Determining machinery and equipment allocation in construction method statements: type selection → reverse-calculation of machine count → mobilisation timing

Machinery and equipment allocation forms part of the resource-allocation plan of a construction method statement (GB/T 50502-2009 Clause 6.4.2): first select types by matching the work content, design documents, geology and hydrology, site surroundings, safety requirements, and techno-economic comparison (including green construction); then reverse-calculate the machine count by N = Q ÷ (P × T × B) (quantity ÷ machine-shift output quota × planned duration × shifts per day), rounding up; finally arrange mobilisation timing per the programme (reserving time for erection and commissioning and for passing inspection), state the source (own/rental/subcontractor), and output the machinery and equipment allocation plan table.

Applicable Codes

  • GB/T 50502-2009 建筑施工组织设计规范
  • GB 51114-2015 露天煤矿施工组织设计规范
  • GB/T 51111-2015 露天金属矿施工组织设计规范
  • GB/T 51310-2018 地下铁道工程施工标准

Topic Positioning

The method for compiling the "machinery and equipment allocation plan" within a construction method statement (and the project execution plan (construction methodology and site organization)), addressing three questions: which machines to select, how many to deploy, and when they mobilise to site.

Core Conclusions

Machinery and equipment allocation is part of the material resource-allocation plan within the resource-allocation plan (GB/T 50502-2009 Clause 6.4.2), determined in three steps: ① Type selection: machinery must match the construction content (insufficient capacity means the task cannot be completed or efficiency drops; excessive capacity is wasteful), and is constrained by design-document requirements (e.g., pile type, pile length and pile diameter determine the type of piling machinery), geological and hydrological conditions, the site and its surroundings (capability for constructing edge piles), and safe-use requirements; similar machines are compared on a techno-economic basis and the best chosen, with preference for equipment of low energy consumption and low noise. ② Quantification: reverse-calculate the machine count from the quantities of work and the quota norms, N = Q ÷ (P × T × B) — Q is the quantity of work of the construction section (unit of measurement consistent with the quota norms), P is the machine-shift output quota (m³/machine-shift, t/machine-shift, etc.), T is the planned duration of that machine's operation (days), and B is the number of shifts per day; round the result up, or adjust it by extending the duration or adding shifts (the formula derives from GB 51114-2015 Clause 8.2.12 and shares the same origin as the reverse-calculation of labour headcount). ③ Timing and source: equipment types, quantities and mobilisation times are determined per the general programme of works and the quantities of work at each stage; mobilisation should reserve time for erection and commissioning, and machines may be used only after passing inspection, testing, erection, commissioning and appraisal; sources may be the contractor's own equipment, external rental, or equipment provided by a subcontractor, with economy pursued on the premise of meeting the programme. The final deliverable is the machinery and equipment allocation plan table (name, specification/model, quantity, source, mobilisation/demobilisation times, corresponding construction stage, and key technical parameters).

Applicable Boundaries

Applies as the general method for machinery allocation in construction method statements for building, municipal, mining, metro and other works; the machine-shift output quota must be taken from current quota norms or the contractor's in-house norms, and regional price data must not be substituted; special method statements for sub-divisional works involving significant hazards must list material and equipment plans in the construction programme per Jianban Zhi [2021] No. 48; the selection of large machinery should preferably be verified against the calculation book of the special method statement.

Further Reading

GB/T 50502-2009 Clause 6.4.2 (resource-allocation plan of construction method statements) and Clause 5.4.2 (resource-allocation plan of unit works); GB 51114-2015 Clause 8.2.12 (programme compilation steps and the machine-shift reverse-calculation formula); GB/T 51111-2015 Clause 6.4.1 (allocation by specialty, trade and batch); GB/T 51310-2018 Clause 4.7.1 (allocation by stage and specialty trade); JGJ 33-2012 "Technical safety code for the use of building machinery" (type selection and safe-use requirements).