Engineering Knowledge Cards.
Confidence HighUpdated 2026-10-18

Four cost components of the material price (norm-based material price for estimating) and the step-by-step computation: the formula, the charging base of purchasing and custody, the double pass of transport wastage and the placement of inspection and testing costs

Material price (norm-based material price for estimating) = (material price at source + freight and handling) x (1 + transport wastage rate) x (1 + purchasing and custody rate); purchasing and custody charges take price at source + freight and handling + transport wastage, i.e. the wastage-inclusive source price and freight, as their base (wastage passes through both the wastage and custody stages - the sanctioned basis, not double counting), and the two rates must not simply be added; at 2% wastage and 3% custody the combined factor is 1.02 x 1.03 = 1.0506 (simple addition gives 1.05, about 0.06% short). The material price contains only four items - source price, freight and handling, transport wastage, purchasing and custody; inspection and testing costs of the contractor's ordinary verification sit in overheads, not in the material price. The railway basis differs: transport wastage merges into purchasing and custody, the formula being (source price + freight included in price) x (1 + custody rate), with no separate wastage multiplier.

Applicable Codes

  • 材料价格信息管理办法 第九条、第十条(材料价格四项构成与计算公式)
  • 湖北省建筑安装工程费用定额(2024)材料费内容
  • 陕西省建设工程费用规则(2025)材料费内容
  • JTG 3830-2018 公路工程建设项目概算预算编制办法(材料采购及保管费)
  • TB 10801-2024 铁路基本建设工程设计概(预)算编制办法 第3.2.4、3.2.5、3.9.2条
  • TB 10811 铁路基本建设工程设计概(预)算费用定额
  • T/SZCA 5-2022 洁净工程项目定额 总则 0.1.14

Positioning

The rate composition and step-by-step computation of the material price (norm-based material price for estimating) - given source price and freight, how to apply the transport wastage rate and the purchasing and custody rate; the charging base of purchasing and custody; the double pass of transport wastage; and why inspection and testing costs stay out of the material price. For material cost build-up and review in estimates and budgets.

Core conclusions

1. Four components and the formula (original text) The Material Price Information Administrative Measures: "Article 9 - the material price consists of the material price at source, freight and handling, transport wastage and purchasing and custody"; "Article 10 - the material price is computed as: material price = (source price + freight and handling) x (1 + transport wastage rate) x (1 + purchasing and custody rate)".

Definitions (per provincial fee norms and the cost engineer textbook):

  1. Price at source (supply price): the ex-works price or the merchant's supply price; for imported materials, per the relevant rules.
  2. Freight and handling: all costs of moving the material from its origin to the site store or designated stockpile (transport, loading/unloading and related carriage costs).
  3. Transport wastage: unavoidable loss in transport and handling.
  4. Purchasing and custody: all costs of organising purchase, supply and custody - purchase, warehousing, site custody and storage loss.

2. Step order (must not be inverted) Step 1 wastage base = source price + freight and handling; Step 2 transport wastage = wastage base x wastage rate; Step 3 custody base = wastage base x (1 + wastage rate) = source price + freight + wastage; Step 4 purchasing and custody = step 3 x custody rate; Step 5 material price = step 3 x (1 + custody rate).

So the custody base is not "source price + freight" but the wastage-inclusive sum - wastage legitimately enters both stages; it is not double counting. The highway rule confirms it: "purchasing and custody is computed on the sum of the material's source price plus freight and handling plus off-site transport wastage, times the custody rate" (JTG 3830-2018).

3. Worked rates (P = source price + freight) At 2% wastage and 3% custody: wastage = 0.02P; custody base = 1.02P; custody = 1.02P x 3% = 0.0306P; material price = 1.02P x 1.03 = 1.0506P - a combined uplift of 5.06%. Common error: adding the rates to (1 + 2% + 3%) = 1.05, about 0.06% short of 1.0506; the product equals 1.03 x 1.02 either way, but describing the 3% base as "source price + freight" is wrong in basis and gets marked down in review.

4. Where inspection and testing costs go The material price holds only the four items above. The railway compilation rules, clause 3.9.2 item 1 sub 6), place "inspection and testing costs" under overheads within on-costs: "costs of the contractor's ordinary verification and checking of equipment, materials, members and buildings per the codes and acceptance standards, including materials and chemicals consumed by its own laboratory and, where needed, outsourced tests commissioned by the contractor. Excludes tests on new structures and new materials funded by research and trial funds and the science-and-technology three items; excludes tests the employer requires on materials holding ex-works certificates, destructive member tests and other special examinations; excludes tests outsourced by the employer; excludes tests beyond the acceptance standards required by the design." I.e. ordinary verification goes to overheads; new-structure and employer-required / outsourced tests are handled separately - none enter the material price.

Applicable boundaries

  1. The formula covers the case "source price and freight known"; if the price taken is already delivered-to-site (freight included), do not add freight again; ex-works prices need freight added.
  2. Industry bases differ and must not be mixed: railway TB 10801-2024 clause 3.2.4 - "the norm-based material price consists of source price, freight included in price, and purchasing and custody"; clause 3.2.5 - "price = (source price + included freight) x (1 + custody rate)", custody already covering transport and storage wastage - no separate wastage multiplier; copying this card's four-factor chain onto railway works overstates wastage.
  3. Highway JTG 3830-2018 bands custody by material class (steel 0.75%, fuel and blasting materials 3.26%, other materials 2.06%, bought-in components and semi-finished products 0.42%), with ready-mixed cement concrete, asphalt mixes and stabilised-soil mixes exempt.
  4. Exceptions exist: the clean-room works quota (T/SZCA 5-2022) places "the contractor's inspection and testing costs" inside the material price (ex-storehouse price) - check the applicable quota; this card's conclusion is not universal.
  5. The material price excludes deductible input VAT; rates and bases must pair with the governing fee norm and the current price-release notes.

Further reading

  • Material Price Information Administrative Measures, Articles 9 (components) and 10 (formula) and the definitions therein.
  • Item-by-item definitions: Hubei construction and installation fee norms (2024), material cost items 1-4; Shaanxi construction cost rules (2025), items 1-4.
  • Custody base "source + freight + off-site wastage" and banded rates: JTG 3830-2018 material cost provisions.
  • Railway basis: TB 10801-2024 clauses 3.2.4 and 3.2.5; custody rates in TB 10811.
  • Inspection and testing in overheads: TB 10801-2024 clause 3.9.2 item 1 sub 6).
  • The clean-room exception: T/SZCA 5-2022 general provisions clause 0.1.14.