Scope of the "delivered price" basis of published material price information: the mainstream basis includes the material price at source, freight and handling charges, transport wastage and purchasing and custody charges, but exceptions exist by region and category; read the notes of the current issue before use, and never count twice charges already included

The mainstream basis of published price information is the "delivered price" - it includes the material price at source, freight and handling charges, transport wastage and purchasing and custody charges (GB/T 50875-2013 defines the material unit price as the comprehensive average price formed from the source of the building material to the site warehouse up to issue from stock). But the basis is not uniform nationwide: Beijing Construction Cost Information states that steel members exclude freight and handling charges, which may be increased on the facts where transport conditions are constrained. The notes of the current issue must be read before use, and freight and handling charges or purchasing and custody charges already included must not be counted again in the rates.

Applicable Codes

  • GB/T 50875-2013 工程造价术语标准(第2.2.14、2.2.16条)
  • TB 10801-2024 铁路基本建设工程设计概(预)算编制办法(第3.2节)
  • TB 10811 铁路基本建设工程设计概(预)算费用定额
  • 《北京工程造价信息》总说明(北京市住建委官网):https://zjw.beijing.gov.cn/bjjs/resource/cms/article/10872402/10877886/2020102014490838433.pdf
  • 内蒙古自治区住建厅政策问答:https://zjt.nmg.gov.cn/hdjl/zcwdk/jdzq/wdzq/bzde/202310/t20231024_2398592.html
  • 海南省住建厅编制说明:http://zjt.hainan.gov.cn/szjt/dejgxx/202304/aa0440e2dcbe42eebb63a40f0ec85ad8/files/24ddd1b787174249958d089f4009f9eb.pdf

Topic Positioning

Determining whether published construction cost information (material market price information) adopts the "delivered price" basis - whether its composition includes the material price at source, freight and handling charges, transport wastage and purchasing and custody charges - together with the checking and no-double-counting rules when using it in rate build-up.

Core Conclusions

  1. Terminology level (standard scope): GB/T 50875-2013 "Standard for Construction Cost Terminology", clause 2.2.14 "material unit price": the comprehensive average price formed from the source of the building material to the site warehouse up to issue from stock. Clause 2.2.16 "material freight and handling charges": the charges incurred in transporting domestically procured materials from their source, or overseas-procured materials from the port of arrival, to the site warehouse or designated stockpiling place. That is, the material unit price / material (budget) price in the sense of the standard is itself a comprehensive price delivered to the site warehouse, not merely an ex-works price; the boundary of "delivered" = the site warehouse or designated stockpiling place.

  2. Railway system: TB 10801-2024 "Rules for Compiling Design Estimates and Budgets of Railway Capital Construction Works", clause 3.2.4: the norm-based material price consists of the material price at source, freight and handling charges included in the price, and purchasing and custody charges; clause 3.2.5: norm-based material price = (material price at source + freight and handling included in the price) x (1 + purchasing and custody percentage rate). Here the material price at source is the ex-works price or the price at the designated place of delivery; freight and handling included in the price covers the relevant charges incurred in transporting the material from its source (production plant or designated delivery place) to the site and carried in the material cost, including transport, loading and unloading and other relevant transport expenses; purchasing and custody charges are the charges incurred in procurement, supply and custody of materials (including procurement charges, warehousing charges, site custody charges, transport wastage and storage wastage), the percentage rate following TB 10811 "Quota of Expenses for Design Estimates and Budgets of Railway Capital Construction Works".

  3. Mainstream basis of published price information (delivered price): most regions publish material market price information computed as "material price = (material price at source + freight and handling charges) x (1 + transport wastage rate) x (1 + purchasing and custody percentage rate)", i.e. a delivered price including the price at source, freight and handling charges, transport wastage and purchasing and custody charges. Examples: the Inner Mongolia Autonomous Region housing and construction authority states in its policy Q&A that material market price information consists of the material price at source, freight and handling charges, transport wastage and purchasing and custody charges, and publishes on that formula; the Hainan provincial compilation notes adopt the same basis (the collected price at source is the month-settled transaction price, with a uniform purchasing and custody rate of 2%); material price information management provisions of some regions likewise record that the material price consists of the material price at source, freight and handling charges, transport wastage and purchasing and custody charges.

  4. Exceptions and divergences (not uniform nationwide): the general notes of Beijing Construction Cost Information (official website of the Beijing municipal housing and construction commission) state expressly: the tax-inclusive market information prices cover the tax-inclusive material (equipment) price at source, freight and handling charges, transport wastage and purchasing and custody charges, but steel members exclude freight and handling charges; the ex-tax market information prices follow the same basis (steel members excluding freight and handling); and the notes record that the prices are average market levels formed by regular large-volume centralized procurement, and where freight and handling charges increase substantially due to small procurement batches or constrained transport conditions, freight and handling and related charges should be increased according to the facts. A few regions publish price information on an ex-works / supply-price basis (excluding freight and handling or purchasing and custody charges, which must then be counted separately in the budget).

  5. Rules of use: where the published price information already includes freight and handling charges and purchasing and custody charges, they must not be counted again in rate build-up; where the contract agrees price adjustment per published price information, the basis (whether freight and handling etc. are included) should be stated to avoid settlement disputes. Before use, open the "general notes / compilation notes" of the local current issue of cost information, check item by item whether each of the four elements (price at source, freight and handling, transport wastage, purchasing and custody) is included and note the tax-inclusive / ex-tax basis, the exclusion clauses (e.g. steel members excluding freight and handling) and the "increase on the facts where transport is constrained" clause.

Applicability Boundaries

  • Applies to basis determination and rate build-up use of published price information / norm-based material prices of construction materials (equipment); railway works pricing follows the TB 10801-2024 / TB 10811 system, highway works the JTG 3830-2018 system (purchasing and custody charges counted additionally on the base of price at source plus freight and handling plus off-site transport wastage).
  • The boundary of "delivered" is the site warehouse or designated stockpiling place, and normally excludes on-site secondary handling and the like.
  • Publication bases, issues and exclusion clauses may change by region; conclusions follow the notes of the current local issue in use and must not be transplanted across regions.
  • This card is for basis determination and reaches no conclusion on the price figures of any specific material.