine-shift cost quota. Price differences are dealt with through adjustment for price differentials, with the quantity untouched: plant usage cost differential = quota machine-shift consumption x (machine-shift rate per machine-shift at the compilation date - machine-shift rate per machine-shift at the base date).

Applicable Codes

  • DB63/T 2013-2022 公路养护工程预算定额
  • TB 10801-2024 铁路基本建设工程设计概(预)算编制办法
  • TB 10811-2024 铁路基本建设工程设计概(预)算费用定额
  • TB/T 10814-2024 铁路工程施工机具台班费用定额
  • TB/T 10834-2024 铁路工程预算定额 Vol. 13 站场工程
  • SJG 111.2-2022 城市地下综合管廊工程消耗量标准
  • DL/T 5468-2013 输变电工程施工图预算编制导则

Topic Positioning

Answers "how to handle quota plant differing from the plant actually used in construction": where the type or specification differs, the machine-shift consumption is locked and no conversion is permitted; the permissible routes are express quota rules, adapted application, and supplementary machine-shift cost quotas; price differences go to adjustment for price differentials.

Core Conclusions

Quantity and price are handled separately: (1) Where the type or specification of plant differs from the quota, converting the machine-shift consumption is not allowed — quota plant is comprehensively determined on the basis of normal, reasonable project execution planning and reflects the social-average level; actually using plant of a different power rating or model is no ground for adjusting the quantity. (2) There are only three legitimate routes: plant adjustments expressly laid down in the quota norms (e.g. where compaction thickness exceeds the limit and compaction is carried out in layers, grader/roller machine-shifts x 2.0; dry-mixed mortar replaced by wet-mixed mortar, deducting mixer machine-shifts; site batching replaced by ready-mixed concrete, deducting batching-plant machine-shifts); where the technical conditions differ materially from the basis of the quota, adapting and applying a similar quota according to the project conditions; where the machine-shift cost quota does not cover the machine, compiling a supplementary machine-shift cost quota as the pricing basis. (3) Same plant at a different price — adjustment for price differentials with the quantity untouched: plant usage cost differential = quota machine-shift consumption x (machine-shift rate per machine-shift at the compilation date - machine-shift rate per machine-shift at the base date), the base-date and compilation-date rates being recalculated using the comprehensive labour, fuel, and water/electricity prices of the respective periods; the machine-shift rate per machine-shift comprises 7 items: depreciation, overhaul, maintenance, assembly/disassembly, labour, power, and other costs. (4) Red line: optimising plant selection falls within project execution planning and bid competition and is no ground for altering the public quota norms.

Applicable Boundaries

Applies to the handling of plant differences when pricing under consumption quotas (resource norms) or budget quotas; cases expressly permitted by the quota to be converted follow the quota; hired plant is priced as agreed between employer and contractor; scheme-level back-calculation of plant "model - count - machine-shifts" is outside the scope of this card.

Further Reading

See DB63/T 2013-2022 Clause 5.8 (plant type/specification not convertible), Clause 5.6(e) (ready-mixed concrete deducts batching-plant machine-shifts); railway system: TB 10801-2024 Clause 4.1.2 item 3 (method of adjustment for price differentials on construction plant and tools), TB 10811-2024 Section 2.3 (plant and small tools cost), TB/T 10814-2024 Clause 1.0.4 (7-item composition of the machine-shift rate per machine-shift); TB/T 10834-2024 Volume 13 road chapter (layered mixing/compaction machine-shifts x 2.0); SJG 111.2-2022 General 0.3.5 (dry/wet mortar conversion); DL/T 5468-2013 Clause 4.1.4 (rules for adapted application).

Keywords

  • 定额机械换算
  • 机械台班消耗量
  • 机械种类规格不同
  • 台班单价价差调整
  • 基期编制期
  • 补充台班费用定额
  • 机械调整系数
  • 商品混凝土拌和台班