Railway 2024 quota: distinguishing surveyed-price materials from base-period-price materials — the Appendix A computer-code test and the main-material list (TB 10811/10801/10813-2024)
The sole test for surveyed-price vs base-period-price materials: check whether the material's computer code falls within Table A.0.1 of Appendix A of TB 10811-2024 "Railway capital construction design estimate (budget) fee quota". Within = main material: compilation-period price is exclusive of deductible input VAT and determined by the design organization's investigation, with price difference = quota-tabulated consumption x (compilation-period price − base-period price) listed as material price difference (TB 10801-2024 clause 4.1.2 item 2 sub-item 2)); outside = auxiliary material: base-period price used directly (TB/T 10813-2024, 2020 price level, exclusive of deductible input VAT), no survey, no compilation-period difference. Special cases: petrol/diesel compilation-period differences go into the construction-plant-use price difference; water and electricity are not on the surveyed list — their difference is computed separately as consumption x (compilation-period price − base-period price) (base prices: water 0.55 yuan/t, electricity 0.0.47 yuan/kWh).
Applicable Codes
- TB 10811-2024 铁路基本建设工程设计概(预)算费用定额(第 2.2.2、2.2.3、2.2.4、2.2.5 条,App. A Table A.0.1)
- TB 10801-2024 铁路基本建设工程设计概(预)算编制办法(第 4.1.1、4.1.2 条)
- TB/T 10813-2024 铁路工程材料基期价格(第 1.0.2~1.0.6 条)
Topic Positioning
This card answers, under the railway 2024 pricing system, "which materials are priced at compilation-period surveyed prices, how surveyed-price and base-period-price materials are distinguished, and how computer codes map in budget software" — the test is the computer-code range of TB 10811-2024 Appendix A Table A.0.1, together with the main-material category list and price-difference calculation rules, for direct use by estimate (budget) compilers.
Core Conclusions
1. The sole test: whether the computer code falls within Appendix A. Per TB 10811-2024 "Norms for On-costs and Expenses for Railway Capital Construction Project Design Estimates (Budgets)", clause 2.2.3 item 1: base-period prices of main materials (computer codes in Appendix A) follow TB/T 10813 "Railway Works Material Base-period Prices", and the compilation-period price is exclusive of deductible input VAT and determined by survey and analysis by the design organization — i.e. "surveyed-price materials"; item 4: other materials (auxiliary materials) besides those above have budget prices that include all freight and handling charges and purchasing and custody charges, at base-period prices, without survey.
2. Surveyed-price (main) material category list (enumerated in clause 2.2.3 item 1; codes in Appendix A): cement, timber, steel, pipe, brick, tile, sand, stone, lime, planting soil, clay, bentonite, fly ash, slag powder, blocks, straw (reed) for wind-sand subgrade protection, sand-control netting, flowers/grass/seedlings, geosynthetics, steel fence mesh panels, active/passive protection nets, mesh reinforcement, rail, turnouts, sleepers, rail fastenings (for concrete sleepers), steel girders, steel pipe arches, stay cables, form travelers, bridge high-strength friction-grip (HSFG) bolts, foundation bolts, reinforced-concrete girders, railway bridge bearings, spherical hinges, bridge waterproofing membranes and coatings, precast reinforced-concrete piles, tunnel waterproof boards, explosives, poles, towers, masts, OCS masts, OCS wires, power wires, optical/copper cables, concrete troughs (slabs), stay anchors, guy anchors, OCS supports and fittings, grouted bolts, sound barriers, anchors, corrugated ducts, bridge expansion joints, iron fitments, joint bars, insulating joint bars, rubber pads, anchoring plates, rail expansion devices, welding consumables, concrete admixtures, waterstops, TBM (shield) cutters, stone slabs, sintered stone, decorative materials, transformers, instrument transformers, breakers, relays, signal mechanisms, lamp units, level-crossing signals, coding transmitters and cabinets/boxes, computer-based interlocking equipment, lightning-protection equipment, switch machines and mounting, switch outer locking, track-circuit outdoor equipment, disconnectors, petrol and diesel etc.
