Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Determining quota material consumption: net quantity + loss composition, determination by four material classes, and the construction consumption formula

Material consumption = net quantity + unavoidable wastage (including transport, processing, operating and storage wastage); main and auxiliary materials per net quantity × (1 + wastage rate); turnaround materials per amortized quantity (one-time use ÷ number of reuses (amortization cycles)) or rental quantity; sundry low-value materials estimated as a proportion of material cost; data collected by field observation, with gross errors rejected and random errors averaged. Based on GB/T 50875-2013, DB11/T 2382-2024 §3.3, TB/T 10821-2024.

Applicable Codes

  • GB/T 50875-2013 工程造价术语标准
  • DB11/T 2382-2024 建设工程施工消耗量标准
  • TB/T 10821-2024 铁路工程基本定额
  • T/CSCS 035-2023 膜结构工程消耗量标准
  • GB/T 50851-2013 建设工程人工材料设备机械数据标准

Topic Positioning

Determining and computing material consumption in quota compilation: composition, determination methods by class, and the construction consumption formula — for compiling consumption/budget quotas, measuring supplementary quota items and reading quota items.

Core Conclusions

Material consumption = net quantity + unavoidable wastage (GB/T 50875-2013 §2.3.16); wastage includes transport, processing, operating and storage wastage. Determined by four classes (DB11/T 2382-2024 §3.3): (1) main/auxiliary materials = net quantity + wastage; construction consumption = net quantity × (1 + wastage rate); (2) turnaround materials that are one-time or low-value perishable are measured by amortized quantity (one-time use ÷ number of reuses (amortization cycles)); standardized tool-type materials are measured by rental quantity; (3) sundry low-value “other materials” are not itemized by name and quantity; they are estimated as a proportion of material cost. Mix-type materials (concrete, mortar): take the mix-proportion data group closest to the net quantity as the net quantity value, then multiply by (1 + wastage rate). Data flow: field-observation collection -> summary in unified units -> gross-error rejection -> averaging of random errors -> determination of net quantity and wastage.

Applicable Boundaries

Applies to consumption/budget quota compilation basis; for railways (TB/T 10821-2024), wastage includes on-site handling and operating wastage; wastage rates are in Chapter 10; quota contents already include wastage; T/CSCS 035-2023 provides the membrane-structure specialty basis. This card excludes material unit prices and material-cost computation.

Further Reading

GB/T 50875-2013 §2.3.16 (definition), §2.3.1 (consumption quota); DB11/T 2382-2024 §3.3 (determination and computation procedure); TB/T 10821-2024 general notes (wastage convention); GB/T 50851-2013 (composition of pricing basis).

Keywords

Cited By