Bases, procedure, and content elements for preparing construction material procurement plans (GB/T 50430-2017, GB/T 50326-2017)

Procurement plans are prepared on the bases of the design documents, current national standards, and the construction contract, following the four-step flow "demand plan → inventory offsetting → procurement plan → approval and implementation"; the content must include five elements: work scope, procurement information, inspection methods, supplier qualification review, and control targets; total material quantities are allocated per the master construction schedule (GB/T 50502-2009, Clause 4.4.5), delivering materials on demand with rolling adjustment as progress advances.

Applicable Codes

  • GB/T 50430-2017 第8.2.1条
  • GB/T 50326-2017 第6.2.1条
  • GB/T 50502-2009 第4.4.5条
  • GB 51114-2015 第9.2.1条
  • DB11/T 382-2017 第4.3.1条

Topic Positioning

How to prepare procurement plans for construction materials, components, and equipment: on which documents they are based, what procedure they follow, and what elements they must contain. Based on GB/T 50430-2017, Code for Quality Management of Construction Enterprises; GB/T 50326-2017, Code for Construction Project Management; and GB/T 50502-2009, Code for Project Execution Plan of Building Engineering.

Core Conclusions

Preparation bases: the design documents, current national standards, and the construction contract (GB/T 50430-2017, Clause 8.2.1), linked with the project execution plan's material allocation plan, the project initiation report, the project management implementation plan, and the procurement management system. Four-step procedure: ① decompose demand by work item per the construction schedule and prepare the procurement demand plan first — GB/T 50326 explicitly requires obtaining the demand plan before preparing the procurement plan; ② deduct existing inventory, in-transit, and transferable resources from demand to get net procurement quantities; ③ finalize the procurement plan specifying the procurement method, categories, specifications, models, quantities, delivery times, technical performance, and quality standards; ④ approve per the system's authority and procedure, then implement. Five content elements (GB/T 50326-2017, Clause 6.2.1): procurement work scope, content, and management standards; procurement information (quantities, technical standards, quality specifications); inspection methods and standards; supplier qualification review requirements; procurement control targets and measures. Material allocation plan (GB/T 50502-2009, Clause 4.4.5): determine the total planned quantities and entry/exit times of principal materials and equipment per the master construction schedule, ensuring continuous construction while controlling capital occupation.

Applicable Boundaries

Applies to preparation and approval management of procurement plans at the construction enterprise's project level. Plans may be subdivided into demand, supply, requisition, and procurement plans, each with defined categories, content, and timing requirements. For materials affecting structural safety and important service functions, review the supplier's product quality assurance capability before procurement, with on-site inspection when necessary (DB11/T 382-2017, Clause 4.3.1 — the supervisor likewise reviews this plan). Plans must be revised on a rolling basis with construction progress, not written once and left alone.

Further Reading

GB/T 50430-2017 Clause 8.2.1 (procurement plan preparation and approval); GB/T 50326-2017 Clause 6.2.1 (five content elements, supplier definition); GB/T 50502-2009 Clause 4.4.5 (material allocation plan); GB 51114-2015, Code for Project Execution Plan of Open-pit Coal Mines, Clause 9.2.1 (demand totals and annual procurement/supply plans per schedule); DB11/T 382-2017, Beijing Specification for Construction Project Supervision, Clause 4.3.1.