How quotas list plant fuel (and power) consumption and the "daily consumption" conversion: no standalone daily quota exists - the machine-shift fuel and power consumption governs (GB/T 51366-2019 Annex C, TB/T 10814-2024, and sector and local machine-shift cost quotas)
The quota system carries no standalone "daily consumption quota" heading; fuel and power list per machine-shift: petrol (kg per shift), diesel (kg per shift), electricity (kWh per shift), water (t per shift), gas (m3 per shift). One machine-shift = one working shift = 8 h, so the shift consumption is in substance one shift's fuel; daily use converts as daily = shift consumption x shifts worked per day (double shift x 2). Sources: MHURD Rules for Compiling Construction Plant Machine-Shift Costs (Jianbiao [2015] No. 34), carried by GB/T 51366-2019 Annex C table C.0.1 "energy use of common construction plant"; sector bases in TB/T 10814-2024 (railway - power cost split into petrol / diesel / electricity / gas / water) and JTG/T 3833-2018 (highway - items 5-7 variable costs); provincial machine-shift quotas and rules all carry a "labour and fuel-and-power quantities" column, priced at local budget or market rates.
Applicable Codes
- 《建设工程施工机械台班费用编制规则》(住房和城乡建设部 建标〔2015〕34号)
- GB/T 51366-2019 · Technical Standard for Application of Building Photovoltaic Systems App. C Table C.0.1
- T/CABEE 062-2024《建筑企业碳排放监管平台技术要求》附录B 表B.0.1
- TB/T 10814-2024 · Quota for Shift Costs of Construction Machinery and Tools of Railway Engineering
- TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects 第3.3节
- JTG/T 3833-2018 · Quota for Shift Costs of Highway Engineering Machinery
- JGJ/T 222-2011 · Technical Specification for Durability Rehabilitation and Protection of Concrete Structures 第5.2.5条
- T/HNCT 001-2022《湖南省建筑工程绿色施工评价标准技术细则》第11.2.7条
Topic Positioning
Answering "is there a daily fuel-consumption quota for construction plant": the listing unit of machine fuel (oil, power, water, gas) in the current pricing / quota system, the authoritative sources, and the conversion of shift consumption to daily consumption - for compiling machine-shift rates, fuel cost estimates, green-construction energy statistics and carbon accounting.
Core Conclusions
No standalone "daily quota"; fuel and power list per machine-shift: petrol (kg/shift), diesel (kg/shift), electricity (kWh/shift), water (t/shift), gas (m3/shift), with a power-cost subtotal. One shift = one working shift = 8 h, so the "shift consumption" is in substance one shift's fuel; daily use converts as daily = shift consumption x shifts per day (double shift x 2).
National general basis: the MHURD Rules for Compiling Construction Plant Machine-Shift Costs (Jianbiao [2015] No. 34) fix the per-shift fuel and power consumption of each machine. GB/T 51366-2019 Standard for Building Carbon Emission Calculation, Annex C table C.0.1 "energy use of common construction plant per shift" carries them verbatim: "the per-shift energy consumption of common construction plant may be taken from table C.0.1. ... Table C.0.1 is drawn from the MHURD Rules (Jianbiao [2015] No. 34)." An association standard carries the same stock: T/CABEE 062-2024, annex B table B.0.1, "drawn from GB/T 51366-2019".
Sector machine-shift quotas:
- Railway: TB/T 10814-2024 Railway Works Plant and Machine-Shift Cost Quota lists, per shift under "cost make-up - power cost", petrol (kg), diesel (kg), electricity (kWh), gas (m3) and water (t) with a power subtotal, plus labour days and labour cost.
- Highway: JTG/T 3833-2018 Highway Plant Machine-Shift Cost Quota, items 5-7 (labour, fuel and power, other) are variable costs - "when compiling machine-shift rates, the operator counts and fuel-and-power consumption shall follow the values in this quota".
Cost make-up of the shift rate: machine-shift rate = depreciation + overhaul + maintenance + erection-and-removal and off-site transport + labour + power (fuel) + other; items 1-4 are fixed, labour, fuel-and-power and other are variable. Power cost covers the fuels, water and power consumed in operation. The shift consumption is a statutory quantity standard, never adjusted for price movement; prices may be taken at local budget or market rates (provincial rules commonly tabulate labour (days), petrol (kg), diesel (kg), electricity (kWh), coal (kg), firewood (kg), water (m3)).
A second route for hauling plant (JGJ/T 222-2011 clause 5.2.5): fuel of construction hauling plant preferably computes F_o = sum of K_i x D_i, F_o the fuel (L), K_i the tonne-kilometre consumption of plant type i [L/(t.km)], D_i its workload (t.km); tonne-km rates follow machine performance, distances the method statement and site conditions.
On-site statistical check (T/HNCT 001-2022 clause 11.2.7): keep fuel logs for heavy consumers and compute unit use between refuellings: unit use = fuel drawn / shifts worked, to check quota values and plan plant demobilisation.
Applicability Boundaries
- For compiling machine-shift rates, fuel / power cost estimates, green-construction energy statistics and carbon accounting.
- Shift fuel-and-power consumption is a quota quantity standard - never self-adjust for site conditions except where the quota expressly allows; deviations belong in enterprise consumption databases, shift logs or site certified records, never in the quota itself.
- Hired plant: actual fuel and standby charges follow the hire contract and site records - never the owned-plant quota basis; fuel prices at local budget or market rates.
- Sector / local quotas classify plant differently (highway by class into items, railway by chapter) - use the current edition matching the discipline; never transplant consumption figures across sectors.
Further Reading
- GB/T 51366-2019, annex C table C.0.1 (drawn from Jianbiao [2015] No. 34).
- MHURD Rules for Compiling Construction Plant Machine-Shift Costs (Jianbiao [2015] No. 34).
- T/CABEE 062-2024, annex B table B.0.1.
- TB/T 10814-2024 Railway Works Plant and Machine-Shift Cost Quota, chapter 2 general plant (power section); with TB 10811 (railway cost quotas) and TB 10801-2024 section 3.3 (plant and machine use cost make-up).
- JTG/T 3833-2018, items 5-7 variable costs and local maintenance supplement notes (operator counts and fuel per the quota; fuel at local site budget prices).
- JGJ/T 222-2011 clause 5.2.5 (hauling fuel formula); T/HNCT 001-2022 clause 11.2.7 (unit-use statistics).
Keywords
- 机械设备油料日消耗定额
- 台班燃料动力消耗量
- 施工机械台班能源用量
- 柴油消耗量 kg/台班
- GB/T 51366-2019 附录C
- TB/T 10814-2024
- 日耗油量折算
- plant rate norms per machine-shift