Engineering Knowledge Cards.
Confidence HighUpdated 2026-10-25

Where material wastage is booked, and the double counting and omission tests: off-site transport and storage losses into the material unit price (price factor) versus site haulage and operation losses into the quota consumption (quantity factor), with the site warehouse / designated stockpile point as the boundary, plus a comparison of booking positions for typical work items and settlement audit checkpoints

Material wastage may enter only one of the material unit price (price factor) or the quota consumption (quantity factor); the dividing line is the site warehouse / designated stockpile point. Losses before the line (source to site warehouse) - transport loss and store-keeping loss - go into the material unit price (highway lists an off-site transport wastage rate separately; railway folds it into purchasing and custody charges; building works list a transport loss charge plus a storage loss); losses after the line (warehouse / stockpile point to the point of working or installation) - transport, processing, working and on-site stockpiling losses - go into the quota consumption. Since material cost = quota material consumption x norm-based material price, each factor carries only its own segment of wastage and nothing repeats: multiplying the same segment into both factors (overstating by roughly that wastage rate) is double counting; missing from both is omission. When applying quotas to compile a budget, the wastage rate must not be applied once more on top of the quota consumption (consumption = net quantity x (1 + wastage rate) is an algorithm at the level of quota compilation and measurement only).

Applicable Codes

  • TB 10801-2024 · Measures for Compilation of Design Estimates and Budgets of Railway Capital Construction Projects 第3.2.1~3.2.6条、第4.1.2条
  • TB/T 10821-2024 · Basic Quota of Railway Engineering 总说明第四条、Ch. 5砌筑说明、附录《材料工地搬运及操作损耗率》
  • TB 10811-2024 · Fee schedule for design estimates and budgets of capital railway works 第2.2节 Table 2.2.2
  • TB/T 10813-2024 · Base Period Prices of Materials for Railway Engineering
  • JTG 3830-2018 · Measure for Compilation of Preliminary Estimates and Budgets of Highway Construction Projects 第3.1.2条、Table 3.1.2-2
  • JTG/T 3832-2018 · Budget Quota of Highway Engineering 附录四
  • GB/T 50875-2013 · Standard glossary of project costs 第2.3.16条
  • DB11/T 2382-2024 · Standard for Construction Consumption of Construction Works (Beijing) 第3.3.1、3.3.6条
  • DB/T 29-200-2019《天津市建筑工程绿色施工评价标准》第2.0.5条
  • DB63/T 2013-2022 · Budget Quota for Highway Maintenance Works (Qinghai) Ch. 5说明
  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第3.6.3条
  • T/ZBD 100.5-2023 · Work Guideline for Settlement Audit of Construction Works 第3.1.7条、第5.0.11条
  • 湖北省建筑安装工程费用定额(2024)材料费组成

Scope

Answers the pricing question 'does material wastage go into the material unit price or into the quota consumption, and how are double counting and omission avoided': gives the dividing line between the two routes, the corresponding formulas and variable definitions, the tests for double counting and omission, the sources of wastage rates (table numbers), a comparison of where typical items such as rebar, concrete, sand and aggregate book their wastage, and the checkpoints of settlement audit. Applies to the preparation of estimates and budgets, to rate build-up and to final account review across the railway, highway and building sectors.

Core Conclusions

1. Dividing principle: the site warehouse (designated stockpile point) is the boundary

  • Losses before the boundary (material source to site warehouse / designated stockpile point): transport loss and store-keeping (storage) loss go into the material unit price (price factor).
  • Losses after the boundary (site warehouse / central stockpile / on-site processing point to the point of working or installation): transport loss, processing loss, working loss and on-site stockpiling loss go into the quota consumption (quantity factor).