3. Appendix A Table A.0.1 computer-code ranges (key excerpts): cement 1070901-1079901; timber 1140001-1140605; steel 1010001-1010729, 1011379-1011743, 1012575-1012627, 1012705-1013199, 1013355, 1013381-1013719, 1220001-1220649, 1221233-1221377, 1290181-1291261, 1291621-1293241, 1293961-1296661, 2032201, 3048737; reinforced-concrete/ductile-iron/steel-plate/plastic pipe 1220673-1221225, 1224225-1224601, 1224617-1224841, 1225193-1225265, 1225857-1226273; sand 1080001-1080729; stone 1084785-1088633, 1089881; lime/planting soil/clay/bentonite 1090001, 1090371, 1097771-1098511, 1099251; fly ash/slag powder 1093331-1094071, 1094441; brick/tile/blocks 1260401, 1100001-1104621, 1108581, 1108801, 1110001, 1110431; flowers and seedlings 1260401-1267601; straw (reed) and sand-control netting 1039283, 1039402, 1260001. The full range is subject to the text of Table A.0.1 itself.
4. Pricing and price-difference mechanisms:
- Surveyed-price materials: base price per TB/T 10813-2024 (clause 1.0.3: 2020 price level, exclusive of deductible input VAT); compilation-period price determined by survey; material cost price difference = quota-tabulated consumption x (compilation-period price − base-period price), computed per TB 10801-2024 clause 4.1.2 item 2 sub-item 2), and included in the item estimate (budget).
- If the surveyed price does not include purchasing and custody charges, these must be charged on the surveyed price exclusive of deductible input VAT; if the surveyed price is the price at a designated delivery point (not the site), the out-of-price freight and handling charges for carriage from the designated delivery point to site must also be computed separately in the item estimate (clause 2.2.3 item 1).
- Petrol/diesel special case: the compilation-period price is likewise determined by survey, but "the difference between the compilation-period price and the base-period price is listed as a price adjustment and included in the price adjustment for plant and small tools cost" (clause 2.2.3 item 3) — because it is machine-shift fuel, it does not enter the material price adjustment.
- Water and electricity: not in the Appendix A list; their price difference "excludes water and electricity consumed by machine-shifts" and is computed as quota-tabulated consumption x (compilation-period price − base-period price) (clause 4.1.2 item 2 sub-item 1)); base prices: water 0.55 yuan/t (for pumping lift of 20 m and below only) and electricity 0.47 yuan/kWh (TB 10811-2024 clauses 2.2.4, 2.2.5).
- Auxiliary materials: base-period price used directly, no compilation-period price difference.
5. Computer codes in budget software: the computer code is the unified code identifying railway works materials in the "railway works material library" (TB/T 10813-2024 clause 1.0.6 item 1). In budget software, surveyed-price materials appear on two legs — "base price + material cost price difference"; checking a material's computer code against the Appendix A range tells whether a compilation-period surveyed-price adjustment must be booked.
Applicable Boundaries
- Applies only to railway works quotas and estimate/preliminary-estimate/budget compilation; not for highways, buildings or other sectors.
- Base-period prices are at the 2020 price level and exclusive of deductible input VAT; implementation-stage prices are market-determined (TB/T 10813-2024 clauses 1.0.2-1.0.3).
- Appendix A gives category code ranges; the specific codes of material entries follow the TB/T 10813 material library and the software material library — this card does not replace the full code table.
- Adjustment for price differentials means the reasonable adjustment of prices from the base period to the compilation period, computed by the design organization per TB 10801-2024 clause 4.1.1 and included in the item estimate; this card contains no project sample prices and does not serve project-specific price taking.
Further Reading
- TB 10811-2024 "Norms for On-costs and Expenses for Railway Capital Construction Project Design Estimates (Budgets)" clause 2.2.2 (purchasing and custody charge rate table: cement 3.78%, crushed stone (including ballast and medium/small pebbles) 3.45%, sand 4.47%, brick/tile/lime 4.98%, rail/turnouts/sleepers/steel girders etc. 1.10%, other materials 2.65%; the purchasing and custody charge rate in the same table also applies to out-of-price freight and handling charges), clause 2.2.3, clauses 2.2.4-2.2.5 (water and electricity price rules and formulas 2.2.5-1~3), Appendix A Table A.0.1.
- TB 10801-2024 "Measures for Compiling Design Estimates (Budgets) of Railway Capital Construction Projects" clauses 4.1.1-4.1.2 (methods of price adjustment for labour, materials and plant and small tools).
- TB/T 10813-2024 "Railway Works Material Base-period Prices" clauses 1.0.2-1.0.6 (A/B/C composition formulas and the computer-code definition).