How a contractor builds its own labour, material and machinery consumption database: three-level structure, data sources, error handling and self-growth
Per T/ZBD 100.1-2022, a contractor's consumption database is organised as a three-level tree — specialty works → work sections/work-section items → work items (process level) — with each node recording the all-in unit rate + labour/material/machinery consumption + factor prices; labour consumption is measured on site by work-study recording / time measurement (basic + extra-haulage + auxiliary labour + margin); materials are back-derived by the four-quantity ledger check (actual consumption = opening stock + deliveries − closing stock − returns − scrap recovery) or net quantity × (1 + wastage rate); machinery by machine-shift operation records (actual machine-shifts = quantity ÷ actual output per machine-shift); data are hierarchically aggregated → gross errors removed → adjustment coefficients applied → random errors averaged, then calibrated against local quota norms, moving towards self-growth through automated collection on smart construction sites.
Applicable Codes
- T/ZBD 100.1-2022 建设工程造价数据建设通用标准
- DB11/T 2382-2024 建设工程施工消耗量标准
- TB/T 10821-2024 铁路工程基本定额
- GB 50501-2007 水利工程工程量清单计价规范
Topic Positioning
This card covers how a contractor distils its own construction efficiency into a labour/material/machinery consumption database (the data foundation of its in-house norms): how to structure the database, where the three consumption data come from, how data are processed and calibrated, and how the database keeps updating.
Core Conclusions
Per T/ZBD 100.1-2022 General Standard for Construction Cost Data Development:
- Database structure: a three-level tree — specialty works → work sections / work-section items → work items (process level) — with each node recording the all-in unit rate, labour/material/machinery consumption and factor prices; the process level is the key granularity for building the database (e.g. for bored piles, hole forming, rebar cage fabrication and placement, concreting and pile head cropping are modelled separately).
- Data sources: labour — field measurement by work-study recording / time measurement (basic labour + extra-haulage labour + auxiliary labour + labour margin, on the 8-hour workday); materials — actual consumption back-derived from delivery notes + requisition slips + stocktake ledgers (opening stock + current-period deliveries − closing stock − returns − scrap recovery), theoretical values as net quantity × (1 + wastage rate), turnover materials amortised per use = one-time usage ÷ number of reuses (amortization cycles); machinery — machine-shift operation records (actual machine-shifts = quantity ÷ actual output per machine-shift), supplemented by rental settlements and fuel ledgers.
- Data processing: hierarchical aggregation by measured item → measurement method → project → gross-error identification and removal → adjustment coefficients rated against labour quota levels → random-error treatment and arithmetic averaging.
- Calibration and updating: benchmark against the local consumption quota (resource norm) (parts below the social average are the contractor's competitiveness); in the early stage use the local quota norms as the template and replace with measured values item by item; in the middle stage rely on smart construction sites to auto-collect actual data; in the long run form a self-growing knowledge base on big-data thinking, supporting tender (priced offer) pricing, labour/material planning and supply-chain management.
Applicable Boundaries
Applies to contractors building internal cost and pricing data and refining labour/material planning; not for direct external pricing (external pricing still follows the contractually agreed bases). Measured values are affected by region, equipment and management level and must not be shared directly across enterprises or regions; single measurements with insufficient samples should not be extrapolated — keep collecting and accumulating.
Further Reading
Database content list: T/ZBD 100.1-2022 Clause 5.2.8; three-level tree structure: Clause 6.2.4; smart construction sites and data application: Clause 6.4.5; big-data self-growth: Clause 6.1.1; consumption measurement methods: DB11/T 2382-2024 Clauses 3.2–3.3; turnover material amortisation: TB/T 10821-2024 (railway basic (fundamental) quota manual) Chapter 9 and JGJ/T 222-2011 Clause 5.2.3.
Keywords
- 消耗量数据库
- contractor's in-house norms
- 人工消耗量测定
- material consumption
- 机械台班消耗
- 智慧工地
- 成本管理数据
- 写实记录法