Sector basis: 1 Highway, JTG 3830-2018 Clause 3.1.2: 'the norm-based material price consists of the material price at source, freight and handling charges, off-site transport loss, and purchasing and custody charges'; 'off-site transport loss means the loss of certain materials occurring in the normal transport process'; the material off-site transport wastage rates are given in Table 3.1.2-2; freight and handling charges are 'the charges for moving material from the supply point to the site warehouse (the place where material is stored at the construction site)'. 2 Railway, TB 10801-2024 Clauses 3.2.4 and 3.2.5: 'the norm-based material price consists of the material price at source, freight and handling included in the price, and purchasing and custody charges'; 'norm-based material price = (material price at source + freight and handling included in the price) x (1 + purchasing and custody rate)'; Clause 3.2.5 item 3 defines purchasing and custody charges as 'all charges incurred in the procurement, supply and custody of materials, including purchasing charges, storage charges, site custody charges, transport loss charges and storage loss charges, and the charges of consignment handling... the rate of purchasing and custody charges follows the Cost Quota for Design Estimates and Budgets of Railway Capital Construction Works TB 10811' - railway thus lists no separate off-site transport wastage rate; transport loss is folded into purchasing and custody charges. 3 Building works cost quota basis (Hubei Building and Installation Works Cost Quota 2024): material cost includes 'the material price at source, material freight and handling charges (all charges from the source to the site warehouse or designated stockpile point), the transport loss charge (unavoidable loss of material in transport and handling), and purchasing and custody charges (covering purchasing charges, storage charges, site custody charges and storage loss)'. 4 The boundary of the quantity factor is fixed in the consumption standards. Beijing DB11/T 2382-2024 Clause 3.3.1 item 1: 'the consumption of principal and auxiliary materials comprises the net quantity and the loss quantity; the net quantity is the net material consumption needed to complete a unit of acceptable product under sound use; the loss quantity covers transport loss, processing loss, working loss and on-site stockpiling loss from the site warehouse, central on-site stockpile or on-site processing point to the point of working or installation; wastage rates of common materials are expressed in percent'; temporary (formwork-type) materials 'are measured separately by amortised or hired quantities', and sundry materials are expressed as a percentage of cost. 5 Railway TB/T 10821-2024 general notes, item 4: 'the material consumption in this volume of quotas includes the net quantity and the loss quantity. The loss quantity covers site haulage and operation loss, meaning all losses of material from the site material store or stockpile to the point of installation (or working), including transport, working and on-site stockpiling losses... see Chapter 10 of this volume for the site haulage and operation wastage rates; except where otherwise stated, the material consumption in this volume includes the loss.' 6 Terminology (GB/T 50875-2013 Clause 2.3.16): material consumption means 'the net quantity plus the unavoidable loss of each class of material consumed in producing the unit of construction product stated in the quota under normal construction conditions'; Tianjin DB/T 29-200-2019 Clause 2.0.5: material wastage rate (%) = (loss quantity / total quantity) x 100%, the loss covering on-site transport loss, stockpiling loss and working loss.

2. Formulas and variables

  • Material cost = sum over items of (quota material consumption x norm-based material price) (TB 10801-2024 Clause 3.2.2).
  • Quota material consumption = net quantity x (1 + working wastage rate eta). This is an algorithm at the quota compilation and measurement level (DB11/T 2382-2024 Clause 3.3.6: for rebar and sections, 'the working consumption is calculated as the net principal material quantity multiplied by (1 + material wastage rate)'; mixed-by-proportion materials likewise). When a budget applies a quota, take the consumption already built into the quota item; do not multiply the wastage rate in again.
  • Norm-based material price (price factor), sector formulas: Highway: norm-based material price = (material price at source + freight and handling) x (1 + off-site transport wastage rate delta) x (1 + purchasing and custody rate k) - recoverable value of packaging (JTG 3830-2018 Clause 3.1.2). Railway: norm-based material price = (material price at source + freight and handling included in the price) x (1 + purchasing and custody rate k), transport and storage losses being inside k (TB 10801-2024 Clause 3.2.5). Building works / published cost information basis: material price = (material price at source + freight and handling) x (1 + transport wastage rate) x (1 + purchasing and custody rate).
  • The correct material cost of one item is then net quantity x (1 + eta) x unit price, with unit price = (source price + freight and handling) x (1 + delta) x (1 + k) (highway) or (source price + freight and handling included in the price) x (1 + k) (railway). Double counting is present whenever eta and delta (or the transport loss folded into k) are applied twice to the same segment.

