Determining construction machinery "model — quantity — machine-shift" in construction schemes: selection logic, back-calculation formula, and machine-shift rate composition

Machinery configuration follows the logic chain "construction method → model selection → back-calculation of quantity → conversion into machine-shifts": first select the model by matching the work process with quota items, then back-calculate the required number of machines by N = Q ÷ (P×T×b×k) from the work quantity, per-shift output, planned duration, shifts per day, and utilization rate, and finally convert into machine-shifts and link up with the industry machine-shift fee quota; the machine-shift unit rate consists of seven components: depreciation, overhaul, maintenance, erection and dismantling, labor, power, and other costs.

Applicable Codes

  • GB/T 50502-2009 建筑施工组织设计规范
  • GB/T 50430-2017 工程建设施工企业质量管理规范
  • TB/T 10814-2024 铁路工程施工机具台班费用定额
  • JTG/T 3833-2018 公路工程机械台班费用定额

Topic Positioning

The integrated method for determining "machinery model — quantity — machine-shift" when preparing construction method statements: model-selection logic, the quantity back-calculation formula, the machine-shift concept and machine-shift rate composition, and the key points of linking up with industry machine-shift fee quotas.

Core Conclusions

Determination follows one logic chain: first fix the construction method (process → machine type → specification), then back-calculate the quantity as "work quantity ÷ per-shift output ÷ available time", and finally convert into machine-shifts and connect with the quota. The plant configuration plan shall determine the types and quantities of machinery according to the site deployment strategy and the construction programme (GB/T 50502-2009, Clause 5.4.2); the plant provided shall satisfy construction needs, be subject to approval, and may be procured or leased (GB/T 50430-2017, Clause 7.2.1). Quantity estimation formula: N = Q ÷ (P×T×b×k), where Q is the work quantity of the sub-item undertaken by that machine, P the per-shift output (per the shift-output quota or rated capacity × working-condition derating), T the planned duration in days, b the shifts per day, and k the shift utilization rate (empirically 0.75–0.85); check against peak periods, and standby machines should be considered for leading machines on the critical path. A machine-shift is the cost unit of one machine operating normally for one work shift (8 h); the machine-shift unit rate consists of seven components — depreciation, overhaul, maintenance, erection and dismantling, labor, power, and other costs (TB/T 10814-2024, Clause 1.0.4; JTG/T 3833-2018 has the same structure, 13 categories and 972 items). The model selected should, as far as possible, fall within a machine-shift quota line item; where no corresponding item exists, a supplementary item must be compiled; the quota machine-shift rate is a base-period price, and price differences at the compilation period are counted separately.

Applicable Boundaries

Applies to machinery configuration estimating and machine-shift cost estimation at the project execution plan / construction method statement stage, and is generally applicable across industries priced by machine-shift quotas — buildings, railways, highways, etc. The quantity formula is an approximate scheme-estimation method and cannot replace the quota pricing path (budget machine-shifts = sub-item work quantity × quota line item machine-shift consumption, where the quota already includes the machinery range difference). Machine-shift working hours and base-period price levels differ by industry (e.g., diving equipment 6 h per machine-shift, transformers and distribution equipment counted per 24 h day); use the current quota edition in force.

Further Reading

See GB/T 50502-2009, Code for Project Execution Planning of Building Works, Clause 5.4.2 (resource configuration plan); GB/T 50430-2017, Code for Quality Management of Construction Enterprises, Clause 7.2.1 (construction plant and facilities management); TB/T 10814-2024, Quota of Machine-Shift Rates for Construction Plant of Railway Works, Clauses 1.0.1–1.0.6 (machine-shift rate composition, residual value ratio, machine-shift definition); JTG/T 3833-2018, Quota of Machine-Shift Rates for Highway Machinery, general notes (13 categories, 972 items, 8 h machine-shift).