Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Whether published price information / base-period prices include the procurement and keeping fee: caliber determination (railway base-period prices fully include, most provincial price information excludes, highway adds separately)

The procurement and keeping fee is added by rate and not merged into the material original price. Railway base-period prices (TB/T 10813-2024), Classes A/B/C, all include the procurement and keeping fee (rates per TB 10811-2024 Table 2.2.2); the price information published by most provinces and cities uses the market-price caliber and excludes the fee, so it must be added separately when compiling budgets; a few publish "comprehensive prices including the fee", which must not be double-counted. Highway JTG 3830-2018 adds the fee separately on the basis of (original price + freight and miscellaneous charges + off-site transport loss). Always read the current issue's publication notes before use.

Applicable Codes

  • GB/T 50875-2013
  • TB 10801-2024
  • TB 10811-2024
  • TB/T 10813-2024
  • JTG 3830-2018

Topic Positioning

Determining whether published price information / base-period prices include the procurement and keeping fee: railway base-period prices fully include it, most provincial price information excludes it, and the highway sector adds it separately — preventing omission or double-counting of the fee.

Core Conclusions

The procurement and keeping fee is added by rate and not merged into the original price: material budget price = (original price + freight-and-miscellaneous charges within the price) x (1 + procurement-and-keeping rate) (TB 10801-2024 Clause 3.2.5). Three calibers: (1) railway base-period prices (TB/T 10813-2024), Classes A/B/C, all include the procurement and keeping fee at rates per TB 10811-2024 Table 2.2.2: rails/turnouts/sleepers/beams/bearings etc. 1.10%, cement 3.78%, crushed stone 3.45%, sand 4.47%, bricks/tiles/lime 4.98%, others 2.65%; (2) the price information of most provinces and cities uses the market-price caliber excluding the fee — add it separately when compiling budgets (generally 2%-3%); a few publish "comprehensive prices including the procurement and keeping fee", which must not be double-counted; (3) highway JTG 3830-2018 adds it separately as (original price + freight and miscellaneous charges + off-site transport loss) x rate: steel 0.75%, fuel and blasting materials 3.26%, the rest 2.06%; ready-mixed concrete, asphalt mixtures, and stabilized-soil mixtures are exempt; purchased members/finished/semi-finished products 0.42%.

Applicable Boundaries

Determination follows the current issue's publication notes (stating "including/excluding the procurement and keeping fee"); railway base-period prices are at the 2020 price level and exclude deductible input VAT, with the difference between the compilation period and the base period listed as a price difference; where freight and miscellaneous charges are listed outside the price, the procurement-and-keeping rate likewise applies; regional calibers differ and must not be applied across regions.

Further Reading

GB/T 50875-2013 Clause 2.2.17 (definition of the procurement and keeping fee); TB 10801-2024 Section 3.2 (material cost); TB/T 10813-2024 Clauses 1.0.2-1.0.5; TB 10811-2024 Table 2.2.2 and Clause 2.2.3; highway JTG 3830-2018 material procurement and keeping fee provisions.