3. Testing for double counting and omission (the two loss classes differ in nature and cannot substitute for each other) Off-site transport loss (delta, or folded into k on railway) and site haulage and operation loss (eta) are losses of different segments and different nature: they can neither substitute for one another nor be stacked. 1 Double counting (overstatement): the same segment multiplied into both the price and the consumption - for example applying an extra 1.5% onto the unit price of rebar whose quota consumption already carries 1.5% site loss, or applying (1 + eta) twice to the consumption; the overstatement is approximately the wastage rate itself (repeating a 1.5% loss overstates by 1.5%; repeating 2% overstates 2%). 2 Cross-system borrowing (the commonest railway double count): the railway purchasing and custody rate already contains transport and storage losses; applying the highway Table 3.1.2-2 off-site transport wastage rate on top (sand 2.5%) counts the transport loss twice, overstating by roughly 2.5%. 3 Omission: neither segment booked. Typical misses - the highway basis omitting the off-site rate delta and the purchasing and custody rate k; the railway basis assuming 'railway has no transport loss' and dropping the purchasing and custody charge, or assuming the quota contains everything and stripping the in-site loss back out of the quota quantity. 4 The working rule (usable directly for self-check): 'in-site (warehouse to point of use) into the quantity; off-site (source to warehouse) into the price; one segment enters one factor only; the two factors never share a segment.' Express authority: the highway maintenance quota DB63/T 2013-2022 Chapter 5 notes: 'materials, finished and semi-finished products in the quotas already include in-site transport and operation losses, and no addition is allowed when compiling a budget; off-site transport loss and store-keeping loss of materials shall be considered within the norm-based material price.' 5 A frequently missed point at quota level: some quota chapters already fold site loss into the quota (e.g. TB/T 10821-2024 Chapter 5 masonry note 2, 'this chapter already includes site haulage and operation loss'); applying the appendix rate again on top of such quotas is double counting; only items not covered by the appendix need the appendix rate.

4. Where typical items book their wastage

Item In the price factor (material unit price) In the quantity factor (quota consumption)
Rebar Highway Table 3.1.2-2 lists no steel (delta taken as 0); purchasing and custody k: highway steel 0.75%, railway per the applicable rate in TB 10811 Table 2.2.2 Plain round bars d<10, wire, strand and wire rope 1.5%; plain round d no less than 10 and ribbed bars (welded) 1.5%; ribbed bars (mechanical splices) 1%; small products and semi-products made of rebar 0.5%
Cast-in-place concrete Highway ready-mixed concrete carries no purchasing and custody charge (k = 0) and Table 3.1.2-2 lists no concrete; railway books it at the unified purchasing and custody rate Concrete (cast-in-place) 2%; concrete (precast) 1%; concrete (self-compacting, ballastless track) 10%
Sand, crushed stone Highway off-site transport loss: sand 2.5% in general areas, 5% in sandstorm areas; stone chip / crushed gravel / sand-gravel / cinder / industrial slag / coal 1% (0.4% per additional handling); railway: transport loss already inside the purchasing and custody charge (sand per TB 10811-2024 Table 2.2.2), no separate off-site loss added Sand (gravel) 2%; crushed stone, pebbles, gravel and white pebble 2%; crushed, pebble and naturally graded ballast 3%; rubble 2%; block stone, dressed stone and flagstone 1%
Cement Highway off-site transport loss 1% (0.4% per additional handling; bagged cement carried over 500km by truck adds 0.5 percentage points) Cement 2%; cement (for pipe joints and mechanical pipelines) 6%; cement grout 5%; mortar (masonry) 2%; mortar (rendering and pointing) 3%; cement-asphalt mortar (ballastless track) 10%
Brick, block Highway off-site transport loss: brick, tile, drummed bitumen, lime and clay 3% (1% per additional handling); no listed item for blocks Brick 2%; firebrick 1.5%; ordinary concrete blocks 1%, hollow and special-shaped concrete blocks 3%, interlocking blocks 2%
Structural steel, plate Not listed in the highway off-site transport loss table (delta as 0), purchasing and custody at 'other materials 2.06%' (highway) / the railway purchasing and custody rate Structural steel 5% (four electrical services and machinery 3%); small products and semi-products of structural steel 0.5%; steel plate 5% (four electrical services and machinery 3%)

5. Settlement audit checkpoints 1 Fix the basis first: confirm the sector and quota edition of the project - railway must not apply the highway off-site transport wastage rate; highway must check that the price formula carries delta and k; building works must check that transport and storage losses are already in the published price or the unit price. 2 Then check 'already in the quota': where item or chapter notes state that site haulage and operation loss is included (e.g. the railway masonry chapter), no further wastage rate may be applied on top of the quota consumption; highway maintenance quotas state 'in-site transport and operation losses are included, and no addition is allowed when compiling a budget'. 3 Recompute the magnitudes: draw the large-value materials (steel, cement, sand and aggregate, concrete, brick) and verify the chain 'net quantity x (1 + eta) x unit price' against 'unit price containing delta and k', confirming that every wastage rate appears exactly once in the chain; the same percentage appearing in both the price and the consumption establishes double counting, and the overstated amount follows that rate. 4 Employer-supplied materials and over-draw: the employer should state a reasonable effective wastage rate for the materials it supplies; where the contractor draws more than 'quantity computed from the drawings + effective wastage rate' for reasons attributable to the contractor, the excess material cost is borne by the contractor, determinable by the employer at the unit price of the relevant supply contract and deductible from the price of the interim settlement by construction stage or of the final account; where the specification of the employer-supplied material mismatches the tender documents and pushes the actual rate above the effective rate, the excess is borne by the employer (GB/T 50500-2024 Clause 3.6.3). 5 Audit trail of the settlement review: re-check that prices of the same material in new rate build-ups are reasonable, that cross deductions are verified, and that the supporting settlement documents are fully signed (T/ZBD 100.5-2023 Clause 5.0.11); price fluctuation adjustment must check the base period and the adjustable scope, adjusting only the material price change cost and the corresponding taxes, with other costs untouched (Clause 3.1.7).

Applicability Boundaries

1 The 'site warehouse / designated stockpile point' boundary is common to all sectors, but the make-up of the price factor differs by sector: railway folds transport loss into purchasing and custody charges (no separate off-site rate); highway lists an off-site rate plus a separate purchasing and custody charge; building works and the published cost information basis use (source price + freight and handling) x (1 + transport wastage rate) x (1 + purchasing and custody rate). Cross-sector borrowing of rates (especially highway Table 3.1.2-2 into railway projects) is a classic error source. 2 Wastage rates must match the quota system in use: railway per the TB/T 10821-2024 Chapter 10 appendix, highway per JTG 3830-2018 Table 3.1.2-2, building works per the appendix of the local consumption quota; the same material may carry different rates in different systems (some building quotas take 2.5% for rebar, railway 1.5%/1%), and changing system means changing table. 3 This card gives no basis for adjusting wastage rates on a particular project: quota consumption is a quantity standard and, save where conversion is expressly allowed, may not be adjusted for actual construction organisation, actual mix proportions or plant type; a contractor's field-measured wastage rates serve assessment and internal management (variance analysis) and cannot directly modify quota consumption. 4 Ready-mixed concrete, asphalt mix and stabilised mix purchased ready-made carry no purchasing and custody charge under the highway basis; their loss appears only on the consumption side; purchased components and finished and semi-finished products carry a rate of 0.42%, and where their loss is booked must follow the class of the material concerned. 5 Where finishing and installation quotas carry separate in-site transport or secondary haulage items, first check whether the item content already includes it, to avoid applying in-site transport twice on a quota that already includes it.

Further Reading

  • Railway: TB 10801-2024 Measures for Preparing Design Estimates and Budgets of Railway Capital Construction Works, Clauses 3.2.1 to 3.2.6 (material cost and the norm-based material price), Clause 4.1.2 (price adjustment of material cost); TB/T 10821-2024 Basic Quota of Railway Works, general note 4, Chapter 5 masonry note 2, and the Chapter 10 appendix Site Haulage and Operation Wastage Rates of Materials; TB 10811-2024 Cost Quota for Design Estimates and Budgets of Railway Capital Construction Works, Section 2.2 Table 2.2.2 (purchasing and custody rates); TB/T 10813-2024 Base-Period Prices of Railway Works Materials.
  • Highway: JTG 3830-2018 Measures for Preparing Estimates and Budgets of Highway Construction Projects, Clause 3.1.2, Table 3.1.2-1 (material gross mass coefficient), Table 3.1.2-2 (material off-site transport wastage rates); JTG/T 3832-2018 Highway Works Budget Quota, Appendix IV.
  • Building and general: GB/T 50875-2013 Standard for Construction Cost Terminology, Clause 2.3.16; DB11/T 2382-2024 Consumption Standards for Construction Works, Clauses 3.3.1 and 3.3.6; DB/T 29-200-2019 Tianjin Standard for Green Construction Evaluation of Building Works, Clause 2.0.5 (definition of the material wastage rate); Hubei Building and Installation Works Cost Quota (2024), composition of material cost.
  • Settlement review: GB/T 50500-2024 Pricing Standard for Bills of Quantities of Construction Works, Clause 3.6.3 (over-draw of employer-supplied materials and the effective wastage rate); T/ZBD 100.5-2023 Work Guide for Settlement Review of Construction Works, Clause 3.1.7 (price adjustment), Clause 5.0.11 (review of deliverables); DB63/T 2013-2022 Highway Maintenance Works Budget Quota, Chapter 5 notes (in-site loss included; off-site loss in the price).
  • Extension: when applying highway quotas, check Table 3.1.2-2 for the material - unlisted items (steel, structural steel, plate, concrete) take delta = 0, so the price factor carries only the purchasing and custody charge and all loss falls on the quantity factor.